Civil Junior Engineer: Estimating, Costing and Valuation of Buildings and Works

Every civil work begins as a number: how much earth, brick, concrete and steel, at what rate, and what the finished property is worth. The civil Junior Engineer list names fundamentals of estimating, cost estimates for works, rate analysis, valuation and detailed estimates. This chapter teaches the measurement rules, the centre-line method, the anatomy of a rate, the weight of reinforcement and the three valuation tools, each with a worked calculation. Rates in the examples are invented round figures, not any department's schedule.
Overview

1. Kinds of estimate and the rules of measurement

1 min read

An approximate (preliminary) estimate gives a quick idea of cost before drawings exist. The plinth-area method multiplies the built-up area by a rate per square metre: 120 m² at ₹18,000 per m² is ₹21.6 lakh. The cubic-content method multiplies volume by a rate and the unit-base method multiplies a count (beds, seats, kilometres of road) by a cost per unit. A detailed estimate is built from quantities of every item taken from the drawings, multiplied by item rates, and summed in an abstract of cost; it is the basis of the tender. Measurement follows a standard code (IS 1200 in India), which fixes the unit and the deductions: earthwork, brickwork, concrete and masonry in cubic metres, plaster, flooring and paint in square metres, pipes and skirting in running metres, and reinforcement in kilograms or quintals.

ItemUnitDeduct or note
Earthwork in excavationm³Length × width × depth; add working space and slope if specified
Brickworkm³Deduct door, window openings; small openings below a set size are ignored
Plasterm²Measure on each face; deduct large openings
RCCm³ (concrete), kg (steel)Concrete and reinforcement measured separately
Formwork (shuttering)m²Area of surface in contact with concrete

An approximate (preliminary) estimate gives a quick idea of cost before drawings exist. The plinth-area method multiplies the built-up area by a rate per square metre: 120 m² at ₹18,000 per…

2. Quantities by the centre-line method

1 min read · 1 part

For a building with closed rectangular walls the centre-line method finds the total length of all walls along their centres and multiplies once by the wall section, which avoids the corner overlap that the long-wall and short-wall method corrects separately. A single room of 5 m × 4 m clear inside, with 0.3 m walls, has a centre rectangle of 5.3 m × 4.3 m, so the centre-line length is 2 × (5.3 + 4.3) = 19.2 m. For a wall 3 m high, the gross brickwork is 19.2 × 0.3 × 3 = 17.28 m³. A door of 1.0 m × 2.1 m in a 0.3 m wall removes 1.0 × 2.1 × 0.3 = 0.63 m³, leaving 16.65 m³. The trench for a footing 0.9 m wide and 1.0 m deep along the same centre line is 19.2 × 0.9 × 1.0 = 17.28 m³ of excavation.

⚠️ Where the centre-line method needs a correction
When walls have different thicknesses or footings of different widths, the centre-line length must be taken wall by wall and a cross wall that joins the main walls adds a length equal to its clear length (not the centre-to-centre length). Using one wall thickness for everything is the usual slip.

For a building with closed rectangular walls the centre-line method finds the total length of all walls along their centres and multiplies once by the wall section, which avoids the corner…

3. Rate analysis, RCC quantities and reinforcement

1 min read

The rate of an item is built from materials, labour, tools and plant, then a margin for overheads and contractor's profit. For 10 m³ of brickwork with 500 bricks per m³ at ₹8 a brick, mortar at ₹2,400 per m³ of work and labour at ₹600 per m³, the direct cost is 10 × 500 × 8 + 10 × 2,400 + 10 × 600 = ₹70,000; adding 20 percent for overheads and profit (departments adopt their own percentages) gives ₹84,000, or ₹8,400 per m³. A rate analysis therefore moves from the unit of work to quantities of each input, and an error in the unit (a brick count per m³ applied to m²) is the commonest slip.

For RCC, concrete is measured as volume and steel separately, since steel is paid by weight. The weight of a round bar per metre is d² ÷ 162 kg with d in mm: a 16 mm bar weighs 256 ÷ 162 = 1.58 kg/m and a 12 mm bar 0.89 kg/m. As a rule of thumb, steel at 1 percent of the concrete volume weighs 0.01 × 7,850 = 78.5 kg per m³ of concrete (steel density 7,850 kg/m³). Bar bending schedules list each bar's diameter, shape, cutting length, number and weight; bends reduce the cutting length (commonly 1d at a 45° bend and 2d at a 90° bend) and hooks add to it.

