The SEBI and PFRDA Commerce paper names costing as its own topic: cost and management accounting, job, batch, contract and process costing, standard and marginal costing, budgetary control, and the lean family (JIT, Kaizen, 5S, TPM, Six Sigma, BPR). This chapter teaches each at the depth a Grade A paper sets, with a worked number for every method that is recomputed by script. The tools are first separated by the question they answer: what did a job cost, what happens to profit if volume changes, and why did actual cost differ from the standard.
Overview

1. Cost concepts and the costing methods

2 min read · 4 parts

Financial accounting reports to outsiders on the whole business and the past; cost accounting ascertains and controls the cost of products and activities; management accounting uses cost and other data for planning and decisions. Costs are classified by element (material, labour, expenses), by traceability (direct costs trace to a unit, indirect costs or overheads do not), by behaviour (fixed, variable, semi-variable) and by function (production, administration, selling and distribution). A sunk cost is already spent and irrelevant to a decision; an opportunity cost is the best alternative given up; a controllable cost is one a given manager can influence.

Which costing method for which business
MethodUsed whenTypical examples
Job costingEach order is different and costed separatelyPrinting, repair shops, tailoring
Batch costingA batch of identical units is the cost unitBiscuits, garments, spare parts
Contract costingOne large long-duration work at the customer's siteBuildings, bridges, roads
Process costingContinuous mass production through successive processesChemicals, textiles, cement
Operating (service) costingCost per unit of serviceTransport per tonne-km, power per unit

Job costing, worked. Materials 12,000, direct labour 8,000 and direct expenses 1,000 give prime cost 21,000. Factory overhead is absorbed at 75% of direct labour, 6,000, so works cost is 27,000. Office overhead at 10% of works cost adds 2,700, giving cost of production 29,700; selling and distribution of 1,300 gives a total cost of 31,000. A profit of 20% on selling price makes the price 31,000 ÷ 0.8 = ₹38,750, whereas 20% on cost would give 37,200: the base of the profit percentage decides the answer.

Process costing, worked. Input is 1,000 units; materials 10,000, labour 5,000 and overhead 3,500 total 18,500. Normal loss is 10% (100 units) sold as scrap at ₹5, realising 500. The cost of the good output is the total cost less scrap value, spread over the expected output: (18,500 − 500) ÷ 900 = ₹20 a unit. Normal loss is absorbed into good units; abnormal loss is valued at the same unit cost and written off to the profit and loss account, not carried in stock.

Financial accounting reports to outsiders on the whole business and the past; cost accounting ascertains and controls the cost of products and activities; management accounting uses cost…

2. Marginal costing and cost-volume-profit analysis

1 min read · 4 parts

Marginal costing charges only variable costs to products; fixed costs are written off in the period. Contribution = selling price − variable cost, and it first covers fixed cost and then becomes profit. The P/V (profit-volume) ratio = contribution ÷ sales. Break-even point is where contribution equals fixed cost: BEP units = fixed cost ÷ contribution per unit, and BEP sales = fixed cost ÷ P/V ratio. The margin of safety is actual sales less break-even sales.

CVP worked: price ₹50, variable cost ₹30, fixed cost ₹40,000
MeasureWorkingResult
Contribution per unit50 − 30₹20
P/V ratio20 ÷ 5040%
Break-even units40,000 ÷ 202,000
Break-even sales40,000 ÷ 0.40₹1,00,000
Margin of safety at 3,000 units(3,000 − 2,000) ÷ 3,00033.3% of sales
Units for a profit of ₹20,000(40,000 + 20,000) ÷ 203,000

Marginal against absorption costing. The two give different profits only when opening and closing stock differ. Production of 1,000 units with fixed overhead 20,000 carries ₹20 of fixed overhead in each unit under absorption costing. If 800 are sold, 200 units remain in stock carrying 4,000 of fixed cost, so absorption costing shows 4,000 more profit than marginal costing, which has already written all 20,000 off. When stock falls, the difference reverses. Marginal costing is preferred for decisions such as make or buy, accept a special order, drop a product or choose the product mix under a limiting factor (rank by contribution per unit of the scarce resource).

