Civil Junior Engineer: Estimating, Costing and Valuation of Buildings and Works
2. Quantities by the centre-line method
For a building with closed rectangular walls the centre-line method finds the total length of all walls along their centres and multiplies once by the wall section, which avoids the corner overlap that the long-wall and short-wall method corrects separately. A single room of 5 m × 4 m clear inside, with 0.3 m walls, has a centre rectangle of 5.3 m × 4.3 m, so the centre-line length is 2 × (5.3 + 4.3) = 19.2 m. For a wall 3 m high, the gross brickwork is 19.2 × 0.3 × 3 = 17.28 m³. A door of 1.0 m × 2.1 m in a 0.3 m wall removes 1.0 × 2.1 × 0.3 = 0.63 m³, leaving 16.65 m³. The trench for a footing 0.9 m wide and 1.0 m deep along the same centre line is 19.2 × 0.9 × 1.0 = 17.28 m³ of excavation.
For a building with closed rectangular walls the centre-line method finds the total length of all walls along their centres and multiplies once by the wall section, which avoids the corner…
3. Rate analysis, RCC quantities and reinforcement
The rate of an item is built from materials, labour, tools and plant, then a margin for overheads and contractor's profit. For 10 m³ of brickwork with 500 bricks per m³ at ₹8 a brick, mortar at ₹2,400 per m³ of work and labour at ₹600 per m³, the direct cost is 10 × 500 × 8 + 10 × 2,400 + 10 × 600 = ₹70,000; adding 20 percent for overheads and profit (departments adopt their own percentages) gives ₹84,000, or ₹8,400 per m³. A rate analysis therefore moves from the unit of work to quantities of each input, and an error in the unit (a brick count per m³ applied to m²) is the commonest slip.
For RCC, concrete is measured as volume and steel separately, since steel is paid by weight. The weight of a round bar per metre is d² ÷ 162 kg with d in mm: a 16 mm bar weighs 256 ÷ 162 = 1.58 kg/m and a 12 mm bar 0.89 kg/m. As a rule of thumb, steel at 1 percent of the concrete volume weighs 0.01 × 7,850 = 78.5 kg per m³ of concrete (steel density 7,850 kg/m³). Bar bending schedules list each bar's diameter, shape, cutting length, number and weight; bends reduce the cutting length (commonly 1d at a 45° bend and 2d at a 90° bend) and hooks add to it.
The rate of an item is built from materials, labour, tools and plant, then a margin for overheads and contractor's profit. For 10 m³ of brickwork with 500 bricks per m³ at ₹8 a brick…
4. Valuation: depreciation, sinking fund and capitalised value
Valuation estimates the worth of a property for sale, mortgage, rent fixation or acquisition. Market value is what a willing buyer would pay; book value is cost less accumulated depreciation; scrap value is the worth of the materials at the end of life. Under straight-line depreciation the yearly charge is (cost − scrap) ÷ life: a building costing ₹8,00,000 with 10 percent scrap value and a 60-year life loses (8,00,000 − 80,000) ÷ 60 = ₹12,000 a year. A sinking fund puts aside a fixed instalment each year at compound interest to rebuild the asset: to accumulate ₹1,00,000 in 10 years at 5 percent the instalment is S i ÷ ((1 + i)ⁿ − 1) = 1,00,000 × 0.05 ÷ (1.05¹⁰ − 1) ≈ ₹7,950.
For an income-producing property the capitalised value is net annual income × years' purchase (YP), where YP = 100 ÷ rate of return in percent. Net income is gross rent less outgoings (repairs, taxes, management, insurance). With gross rent ₹60,000 a year and outgoings 25 percent, the net income is ₹45,000; at a 6 percent return YP = 16.67 and the value is 45,000 × 16.67 = ₹7,50,000, which is the same as 45,000 ÷ 0.06. A lower expected return raises YP and the value; taking gross rent instead of net income overstates it.
