Industrial Engineering in Numbers: Time Study and Work Sampling, PMTS, Learning Curves, Assembly Line Balancing, Facility Location and Break-Even Comparisons
Learning Curves
Every time the cumulative output doubles, the time per unit falls to a fixed fraction s (the learning rate). With T_n = T₁ n^b and b = ln s/ln 2: for s = 0.8, b = -0.3219. If the first unit takes 100 h, the 8th takes 100 × 8^b = 51.2 h (0.8³ = 51.2% of the first, because 8 = 2³ doublings), and the 16th takes 41.0 h. In the cumulative-average model the average over the first n units is Y_n = Y₁ n^b, so the average over 8 units is 51.2 h and the total time is 8 × 51.2 = 409.6 h, whereas under the unit-time model the total is Σ T₁ n^b = 534.6 h (average 66.8); the two models differ, so a question must say which it means. Learning explains why early standard times overestimate and why a new line is under-performing at start-up; it applies to labour-intensive work, not to machine-paced operations. Typical rates are 70–80% for assembly and 85–90% for machining.
| Unit n | Time, 80% curve (h) | % of first |
|---|---|---|
| 1 | 100.0 | 100.0 |
| 2 | 80.0 | 80.0 |
| 4 | 64.0 | 64.0 |
| 8 | 51.2 | 51.2 |
| 16 | 41.0 | 41.0 |
Every time the cumulative output doubles, the time per unit falls to a fixed fraction s (the learning rate). With T_n = T₁ n^b and b = ln s/ln 2: for s = 0.8, b = -0.3219. If the first unit…
Assembly Line Balancing
The cycle time is C = available time / required output: 480 min × 60 s = 28800 s over 2880 units gives 10 s. For the eight-task network below (times in minutes, total = 29 min) with C = 10 min the theoretical minimum number of stations is ⌈ΣT/C⌉ = ⌈29/10⌉ = 3, and C cannot be less than the longest task (6 min). The ranked positional weight (RPW) rule gives each task a weight equal to its time plus the times of all its followers, then loads stations in order of weight, always respecting precedence and the cycle time. The weights are A 29, C 19, E 15, B 14, D 11, F 9, G 6, H 2; the loading is station 1: A+C = 9 min; station 2: E+B = 9 min; station 3: D+F+G = 9 min; station 4: H = 2 min. RPW is a heuristic and here it uses 4 stations at 29/(4 × 10) = 72.5% efficiency; a better assignment — (A, B, D), (C, E), (F, G, H) with loads 10, 10 and 9 min — reaches the theoretical 3 stations, line efficiency = ΣT/(N × C) = 29/(3 × 10) = 96.7%, balance delay 3.3%. The precedence is A → B, C; B → D; C → E; D, E → F; F → G → H. Lowering C below the heaviest cumulative chain is impossible; raising it lowers the output.
| Task | Time (min) | Positional weight |
|---|---|---|
| A | 5 | 29 |
| C | 4 | 19 |
| E | 6 | 15 |
| B | 3 | 14 |
| D | 2 | 11 |
| F | 3 | 9 |
| G | 4 | 6 |
| H | 2 | 2 |
The cycle time is C = available time / required output: 480 min × 60 s = 28800 s over 2880 units gives 10 s. For the eight-task network below (times in minutes, total = 29 min) with C = 10…
Facility Location, Break-Even Comparison and Layout Loads
The centre of gravity method places a single facility at the weighted mean of the demand points: for points (2,8) w 30, (9,3) w 50, (5,6) w 20, (7,9) w 40 (total 140), x = Σwx/Σw = 6.36, y = 6.21. That minimises squared Euclidean distance. When goods move along aisles (rectilinear distance) the optimum is the weighted median in each coordinate separately: x = 7, y = 6, with a transport load Σw(|Δx| + |Δy|) = 620 against 646 at the centre of gravity — the median is better for rectilinear moves. The factor rating method weights qualitative factors (labour, power, markets), and the break-even comparison finds the volume at which two sites cost the same: site A fixed ₹5 lakh and ₹60 per unit, site B fixed ₹8 lakh and ₹35 per unit, equal at x = (800 000 − 500 000)/(60 − 35) = 12,000 units; below it A is cheaper, above it B. Layouts (product, process, cellular, fixed-position) trade flow against flexibility; group technology forms cells by part family. Ergonomics: the Murrell rest allowance R = T(E − 5.2)/(E − 1.5) for an energy expenditure E = 7.5 kcal/min over a 480-min shift is 184 min; the NIOSH recommended weight limit is RWL = 23 kg × the product of horizontal, vertical, distance, asymmetry, frequency and coupling multipliers (here 0.8 × 0.9 × 0.85 × 0.95 gives 13.4 kg).
| Method | Minimises | Result |
|---|---|---|
| Centre of gravity | Squared Euclidean distance | (6.36, 6.21) |
| Weighted median | Rectilinear distance | (7, 6) |
| Break-even of sites A and B | Total cost equality | 12,000 |
The centre of gravity method places a single facility at the weighted mean of the demand points: for points (2,8) w 30, (9,3) w 50, (5,6) w 20, (7,9) w 40 (total 140), x = Σwx/Σw = 6.36, y…
Key takeaways
- Normal time = observed × rating; standard time = normal × (1 + allowance) or normal/(1 − allowance) depending on the allowance basis.