⚠️ Exam trap: divide by the ratio
P/V ratio is a percentage of sales, not of cost. If the P/V ratio is 25% and fixed cost is ₹30,000, break-even sales are 30,000 ÷ 0.25 = ₹1,20,000, not ₹30,000 × 25. Dividing by the ratio, never multiplying, is the check.

Marginal costing charges only variable costs to products; fixed costs are written off in the period. Contribution = selling price − variable cost, and it first covers fixed cost and then…

3. Standard costing, variances and budgetary control

2 min read · 2 parts

Standard costing sets what a unit should cost, then explains the gap from actual cost as variances, favourable (F) when actual is better than standard and adverse (A) when worse. Material cost variance splits into price = (standard price − actual price) × actual quantity and usage = (standard quantity for actual output − actual quantity) × standard price. Labour splits into rate = (standard rate − actual rate) × actual hours and efficiency = (standard hours for actual output − actual hours) × standard rate. The price/rate variance uses the actual quantity or hours; the usage/efficiency variance uses the standard price or rate.

Variances worked
Case and varianceWorkingResult
Material: standard 2 kg a unit at ₹10; 500 units made; 1,100 kg used at ₹9.50. Price variance(10 − 9.5) × 1,100₹550 F
Material usage variance (standard quantity 1,000 kg)(1,000 − 1,100) × 10₹1,000 A
Material cost variance10,000 − 10,450₹450 A
Labour: standard 3 hours a unit at ₹40; 1,600 hours at ₹38. Rate variance(40 − 38) × 1,600₹3,200 F
Labour efficiency variance (standard hours 1,500)(1,500 − 1,600) × 40₹4,000 A
Labour cost variance60,000 − 60,800₹800 A

The check is that the parts add to the whole: 550 F − 1,000 A = 450 A, and 3,200 F − 4,000 A = 800 A. A cheap purchase (favourable price) that causes wastage (adverse usage) is the classic reading of the first set. Budgetary control compares actual results with a budget prepared in advance: a fixed budget stays at one level of activity, a flexible budget is recast for the actual level of activity so that the comparison is fair, a zero-base budget justifies every item from scratch each period, and a master budget consolidates the functional budgets (sales, production, purchases, cash). The key (limiting) factor is the one that restricts activity and is budgeted first.

Standard costing sets what a unit should cost, then explains the gap from actual cost as variances, favourable (F) when actual is better than standard and adverse (A) when worse. Material…

4. Material control and the lean and quality tools

1 min read · 3 parts

Economic order quantity minimises the sum of ordering and carrying costs: EOQ = √(2 × annual demand × cost per order ÷ carrying cost per unit per year). For demand 3,600 units, ordering cost ₹150 and carrying cost ₹3, EOQ = √(2 × 3,600 × 150 ÷ 3) = 600 units. Stock levels follow from usage and lead time: reorder level = maximum usage × maximum lead time = 50 × 12 = 600; minimum level = reorder level − (normal usage × normal lead time) = 600 − 40 × 10 = 200; maximum level = reorder level + reorder quantity − (minimum usage × minimum lead time) = 600 + 600 − 30 × 8 = 960. ABC analysis puts effort where value is: a few A items carry most of the value.

The lean and quality family
ToolIdea
Just-in-time (JIT)Receive and produce only what is needed, when needed; cuts inventory and waste
KaizenJapanese for continuous small improvement by everyone
5SSort, set in order, shine, standardise, sustain (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)
Total productive maintenance (TPM)Operators and maintenance together keep machines running; aims at zero breakdowns
Six SigmaData-driven defect reduction to 3.4 defects per million opportunities; method DMAIC (define, measure, analyse, improve, control)
Business process re-engineering (BPR)Radical redesign of a process from scratch for dramatic gains, unlike Kaizen's small steps
Activity-based costing (ABC)Assigns overhead to products through the activities (cost drivers) that cause it, not a single labour-hour rate
⚠️ Exam trap: Kaizen against BPR
Kaizen and BPR are opposites in pace: Kaizen is continuous and incremental, BPR is a one-time radical redesign. Six Sigma's 3.4 defects is per million opportunities, not per million units.