| Method | Formula | Worked figure |
|---|---|---|
| Straight-line depreciation | (C − S) ÷ n | ₹12,000 a year |
| Sinking fund instalment | S i ÷ ((1 + i)ⁿ − 1) | ₹7,950 for ₹1,00,000 in 10 years at 5% |
| Capitalised value | Net income × YP | ₹7,50,000 |
Valuation estimates the worth of a property for sale, mortgage, rent fixation or acquisition. Market value is what a willing buyer would pay; book value is cost less accumulated…
5. Worked problems: deductions, brick count and the sinking fund
Quantity take-off always follows the same order: gross quantity first, then deductions for openings, then the net quantity that is paid for. Consider a brick wall 10 m long, 3 m high and 0.2 m thick. Its gross volume is 10 × 3 × 0.2 = 6.0 m³. A door opening 1 m wide and 2 m high deducts 1 × 2 × 0.2 = 0.4 m³, leaving 5.6 m³. Modular brickwork of 20 × 10 × 10 cm bricks (nominal size, mortar included) takes 1 ÷ (0.2 × 0.1 × 0.1) = 500 bricks per cubic metre, so the wall needs 5.6 × 500 = 2,800 bricks, before wastage.
| Item | Formula | Worked value |
|---|---|---|
| Straight-line depreciation | (Cost − salvage) ÷ life | (₹5,00,000 − ₹50,000) ÷ 30 = ₹15,000 a year |
| Sinking-fund instalment | A = i S ÷ [(1 + i)ⁿ − 1] | ₹1,00,000 in 5 years at 8% needs ₹17,046 a year |
| Centre-line length of a room | 2 × (centre length + centre breadth) | Rooms 5 m × 4 m between centres give 18 m |
| Trench volume | Centre-line length × width × depth | 36 m × 0.6 m × 0.9 m = 19.44 m³ |
For the sinking fund the factor (1.08)⁵ = 1.4693, so A = 1,00,000 × 0.08 ÷ 0.4693 = ₹17,046. Paid at the end of each of the five years and earning 8%, the instalments grow to exactly ₹1,00,000, which is a good check.
Quantity take-off always follows the same order: gross quantity first, then deductions for openings, then the net quantity that is paid for. Consider a brick wall 10 m long, 3 m high and…
Second Pass: Trench Volume, Plaster Area, Cement for Concrete, Bar Weight and Wastage
Quantities come from simple geometry with deductions for openings. Dry volume of concrete is about 1.54 times the wet volume, and a 1 : 2 : 4 mix divides it into seven parts. One cubic metre of cement is 28.8 bags of 50 kg. The weight of a steel bar in kg per metre is d²/162 with d in mm. Bricks are ordered with an allowance of about 5% for breakage.
| Item | Working | Answer |
|---|---|---|
| Trench 10 m × 1 m × 1.5 m | 10 × 1 × 1.5 | 15 m³ |
| Room 4 × 3 × 3 m, door 1 × 2, window 1 × 1 | 2(4 + 3) × 3 − 3 | 39 m² |
| Cement for 1 m³ of 1 : 2 : 4 | 1.54/7 × 28.8 | ≈ 6.3 bags |
| 12 mm bar | 12²/162 | 0.89 kg/m |
Quantities come from simple geometry with deductions for openings. Dry volume of concrete is about 1.54 times the wet volume, and a 1 : 2 : 4 mix divides it into seven parts. One cubic…
Key takeaways
- Approximate estimates use plinth area, cubic content or a unit base; a detailed estimate builds item quantities from drawings and ends in an abstract of cost.
- In the centre-line method the total centre length times the wall section gives the brickwork; deduct openings afterwards.
- A rate is materials plus labour plus tools and plant, then overheads and profit; check the unit before multiplying.
- Weight of a round bar is d² ÷ 162 kg per metre, and steel at 1% of concrete volume is 78.5 kg per m³.
- Straight-line depreciation is (cost − scrap) ÷ life; the sinking-fund instalment is S i ÷ ((1 + i)ⁿ − 1).
- Capitalised value is net income times years' purchase, with YP = 100 ÷ rate in percent; use net, not gross, income.
- Net quantity = gross − openings; modular brickwork takes 500 bricks per m³; sinking-fund instalment A = iS ÷ [(1 + i)ⁿ − 1].