The rate of an item is built from materials, labour, tools and plant, then a margin for overheads and contractor's profit. For 10 m³ of brickwork with 500 bricks per m³ at ₹8 a brick…

4. Valuation: depreciation, sinking fund and capitalised value

1 min read · 1 part

Valuation estimates the worth of a property for sale, mortgage, rent fixation or acquisition. Market value is what a willing buyer would pay; book value is cost less accumulated depreciation; scrap value is the worth of the materials at the end of life. Under straight-line depreciation the yearly charge is (cost − scrap) ÷ life: a building costing ₹8,00,000 with 10 percent scrap value and a 60-year life loses (8,00,000 − 80,000) ÷ 60 = ₹12,000 a year. A sinking fund puts aside a fixed instalment each year at compound interest to rebuild the asset: to accumulate ₹1,00,000 in 10 years at 5 percent the instalment is S i ÷ ((1 + i)ⁿ − 1) = 1,00,000 × 0.05 ÷ (1.05¹⁰ − 1) ≈ ₹7,950.

For an income-producing property the capitalised value is net annual income × years' purchase (YP), where YP = 100 ÷ rate of return in percent. Net income is gross rent less outgoings (repairs, taxes, management, insurance). With gross rent ₹60,000 a year and outgoings 25 percent, the net income is ₹45,000; at a 6 percent return YP = 16.67 and the value is 45,000 × 16.67 = ₹7,50,000, which is the same as 45,000 ÷ 0.06. A lower expected return raises YP and the value; taking gross rent instead of net income overstates it.

MethodFormulaWorked figure
Straight-line depreciation(C − S) ÷ n₹12,000 a year
Sinking fund instalmentS i ÷ ((1 + i)ⁿ − 1)₹7,950 for ₹1,00,000 in 10 years at 5%
Capitalised valueNet income × YP₹7,50,000

Valuation estimates the worth of a property for sale, mortgage, rent fixation or acquisition. Market value is what a willing buyer would pay; book value is cost less accumulated…

5. Worked problems: deductions, brick count and the sinking fund

1 min read · 1 part

Quantity take-off always follows the same order: gross quantity first, then deductions for openings, then the net quantity that is paid for. Consider a brick wall 10 m long, 3 m high and 0.2 m thick. Its gross volume is 10 × 3 × 0.2 = 6.0 m³. A door opening 1 m wide and 2 m high deducts 1 × 2 × 0.2 = 0.4 m³, leaving 5.6 m³. Modular brickwork of 20 × 10 × 10 cm bricks (nominal size, mortar included) takes 1 ÷ (0.2 × 0.1 × 0.1) = 500 bricks per cubic metre, so the wall needs 5.6 × 500 = 2,800 bricks, before wastage.

ItemFormulaWorked value
Straight-line depreciation(Cost − salvage) ÷ life(₹5,00,000 − ₹50,000) ÷ 30 = ₹15,000 a year
Sinking-fund instalmentA = i S ÷ [(1 + i)ⁿ − 1]₹1,00,000 in 5 years at 8% needs ₹17,046 a year
Centre-line length of a room2 × (centre length + centre breadth)Rooms 5 m × 4 m between centres give 18 m
Trench volumeCentre-line length × width × depth36 m × 0.6 m × 0.9 m = 19.44 m³

For the sinking fund the factor (1.08)⁵ = 1.4693, so A = 1,00,000 × 0.08 ÷ 0.4693 = ₹17,046. Paid at the end of each of the five years and earning 8%, the instalments grow to exactly ₹1,00,000, which is a good check.

⚠️ Deduct openings once, and from the right items
Openings are deducted from the masonry or plaster that they interrupt, using the thickness of that item. A door deducted from brickwork uses the wall thickness; the same door deducted from plastering uses the plastered area on each face.

Quantity take-off always follows the same order: gross quantity first, then deductions for openings, then the net quantity that is paid for. Consider a brick wall 10 m long, 3 m high and…

Second Pass: Trench Volume, Plaster Area, Cement for Concrete, Bar Weight and Wastage

1 min read · 2 parts

Quantities come from simple geometry with deductions for openings. Dry volume of concrete is about 1.54 times the wet volume, and a 1 : 2 : 4 mix divides it into seven parts. One cubic metre of cement is 28.8 bags of 50 kg. The weight of a steel bar in kg per metre is d²/162 with d in mm. Bricks are ordered with an allowance of about 5% for breakage.