Economic order quantity minimises the sum of ordering and carrying costs: EOQ = √(2 × annual demand × cost per order ÷ carrying cost per unit per year). For demand 3,600 units, ordering…

Worked Drills: Margin of Safety, Target Profit, Labour Variances and Overhead Absorption

1 min read · 2 parts

Break-even and target profit questions reduce to one equation: units needed = (fixed cost + target profit) ÷ contribution per unit. Variances split a total difference into a price part and a quantity or efficiency part. Overhead is absorbed at a predetermined rate (budgeted overhead ÷ budgeted base), so any gap between absorbed and actual overhead is under- or over-absorption.

Costing arithmetic at a glance
QuestionWorkingAnswer
Fixed cost 60,000, P/V ratio 40%: break-even sales60,000/0.40₹1,50,000
Sales 2,00,000, break-even 1,50,000: margin of safety(2,00,000 − 1,50,000)/2,00,00025%
Price 80, variable 50, fixed 45,000, profit 15,000(45,000 + 15,000)/302,000 units
Overhead 2,40,000 on 40,000 hours2,40,000/40,000₹6 per hour
🧠 Labour variance split into rate and efficiency
Standard rate ₹20 an hour; actual rate ₹22; actual hours 500; standard hours allowed for the actual output 480. Rate variance = (20 − 22) × 500 = ₹1,000 adverse. Efficiency variance = (480 − 500) × 20 = ₹400 adverse. Total variance = ₹1,400 adverse. Route two: standard cost 480 × 20 = 9,600 and actual cost 500 × 22 = 11,000, a difference of ₹1,400 ✓.

Break-even and target profit questions reduce to one equation: units needed = (fixed cost + target profit) ÷ contribution per unit. Variances split a total difference into a price part and…

Key takeaways

  • Costs are classified by element, traceability (direct or overhead), behaviour (fixed, variable) and function; sunk costs are ignored in decisions and opportunity cost is counted.
  • Job, batch, contract, process and service costing match the type of production; normal loss is absorbed in good units, abnormal loss is written off.
  • Contribution = price − variable cost; break-even units = fixed cost ÷ contribution per unit; break-even sales = fixed cost ÷ P/V ratio; margin of safety = actual − break-even sales.
  • Absorption costing shows more profit than marginal costing when closing stock exceeds opening stock, by the fixed overhead carried in the extra stock.
  • Price and rate variances use actual quantity or hours; usage and efficiency variances use the standard price or rate; the sub-variances must add up to the total.
  • EOQ = √(2AO ÷ C); reorder level = maximum usage × maximum lead time; Kaizen is continuous, BPR radical, Six Sigma 3.4 defects per million opportunities, 5S has five Japanese steps.

Practice questions (27)

Attempt each one before opening the answer. Every explanation names the tempting wrong option as well as the right one, because that is where marks are lost.

  1. Selling price ₹50, variable cost ₹30 and fixed cost ₹40,000. The break-even point in units is:

    1. 800
    2. 2,000
    3. 1,333
    4. 4,000
    Show answer

    Answer: B — 2,000

    Contribution per unit is 50 − 30 = 20, so break-even units = 40,000 ÷ 20 = 2,000. The figure 800 divides by the selling price and 1,333 by the variable cost, both the wrong denominator.
  2. The P/V ratio of a product is 25% and fixed cost is ₹30,000. Break-even sales are:

    1. ₹75,000
    2. ₹7,500
    3. ₹1,20,000
    4. ₹30,000
    Show answer

    Answer: C — ₹1,20,000

    Break-even sales = fixed cost ÷ P/V ratio = 30,000 ÷ 0.25 = ₹1,20,000. Multiplying by 25% gives the wrong ₹7,500; at ₹1,20,000 the contribution of 25% is exactly 30,000.
  3. Which costing method suits a cement manufacturer producing continuously through successive stages?