Practice questions (25)
Attempt each one before opening the answer. Every explanation names the tempting wrong option as well as the right one, because that is where marks are lost.
A plinth-area estimate for a 120 m² building at ₹18,000 per m² is:
Show answer
Answer: B — ₹21.6 lakh
120 × 18,000 = 21,60,000, which is ₹21.6 lakh. A slipped decimal gives the other figures.In IS 1200 measurement, brickwork is measured in:
Show answer
Answer: C — Cubic metres
Masonry is a volume and is paid in cubic metres; plaster is in square metres.A room 5 m × 4 m clear inside has 0.3 m thick walls. Its centre-line length is:
Show answer
Answer: D — 19.2 m
The centre rectangle is 5.3 × 4.3, so 2 × (5.3 + 4.3) = 19.2 m. Using the clear dimensions gives 18 m.
Show the other 22 questions
Gross brickwork for a centre-line length of 19.2 m, wall thickness 0.3 m and height 3 m is:
Show answer
Answer: A — 17.28 m³
Volume = 19.2 × 0.3 × 3 = 17.28 m³. Leaving out the thickness gives an area, 57.6 m².The weight per metre of a 16 mm diameter steel bar is about:
Show answer
Answer: B — 1.58 kg
Weight = d² ÷ 162 = 256 ÷ 162 = 1.58 kg/m. Taking d ÷ 10 or d²/100 gives the other figures.Direct cost of 10 m³ brickwork is ₹70,000. Adding 20% for overheads and profit, the rate per m³ is:
Show answer
Answer: C — ₹8,400
70,000 × 1.2 = 84,000 for 10 m³, so ₹8,400 per m³. ₹84,000 forgets to divide by the quantity.Straight-line depreciation: cost ₹8,00,000, scrap value 10% of cost, life 60 years. The yearly depreciation is:
Show answer
Answer: D — ₹12,000
(8,00,000 − 80,000) ÷ 60 = 12,000. Ignoring the scrap value gives 13,333.Years' purchase at a 5% rate of return is:
Show answer
Answer: A — 20
YP = 100 ÷ 5 = 20. A lower rate gives a larger YP.A property has gross rent ₹60,000 a year, outgoings 25% of it, and a 6% return is expected. Its capitalised value is:
Show answer
Answer: B — ₹7,50,000
Net income = 60,000 × 0.75 = 45,000; value = 45,000 ÷ 0.06 = 7,50,000. Using gross rent gives 10,00,000.Steel at 1% of the volume of concrete weighs, per m³ of concrete, about (steel density 7,850 kg/m³):
Show answer
Answer: C — 78.5 kg
0.01 × 7,850 = 78.5 kg. A slipped factor of ten gives 7.85 or 785.A brick wall is 10 m long, 3 m high and 0.2 m thick and has one door opening 1 m wide and 2 m high. Using 500 modular bricks per cubic metre, the number of bricks needed (without wastage) is:
Show answer
Answer: A — 2,800
Gross volume 10 × 3 × 0.2 = 6.0 m³, less the opening 1 × 2 × 0.2 = 0.4 m³, gives 5.6 m³, and 5.6 × 500 = 2,800. Using the gross volume gives 3,000, the common slip.A sum of ₹1,00,000 is needed at the end of 5 years. Equal instalments are paid at the end of each year into a sinking fund earning 8% a year. Taking (1.08)⁵ = 1.4693, each instalment is nearest to:
Show answer
Answer: A — ₹17,046
A = iS ÷ [(1 + i)ⁿ − 1] = 8,000 ÷ 0.4693 = ₹17,046. Dividing 1,00,000 by 5 gives ₹20,000 and ignores the interest earned.A trench is 10 m long, 1 m wide and 1.5 m deep. The volume of earth to be excavated is:
Show answer
Answer: A — 15 m³
Volume = length × width × depth = 10 × 1 × 1.5 = 15 m³. Estimating excavation is measured in cubic metres.A room is 4 m × 3 m inside with a height of 3 m, one door of 1 m × 2 m and one window of 1 m × 1 m. The area of internal plastering on the walls is:
Show answer
Answer: A — 39 m²