- Sample sizes: time study n = (1.96 CV/k)², work sampling n = z²p(1 − p)/e²; 1 TMU = 0.036 s.
- Learning curve T_n = T₁ n^(log s/log 2); an 80% curve gives 51.2% of the first unit at the 8th.
- Line balancing: minimum stations = ⌈ΣT/C⌉, efficiency = ΣT/(N C), RPW loads by positional weight within precedence.
- Centre of gravity suits Euclidean distance, the weighted median suits rectilinear distance, break-even compares fixed and variable costs.
Practice questions (24)
Attempt each one before opening the answer. Every explanation names the tempting wrong option as well as the right one, because that is where marks are lost.
A cycle is observed at 1.20 min, the operator is rated at 110% and the allowance is 15% of normal time. The standard time in minutes (three decimals) is:
Numerical answer — type the value.
Show answer
Answer: 1.518
NT = 1.20 × 1.10 = 1.32; ST = 1.32 × 1.15 = 1.518 min. If the allowance were a fraction of the total time the result would be 1.553 min, so the basis must be read from the question.In work sampling, to halve the absolute accuracy interval e while keeping the confidence level, the number of observations must:
Show answer
Answer: C — Quadruple, since n ∝ 1/e²
n = z²p(1 − p)/e², so halving e multiplies n by 4. Accuracy is expensive: each extra decimal of precision costs a hundred-fold more observations.For work sampling with expected proportion 0.30, absolute error ±0.05 and 95% confidence (z = 1.96), the number of observations (nearest integer) is:
Numerical answer — type the value.
Show answer
Answer: 323
n = 1.96² × 0.30 × 0.70/0.05² = 322.7 ≈ 323. Using relative accuracy 5% of p instead would need far more.
Show the other 21 questions
An 80% learning curve with a first-unit time of 100 h (unit-time model). The time for the 8th unit in hours (one decimal) is:
Numerical answer — type the value.
Show answer
Answer: 51.2
8 = 2³, so three doublings: 100 × 0.8³ = 51.2 h. Taking 100 × 0.8 × 8 or 0.8⁸ would be wrong; the rate applies per doubling.The learning-curve exponent b for an 80% curve is:
Show answer
Answer: A — -0.322 = ln 0.8/ln 2
T_n = T₁ n^b with T₂ = 0.8T₁ gives 2^b = 0.8, so b = ln 0.8/ln 2 = -0.322; it is negative because time falls with experience.An eight-task assembly line with total work content 29 min is run at a cycle time of 10 min. The theoretical minimum number of stations is:
Numerical answer — type the value.
Show answer
Answer: 3
⌈29/10⌉ = ⌈2.9⌉ = 3 stations. Rounding down to 2 is impossible because the work then exceeds the cycle at each station.With total work content 29 min, 3 stations and a cycle time of 10 min, the line efficiency in per cent (one decimal) is:
Numerical answer — type the value.
Show answer
Answer: 96.7
Efficiency = ΣT/(N × C) = 29/(3 × 10) = 96.7%; the balance delay is the remaining 3.3%.For four demand points weighted 30, 50, 20 and 40 and rectilinear aisle travel, the optimum single location uses:
Show answer
Answer: B — The weighted median of each coordinate separately
Rectilinear distance sums separate absolute deviations in x and y, and the weighted median minimises a sum of absolute values; the weighted mean minimises squared (Euclidean-squared) distance instead.Site A has a fixed cost of ₹5 lakh and a variable cost of ₹60 per unit; site B has ₹8 lakh and ₹35 per unit. The volume at which the two cost the same (units) is:
Numerical answer — type the value.
Show answer
Answer: 12000
500 000 + 60x = 800 000 + 35x gives x = 300 000/25 = 12,000. Below this volume A (low fixed cost) is cheaper; above it B (low variable cost) wins.Which statements are correct?
Show answer
Answer: A — The learning rate applies per doubling of cumulative output; B — PMTS builds task times from basic motions without a stop-watch; D — Standard time is normal time plus allowances
Efficiency ΣT/(NC) cannot exceed 1 because stations cannot be loaded beyond the cycle time; the other three statements are definitions.An assembly line must produce 30 units per hour. The required cycle time, in minutes per unit, is ____.