    1. Job costing
    2. Contract costing
    3. Process costing
    4. Batch costing
    Show answer

    Answer: C — Process costing

    Continuous mass production through successive processes, with each process's output feeding the next, is the case for process costing. Job and contract costing fit one-off orders and large site works.
Show the other 24 questions
  1. In process costing, 1,000 units are put in at a total cost of ₹18,500, normal loss is 10% and the scrap sells at ₹5 a unit. The cost per good unit is:

    1. ₹20.00
    2. ₹20.56
    3. ₹18.00
    4. ₹18.50
    Show answer

    Answer: A — ₹20.00

    Normal loss is 100 units realising ₹500, so the net cost is 18,500 − 500 = 18,000 over 900 good units = ₹20. Dividing 18,500 by 900 forgets the scrap value (₹20.56), and 18,500 by 1,000 forgets the loss.
  2. Standard price ₹10 a kg, actual price ₹9.50, actual quantity 1,100 kg. The material price variance is:

    1. ₹550 adverse
    2. ₹1,000 adverse
    3. ₹450 adverse
    4. ₹550 favourable
    Show answer

    Answer: D — ₹550 favourable

    (Standard price − actual price) × actual quantity = (10 − 9.5) × 1,100 = ₹550, and since actual price is lower it is favourable. The ₹1,000 adverse figure is the usage variance, and ₹450 adverse the total cost variance.
  3. A firm produces 1,000 units, sells 800 and has fixed overhead of ₹20,000. Absorption costing profit exceeds marginal costing profit by:

    1. ₹20,000
    2. ₹4,000
    3. ₹16,000
    4. Nothing
    Show answer

    Answer: B — ₹4,000

    Closing stock is 200 units carrying ₹20 of fixed overhead each, so 4,000 of fixed cost is deferred under absorption costing but written off under marginal costing. The difference is 4,000, not the whole 20,000.
  4. A job has a total cost of ₹31,000. To earn a profit of 20% on the selling price, the price must be:

    1. ₹34,100
    2. ₹31,200
    3. ₹37,200
    4. ₹38,750
    Show answer

    Answer: D — ₹38,750

    Profit of 20% on price means cost is 80% of price, so price = 31,000 ÷ 0.8 = ₹38,750. Adding 20% to the cost gives ₹37,200, which is only a 16.7% profit on that price.
  5. Annual demand is 3,600 units, ordering cost ₹150 a order and carrying cost ₹3 a unit a year. The economic order quantity is:

    1. 600
    2. 1,800
    3. 300
    4. 360
    Show answer

    Answer: A — 600

    EOQ = √(2 × 3,600 × 150 ÷ 3) = √360,000 = 600 units. Forgetting the square root gives 360,000, and halving the demand (1,800) is a guess with no basis in the formula.
  6. A firm uses a maximum of 50 units a day and a normal 40 a day, and the lead time is at most 12 and normally 10 days. The reorder level and minimum level are:

    1. 600 and 400
    2. 480 and 200
    3. 600 and 200
    4. 500 and 100
    Show answer

    Answer: C — 600 and 200

    Reorder level = maximum usage × maximum lead time = 50 × 12 = 600. Minimum level = 600 − (40 × 10) = 200. The option 600 and 400 forgets to deduct normal usage over normal lead time, and the other pairs mix the maximum and normal figures.
  7. Fixed costs are ₹60,000 and the P/V ratio of a product is 40%. The break-even sales value is:

    1. ₹1,50,000
    2. ₹24,000
    3. ₹2,40,000
    4. ₹1,00,000
    Show answer

    Answer: A — ₹1,50,000

    Break-even sales = fixed cost ÷ P/V ratio = 60,000/0.40 = ₹1,50,000. Multiplying (₹24,000) inverts the relationship.
  8. Actual sales are ₹2,00,000 and break-even sales are ₹1,50,000. The margin of safety ratio is:

    1. 25%
    2. 33.3%
    3. 75%
    4. 50%
    Show answer

    Answer: A — 25%

    Margin of safety = (actual − break-even)/actual = 50,000/2,00,000 = 25%. Using break-even as the base (33.3%) is the usual error.
  9. A product sells at ₹80 with a variable cost of ₹50 a unit, and fixed costs are ₹45,000. The units to be sold to earn a profit of ₹15,000 are:

    1. 2,000
    2. 1,500
    3. 3,000
    4. 1,000
    Show answer

    Answer: A — 2,000

    Contribution per unit = 80 − 50 = ₹30, and units = (45,000 + 15,000)/30 = 2,000. The value 1,500 is the break-even volume (45,000/30), without the target profit.
  10. The standard labour rate is ₹20 per hour. Actual wages were ₹22 per hour for 500 hours, while the standard hours allowed for the actual output were 480. The total labour cost variance is:

    1. ₹1,400 adverse
    2. ₹1,000 adverse
    3. ₹400 adverse
    4. ₹1,400 favourable
    Show answer

    Answer: A — ₹1,400 adverse

    Standard cost = 480 × 20 = ₹9,600 and actual cost = 500 × 22 = ₹11,000, so the total is ₹1,400 adverse, made of rate variance ₹1,000 and efficiency variance ₹400, both adverse.
  11. Budgeted overhead is ₹2,40,000 on 40,000 budgeted labour hours. Actual hours worked are 38,000 and actual overhead is ₹2,35,000. The overhead is:

    1. Under-absorbed by ₹7,000
    2. Over-absorbed by ₹7,000
    3. Under-absorbed by ₹5,000
    4. Over-absorbed by ₹5,000
    Show answer

    Answer: A — Under-absorbed by ₹7,000

    Rate = 2,40,000/40,000 = ₹6 per hour, so absorbed overhead = 38,000 × 6 = ₹2,28,000. Actual ₹2,35,000 exceeds this by ₹7,000, so overhead is under-absorbed.
  12. Direct material ₹50,000, direct labour ₹30,000, factory overhead ₹20,000, administration overhead ₹10,000 and selling and distribution overhead ₹8,000. The total cost is:

    1. ₹1,18,000
    2. ₹1,00,000
    3. ₹1,10,000
    4. ₹1,08,000
    Show answer

    Answer: A — ₹1,18,000

    Prime cost = 80,000; factory cost = 1,00,000; cost of production = 1,10,000 after administration; total cost = 1,18,000 after selling and distribution. Stopping before selling gives ₹1,10,000.
  13. Consider the following statements:
    1. Marginal costing treats fixed costs as period costs charged in full to the period.
    2. When closing stock is greater than opening stock, absorption costing shows a lower profit than marginal costing.
    Which of the statements is/are correct?

    1. 1 only
    2. 2 only
    3. Both 1 and 2
    4. Neither 1 nor 2
    Show answer

    Answer: A — 1 only

    Marginal costing charges all fixed cost to the period. With rising stock, absorption costing carries part of the fixed overhead forward in closing stock, so its profit is higher, not lower; statement 2 is reversed.
  14. A product sells at ₹100 with a variable cost of ₹60 a unit. Fixed costs are ₹80,000 and the firm wants a profit of ₹40,000. The units to be sold are:

    1. 3,000
    2. 1,200
    3. 2,000
    4. 4,000
    Show answer

    Answer: A — 3,000

    Units = (fixed cost + target profit) ÷ contribution per unit = 1,20,000 ÷ 40 = 3,000. Check: 3,000 × 40 = 1,20,000, less 80,000 fixed = 40,000 profit. Using only fixed cost gives the break-even 2,000, the tempting wrong answer.
  15. The margin of safety is ₹1,25,000 and the P/V ratio is 40%. The profit is:

    1. ₹75,000
    2. ₹50,000
    3. ₹1,25,000
    4. ₹31,250
    Show answer

    Answer: B — ₹50,000

    Profit = margin of safety × P/V ratio = 1,25,000 × 0.40 = ₹50,000, because above break-even every rupee of sales adds the contribution percentage as profit. The margin itself (1,25,000) is sales, not profit.
  16. Consider the following statements:
    1. Within the relevant range, fixed cost per unit falls as output rises.
    2. Within the relevant range, variable cost per unit rises in proportion to output.
    Which of the statements given above is/are correct?