Wall area = 2(4 + 3) × 3 = 42 m², and deducting the openings 2 + 1 = 3 m² leaves 39 m². The 42 m² forgets the deductions.The quantity of cement in 1 m³ of 1 : 2 : 4 concrete, taking the dry volume as 1.54 m³ and 1 m³ of cement as 28.8 bags, is nearest to:
Show answer
Answer: A — 6.3 bags
Cement is 1/7 of 1.54 = 0.22 m³, and 0.22 × 28.8 = 6.3 bags. The 28.8 is the bags in a whole cubic metre of cement.The weight of a 12 mm diameter steel bar per metre length, by the formula d²/162, is nearest to:
Show answer
Answer: A — 0.89 kg
W = 12²/162 = 144/162 = 0.89 kg/m, consistent with the density of steel 7,850 kg/m³ and area 113 mm². The 16 mm bar weighs 1.58 kg/m.A building yields a net annual income of ₹45,000 and the capitalisation rate is 5%. Its capitalised value is:
Show answer
Answer: A — ₹9,00,000
Capitalised value = net income × years' purchase = 45,000 × 20 = ₹9,00,000, since YP = 100/5 = 20. The ₹2,25,000 multiplies by the rate instead.A machine costing ₹1,00,000 is depreciated at 10% a year by the declining-balance (written-down value) method. Its book value after two years is:
Show answer
Answer: A — ₹81,000
After year 1 the value is 90,000 and after year 2 it is 90,000 × 0.9 = 81,000. The ₹80,000 is the straight-line value.A wall requires 5 m³ of brickwork at 500 bricks per cubic metre. Allowing 5% for breakage, the number of bricks to be ordered is:
Show answer
Answer: A — 2,625
Net bricks = 5 × 500 = 2,500, and adding 5% (125) gives 2,625. The 2,500 omits the breakage allowance.The plinth-area estimate of a 150 m² building at ₹16,000 per m² is:
Show answer
Answer: D — ₹24 lakh
150 × 16,000 = ₹24,00,000 = ₹24 lakh. Check: 15 × 16,000 = 2.4 lakh, times 10. Misplacing a zero gives ₹2.4 lakh.The weight per metre of a 20 mm diameter steel bar, by the formula d²/162, is about:
Show answer
Answer: B — 2.47 kg
W = d² ÷ 162 = 400 ÷ 162 = 2.47 kg/m. The 1.58 kg belongs to a 16 mm bar (256 ÷ 162), the tempting neighbouring size.The cross-sectional areas of an embankment at two sections 30 m apart are 12 m² and 18 m². By the mean sectional area method the volume between them is:
Show answer
Answer: B — 450 m³
Volume = length × (A₁ + A₂) ÷ 2 = 30 × 15 = 450 m³. Using only one end area (360 or 540) is the tempting slip, and 900 forgets to halve the sum.A building costs ₹5,00,000, has a life of 10 years and a scrap value of ₹50,000. Using straight-line depreciation, its book value after 3 years is:
Show answer
Answer: A — ₹3,65,000
Annual depreciation = (5,00,000 − 50,000) ÷ 10 = ₹45,000, so after 3 years it is 1,35,000 and the book value is 5,00,000 − 1,35,000 = ₹3,65,000. Using 10% of the full cost gives the tempting ₹3,50,000.A bill of quantities (BOQ) is a document that:
Show answer
Answer: A — Lists the items of work with their quantities, units and rates
The BOQ itemises the work, with quantity and rate for each item, and is the basis for tenders and bills. A lump-sum total hides this detail, the tempting wrong choice.Assertion (A): The centre-line method gives the quantity of walls of a building correctly without separate deduction at junctions.
Reason (R): The overlap of walls at corners and junctions is automatically accounted for in the centre-line length.
Which one of the following is correct?Show answer
Answer: A — Both A and R are true, and R is the correct explanation of A
In the centre-line length the corner overlaps are balanced out, so the quantity comes right, and R explains A. Adding the outer lengths without correction would over-measure, the tempting method.