Numerical answer — type the value.
Show answer
Answer: 2
Cycle time = available time/demand = 60/30 = 2 min/unit. Inverting (30/60 = 0.5) gives the rate, not the cycle time.An assembly line has total task time 10 min and a cycle time of 2 min. The theoretical minimum number of workstations is ____.
Numerical answer — type the value.
Show answer
Answer: 5
N_min = ⌈Σt/CT⌉ = ⌈10/2⌉ = 5 stations. Rounding down would leave insufficient capacity, so the ceiling is used.In an 80% learning curve, every doubling of cumulative output reduces the average (or unit) time to
Show answer
Answer: C — 80% of the previous value
An 80% curve means time falls to 0.8 of its previous value each time output doubles. Taking 20% confuses the learning percentage with the reduction, the standard slip.The centre-of-gravity method for facility location minimises
Show answer
Answer: A — the total weighted distance (transport cost) to the demand points
It places the facility at the load-weighted centroid of the demand points, minimising transport cost. Construction and labour costs are not what the centroid optimises, the tempting distractors.A line has 5 stations, a cycle time of 2.2 min and a total task content of 10 min. The line (balance) efficiency, in % (one decimal), is ____.
Numerical answer — type the value.
Show answer
Answer: 90.9
Efficiency = Σt/(N × CT) = 10/(5 × 2.2) = 10/11 = 90.9%. Dividing by Σt instead of N×CT would always give 100%, missing the balance delay.The first unit takes 100 min on an 80% learning curve (unit-time model, b = log0.8/log2). The time for the 8th unit, in min (one decimal), is ____.
Numerical answer — type the value.
Show answer
Answer: 51.2
The 8th unit is three doublings (1→2→4→8), so T₈ = 100 × 0.8³ = 51.2 min. Multiplying by 0.8 only once (80 min) counts one doubling instead of three.For the line above (5 stations, CT 2.2 min, task content 10 min), the balance delay, in % (two decimals), is ____.
Numerical answer — type the value.
Show answer
Answer: 9.09
Balance delay = 1 − efficiency = (11 − 10)/11 = 9.09%. Reporting the efficiency 90.9% instead confuses the idle fraction with the utilised fraction.A time study needs the number of cycles n for 5% accuracy at 95% confidence (z = 1.96) when the mean is 20 and standard deviation 5, using n = (z·s/(e·x̄))². The value of n (nearest integer) is ____.
Numerical answer — type the value.
Show answer
Answer: 96
n = (1.96 × 5/(0.05 × 20))² = (9.8/1)² = 96.04 ≈ 96. Using e = 5 instead of 0.05 shrinks n to below 1, a sign the accuracy was misread as a whole number.Which of the following are qualitative factors in facility location decisions?
Show answer
Answer: A — Availability of skilled labour; B — Community and regulatory environment; D — Proximity to markets and suppliers
Market/supplier access, labour and the regulatory climate are qualitative considerations weighed by factor rating. An exact present value is a quantitative figure, not a qualitative factor, the trap.Over a 40 h week a work-sampling study finds a machine idle 5% of observations. Its utilisation, in %, is ____.
Numerical answer — type the value.
Show answer
Answer: 95
Utilisation = 100% − idle% = 100 − 5 = 95%. Reporting the 5% idle figure as utilisation inverts busy and idle.On an 80% unit-time learning curve with a first-unit time of 100 min, the total time for the first 4 units, in min (nearest integer), is ____.
Numerical answer — type the value.
Show answer
Answer: 314
T = 100(1 + 2^b + 3^b + 4^b) with b = −0.322: 100(1 + 0.8 + 0.702 + 0.64) = 314 min. Multiplying the 4th-unit time by 4 (4 × 64 = 256) ignores that earlier units took longer.A machine has availability 90%, performance 95% and quality 98%. Its overall equipment effectiveness (OEE), in % (two decimals), is ____.
Numerical answer — type the value.
Show answer
Answer: 83.79
OEE = 0.90 × 0.95 × 0.98 = 0.8379 = 83.79%. Averaging the three (94.3%) instead of multiplying overstates effectiveness.An assembly line runs for 480 min per shift at a cycle time of 2.2 min with no losses. Its shift output, in units (nearest integer), is ____.
Numerical answer — type the value.
Show answer
Answer: 218
Output = available time/CT = 480/2.2 = 218.2 ≈ 218 units (rounding down, as a part unit is not completed). Multiplying 480 × 2.2 instead of dividing gives a meaningless 1056.In single-model assembly-line balancing, the cycle time can never be less than
Show answer
Answer: B — the largest single task time
A station must complete its longest indivisible task within the cycle, so CT ≥ max task time. Setting CT below that largest task is physically impossible, which is why the smallest or average bounds are wrong.