    1. 1 only
    2. 2 only
    3. Both 1 and 2
    4. Neither 1 nor 2
    Show answer

    Answer: A — 1 only

    Total fixed cost is spread over more units, so the per-unit figure falls (1 is correct). Total variable cost rises with output, but the per-unit figure stays constant, so 2 confuses the total with the per-unit cost, which is the tempting error.
  17. The standard quantity of material for the actual output is 1,000 kg, the actual quantity used is 1,050 kg and the standard price is ₹20 a kg. The material usage variance is:

    1. ₹1,050 adverse
    2. ₹21,000 adverse
    3. ₹1,000 adverse
    4. ₹1,000 favourable
    Show answer

    Answer: C — ₹1,000 adverse

    Usage variance = (standard quantity − actual quantity) × standard price = (1,000 − 1,050) × 20 = ₹1,000, and the negative sign makes it adverse. It is valued at the standard price, not the actual price, and it is not the whole cost of 1,050 kg.
  18. The standard rate is ₹20 an hour, the actual hours are 500 and the standard hours allowed for the actual output are 480. The labour efficiency variance is:

    1. ₹10,000 adverse
    2. ₹400 favourable
    3. ₹400 adverse
    4. ₹9,600 favourable
    Show answer

    Answer: C — ₹400 adverse

    Efficiency variance = (standard hours − actual hours) × standard rate = (480 − 500) × 20 = ₹400 adverse, since more hours were taken than allowed. It uses the standard rate, so the actual rate of ₹22 in the rate variance is not involved.
  19. Assertion (A): Under marginal costing, closing stock is valued at variable cost only.
    Reason (R): Fixed overhead is treated as a period cost and charged to profit in the period it is incurred.
    Which one of the following is correct?

    1. Both A and R are true, and R is the correct explanation of A
    2. Both A and R are true, but R is not the correct explanation of A
    3. A is true, but R is false
    4. A is false, but R is true
    Show answer

    Answer: A — Both A and R are true, and R is the correct explanation of A

    Because fixed overhead is written off in the period, none of it is carried into stock, so stock carries variable cost only. R is the reason for A. Absorption costing, which carries a share of fixed overhead in stock, is the tempting contrast to avoid mixing up.
  20. The economic order quantity is 600 units when annual demand is 3,600 units. If annual demand rises to 14,400 units (four times) with the same ordering and carrying costs, the EOQ becomes:

    1. 2,400 units
    2. 1,200 units
    3. 1,800 units
    4. 600 units
    Show answer

    Answer: B — 1,200 units

    EOQ = √(2DS ÷ C) varies with the square root of demand, so four times the demand doubles it: √(2 × 14,400 × 150 ÷ 3) = √14,40,000 = 1,200. Quadrupling it to 2,400 is the tempting error.
  21. In ABC analysis of inventory, Class A items are those that:

    1. Are few in number but account for a large share of the value
    2. Are many in number and account for a small share of the value
    3. Are slow-moving and obsolete
    4. Are bought only on credit
    Show answer

    Answer: A — Are few in number but account for a large share of the value

    Class A is a small fraction of items (often about 10%) carrying most of the value (often about 70%) and so gets the tightest control. The many low-value items are Class C, which is the tempting reversal.
  22. Arrange the following cost-sheet totals in the order in which they build up:
    1. Cost of production
    2. Prime cost
    3. Cost of sales
    4. Works (factory) cost

    1. 2, 4, 1, 3
    2. 1, 2, 4, 3
    3. 4, 2, 1, 3
    4. 2, 1, 4, 3
    Show answer

    Answer: A — 2, 4, 1, 3

    Prime cost (direct material, labour and expenses) comes first; adding factory overhead gives works cost; adding administration overhead gives cost of production; adding selling and distribution overhead gives cost of sales. Putting works cost before prime cost is the tempting error.
  23. A product has a P/V ratio of 40% and sells at ₹50 a unit. Its variable cost per unit is:

    1. ₹10
    2. ₹30
    3. ₹20
    4. ₹40
    Show answer

    Answer: B — ₹30

    Variable cost is the share of price that is not contribution: 60% of 50 = ₹30. Check: contribution 50 − 30 = 20 = 40% of 50. The ₹20 is the contribution, the tempting wrong answer.
  24. Budgeted factory overhead is ₹3,60,000 and budgeted machine hours are 12,000. The predetermined overhead absorption rate per machine hour is:

    1. ₹30
    2. ₹300
    3. ₹12
    4. ₹3.33
    Show answer

    Answer: A — ₹30

    Rate = budgeted overhead ÷ budgeted base = 3,60,000 ÷ 12,000 = ₹30 per machine hour. Check: 12,000 × 30 = 3,60,000. Dividing the hours by the overhead gives the meaningless 0.033.