Worked values
ItemWorkingAnswer
Trench 10 m × 1 m × 1.5 m10 × 1 × 1.515 m³
Room 4 × 3 × 3 m, door 1 × 2, window 1 × 12(4 + 3) × 3 − 339 m²
Cement for 1 m³ of 1 : 2 : 41.54/7 × 28.8≈ 6.3 bags
12 mm bar12²/1620.89 kg/m
🧠 Cement bags for a cubic metre
For 1 m³ of 1 : 2 : 4 concrete the dry volume is 1.54 m³, of which cement is 1/7 = 0.22 m³. Since 1 m³ of cement is 28.8 bags, the quantity is 0.22 × 28.8 = 6.3 bags (about 316 kg).

Quantities come from simple geometry with deductions for openings. Dry volume of concrete is about 1.54 times the wet volume, and a 1 : 2 : 4 mix divides it into seven parts. One cubic…

Key takeaways

  • Approximate estimates use plinth area, cubic content or a unit base; a detailed estimate builds item quantities from drawings and ends in an abstract of cost.
  • In the centre-line method the total centre length times the wall section gives the brickwork; deduct openings afterwards.
  • A rate is materials plus labour plus tools and plant, then overheads and profit; check the unit before multiplying.
  • Weight of a round bar is d² ÷ 162 kg per metre, and steel at 1% of concrete volume is 78.5 kg per m³.
  • Straight-line depreciation is (cost − scrap) ÷ life; the sinking-fund instalment is S i ÷ ((1 + i)ⁿ − 1).
  • Capitalised value is net income times years' purchase, with YP = 100 ÷ rate in percent; use net, not gross, income.
  • Net quantity = gross − openings; modular brickwork takes 500 bricks per m³; sinking-fund instalment A = iS ÷ [(1 + i)ⁿ − 1].

Practice questions (25)

Attempt each one before opening the answer. Every explanation names the tempting wrong option as well as the right one, because that is where marks are lost.

  1. A plinth-area estimate for a 120 m² building at ₹18,000 per m² is:

    1. ₹216 lakh
    2. ₹21.6 lakh
    3. ₹2.16 lakh
    4. ₹15 lakh
    Show answer

    Answer: B — ₹21.6 lakh

    120 × 18,000 = 21,60,000, which is ₹21.6 lakh. A slipped decimal gives the other figures.
  2. In IS 1200 measurement, brickwork is measured in:

    1. Running metres
    2. Kilograms
    3. Cubic metres
    4. Square metres
    Show answer

    Answer: C — Cubic metres

    Masonry is a volume and is paid in cubic metres; plaster is in square metres.
  3. A room 5 m × 4 m clear inside has 0.3 m thick walls. Its centre-line length is:

    1. 18 m
    2. 20.4 m
    3. 9.6 m
    4. 19.2 m
    Show answer

    Answer: D — 19.2 m

    The centre rectangle is 5.3 × 4.3, so 2 × (5.3 + 4.3) = 19.2 m. Using the clear dimensions gives 18 m.
Show the other 22 questions
  1. Gross brickwork for a centre-line length of 19.2 m, wall thickness 0.3 m and height 3 m is:

    1. 17.28 m³
    2. 5.76 m³
    3. 57.6 m³
    4. 1.73 m³
    Show answer

    Answer: A — 17.28 m³

    Volume = 19.2 × 0.3 × 3 = 17.28 m³. Leaving out the thickness gives an area, 57.6 m².
  2. The weight per metre of a 16 mm diameter steel bar is about:

    1. 4.0 kg
    2. 1.58 kg
    3. 2.56 kg
    4. 0.99 kg
    Show answer

    Answer: B — 1.58 kg

    Weight = d² ÷ 162 = 256 ÷ 162 = 1.58 kg/m. Taking d ÷ 10 or d²/100 gives the other figures.
  3. Direct cost of 10 m³ brickwork is ₹70,000. Adding 20% for overheads and profit, the rate per m³ is:

    1. ₹84,000
    2. ₹8,000
    3. ₹8,400
    4. ₹7,000
    Show answer

    Answer: C — ₹8,400

    70,000 × 1.2 = 84,000 for 10 m³, so ₹8,400 per m³. ₹84,000 forgets to divide by the quantity.
  4. Straight-line depreciation: cost ₹8,00,000, scrap value 10% of cost, life 60 years. The yearly depreciation is:

    1. ₹13,333
    2. ₹1,333
    3. ₹8,000
    4. ₹12,000
    Show answer

    Answer: D — ₹12,000

    (8,00,000 − 80,000) ÷ 60 = 12,000. Ignoring the scrap value gives 13,333.
  5. Years' purchase at a 5% rate of return is:

    1. 20
    2. 5
    3. 0.05
    4. 15
    Show answer

    Answer: A — 20

    YP = 100 ÷ 5 = 20. A lower rate gives a larger YP.
  6. A property has gross rent ₹60,000 a year, outgoings 25% of it, and a 6% return is expected. Its capitalised value is:

    1. ₹4,50,000
    2. ₹7,50,000
    3. ₹10,00,000
    4. ₹9,00,000
    Show answer

    Answer: B — ₹7,50,000

    Net income = 60,000 × 0.75 = 45,000; value = 45,000 ÷ 0.06 = 7,50,000. Using gross rent gives 10,00,000.
  7. Steel at 1% of the volume of concrete weighs, per m³ of concrete, about (steel density 7,850 kg/m³):

    1. 785 kg
    2. 1 kg
    3. 78.5 kg
    4. 7.85 kg
    Show answer

    Answer: C — 78.5 kg

    0.01 × 7,850 = 78.5 kg. A slipped factor of ten gives 7.85 or 785.
  8. A brick wall is 10 m long, 3 m high and 0.2 m thick and has one door opening 1 m wide and 2 m high. Using 500 modular bricks per cubic metre, the number of bricks needed (without wastage) is:

    1. 2,800
    2. 3,000
    3. 2,600
    4. 3,200
    Show answer

    Answer: A — 2,800

    Gross volume 10 × 3 × 0.2 = 6.0 m³, less the opening 1 × 2 × 0.2 = 0.4 m³, gives 5.6 m³, and 5.6 × 500 = 2,800. Using the gross volume gives 3,000, the common slip.
  9. A sum of ₹1,00,000 is needed at the end of 5 years. Equal instalments are paid at the end of each year into a sinking fund earning 8% a year. Taking (1.08)⁵ = 1.4693, each instalment is nearest to:

    1. ₹17,046
    2. ₹20,000
    3. ₹14,693
    4. ₹18,400
    Show answer

    Answer: A — ₹17,046

    A = iS ÷ [(1 + i)ⁿ − 1] = 8,000 ÷ 0.4693 = ₹17,046. Dividing 1,00,000 by 5 gives ₹20,000 and ignores the interest earned.
  10. A trench is 10 m long, 1 m wide and 1.5 m deep. The volume of earth to be excavated is:

    1. 15 m³
    2. 10 m³
    3. 25 m³
    4. 1.5 m³
    Show answer

    Answer: A — 15 m³

    Volume = length × width × depth = 10 × 1 × 1.5 = 15 m³. Estimating excavation is measured in cubic metres.
  11. A room is 4 m × 3 m inside with a height of 3 m, one door of 1 m × 2 m and one window of 1 m × 1 m. The area of internal plastering on the walls is:

    1. 39 m²
    2. 42 m²
    3. 36 m²
    4. 45 m²
    Show answer

    Answer: A — 39 m²

    Wall area = 2(4 + 3) × 3 = 42 m², and deducting the openings 2 + 1 = 3 m² leaves 39 m². The 42 m² forgets the deductions.
  12. The quantity of cement in 1 m³ of 1 : 2 : 4 concrete, taking the dry volume as 1.54 m³ and 1 m³ of cement as 28.8 bags, is nearest to:

    1. 6.3 bags
    2. 1.54 bags
    3. 28.8 bags
    4. 12 bags
    Show answer

    Answer: A — 6.3 bags

    Cement is 1/7 of 1.54 = 0.22 m³, and 0.22 × 28.8 = 6.3 bags. The 28.8 is the bags in a whole cubic metre of cement.
  13. The weight of a 12 mm diameter steel bar per metre length, by the formula d²/162, is nearest to:

    1. 0.89 kg
    2. 0.12 kg
    3. 1.6 kg
    4. 8.9 kg
    Show answer

    Answer: A — 0.89 kg

    W = 12²/162 = 144/162 = 0.89 kg/m, consistent with the density of steel 7,850 kg/m³ and area 113 mm². The 16 mm bar weighs 1.58 kg/m.
  14. A building yields a net annual income of ₹45,000 and the capitalisation rate is 5%. Its capitalised value is:

    1. ₹9,00,000
    2. ₹2,25,000
    3. ₹4,50,000
    4. ₹90,000
    Show answer

    Answer: A — ₹9,00,000

    Capitalised value = net income × years' purchase = 45,000 × 20 = ₹9,00,000, since YP = 100/5 = 20. The ₹2,25,000 multiplies by the rate instead.
  15. A machine costing ₹1,00,000 is depreciated at 10% a year by the declining-balance (written-down value) method. Its book value after two years is:

    1. ₹81,000
    2. ₹80,000
    3. ₹90,000
    4. ₹82,000
    Show answer

    Answer: A — ₹81,000

    After year 1 the value is 90,000 and after year 2 it is 90,000 × 0.9 = 81,000. The ₹80,000 is the straight-line value.
  16. A wall requires 5 m³ of brickwork at 500 bricks per cubic metre. Allowing 5% for breakage, the number of bricks to be ordered is:

    1. 2,625
    2. 2,500
    3. 2,375
    4. 2,750
    Show answer

    Answer: A — 2,625

    Net bricks = 5 × 500 = 2,500, and adding 5% (125) gives 2,625. The 2,500 omits the breakage allowance.
  17. The plinth-area estimate of a 150 m² building at ₹16,000 per m² is:

    1. ₹240 lakh
    2. ₹10.7 lakh
    3. ₹2.4 lakh
    4. ₹24 lakh
    Show answer

    Answer: D — ₹24 lakh

    150 × 16,000 = ₹24,00,000 = ₹24 lakh. Check: 15 × 16,000 = 2.4 lakh, times 10. Misplacing a zero gives ₹2.4 lakh.
  18. The weight per metre of a 20 mm diameter steel bar, by the formula d²/162, is about:

    1. 3.95 kg
    2. 2.47 kg
    3. 0.99 kg
    4. 1.58 kg
    Show answer

    Answer: B — 2.47 kg

    W = d² ÷ 162 = 400 ÷ 162 = 2.47 kg/m. The 1.58 kg belongs to a 16 mm bar (256 ÷ 162), the tempting neighbouring size.
  19. The cross-sectional areas of an embankment at two sections 30 m apart are 12 m² and 18 m². By the mean sectional area method the volume between them is:

    1. 540 m³
    2. 450 m³
    3. 900 m³
    4. 360 m³
    Show answer

    Answer: B — 450 m³

    Volume = length × (A₁ + A₂) ÷ 2 = 30 × 15 = 450 m³. Using only one end area (360 or 540) is the tempting slip, and 900 forgets to halve the sum.
  20. A building costs ₹5,00,000, has a life of 10 years and a scrap value of ₹50,000. Using straight-line depreciation, its book value after 3 years is:

    1. ₹3,65,000
    2. ₹4,50,000
    3. ₹3,50,000
    4. ₹3,00,000
    Show answer

    Answer: A — ₹3,65,000

    Annual depreciation = (5,00,000 − 50,000) ÷ 10 = ₹45,000, so after 3 years it is 1,35,000 and the book value is 5,00,000 − 1,35,000 = ₹3,65,000. Using 10% of the full cost gives the tempting ₹3,50,000.
  21. A bill of quantities (BOQ) is a document that:

    1. Lists the items of work with their quantities, units and rates
    2. Gives only the total cost without detail
    3. Records the attendance of workers
    4. Is a drawing of the building plan
    Show answer

    Answer: A — Lists the items of work with their quantities, units and rates

    The BOQ itemises the work, with quantity and rate for each item, and is the basis for tenders and bills. A lump-sum total hides this detail, the tempting wrong choice.
  22. Assertion (A): The centre-line method gives the quantity of walls of a building correctly without separate deduction at junctions.
    Reason (R): The overlap of walls at corners and junctions is automatically accounted for in the centre-line length.
    Which one of the following is correct?

    1. Both A and R are true, and R is the correct explanation of A
    2. Both A and R are true, but R is not the correct explanation of A
    3. A is true, but R is false
    4. A is false, but R is true
    Show answer

    Answer: A — Both A and R are true, and R is the correct explanation of A

    In the centre-line length the corner overlaps are balanced out, so the quantity comes right, and R explains A. Adding the outer lengths without correction would over-measure, the tempting method.