Industrial Engineering: Product Design, Work System Design and Facility Design

Section 6 of the GATE Production and Industrial Engineering (PI) paper is about designing the product, the job and the plant. Product design and development — the principles of product design, tolerance design, quality and cost considerations, the product life cycle, standardisation, simplification and diversification, value engineering and analysis, concurrent engineering, and design for X. Work system design — Taylor's scientific management and the Gilbreths' contributions, productivity and its measurement, method study, micro-motion study and the principles of motion economy, work measurement by time study, work sampling, standard data and predetermined motion time systems, ergonomics, and job evaluation and merit rating. Facility design — facility location factors and the evaluation of alternative locations, the types of plant layout and their evaluation, assembly line balancing, and material handling systems. The calculations here — standard time, work-sampling size, centre of gravity, line efficiency, tolerance stacks — are short, and every one of them has a definitional trap: which allowance base, which accuracy, which cycle time.

1. Principles of product design, tolerance design, quality and cost, and the product life cycle

A good product design meets its function reliably, is safe and ergonomic to use, looks right (aesthetics), can be made and assembled economically with the processes available (producibility), uses materials and standard parts sensibly, can be maintained, and meets its cost target. Because most of a product's lifetime cost is committed by decisions taken at the design stage, long before much of it is spent, cost and quality are designed in rather than inspected in. The designer therefore balances performance against cost at every choice of material, tolerance and process.

Tolerance design decides how much variation each dimension may have. When parts stack in an assembly, the worst-case method adds tolerances linearly, T_assembly = ΣT_i, guaranteeing every assembly fits but forcing tight, costly part tolerances. The statistical (root-sum-square) method assumes independent, normally distributed, centred dimensions and adds them as T_assembly = √(ΣT_i²): parts of ±0.02, ±0.03 and ±0.06 mm give ±0.11 mm worst case but only ±0.07 mm statistically, so wider, cheaper part tolerances achieve the same assembly tolerance with a small, known risk. Taguchi's quality loss function L(y) = k(y − m)² puts a cost on any deviation from the target m, not only on out-of-specification parts: if a deviation of 0.5 mm costs Rs 100, k = 400 Rs/mm² and a 0.2 mm deviation costs Rs 16. Robust design then chooses parameter settings that make the product insensitive to noise.

The product life cycle
StageSales and profitProduction emphasis
IntroductionLow sales, losses or thin profitDesign changes, flexible low-volume production
GrowthRapidly rising sales, rising profitCapacity expansion, process standardisation
MaturitySales level off, strongest competition, price pressureCost reduction, high-volume efficient processes
DeclineFalling sales and profitRationalise the range, phase out or redesign

2. Standardisation, simplification and diversification; value engineering; concurrent engineering; design for X

  • Standardisation fixes sizes, materials, methods and parts to agreed norms, so that parts interchange, inventories shrink, economies of scale grow and quality becomes repeatable; preferred numbers (geometric series) give a rational spread of sizes.
  • Simplification reduces the number of varieties — models, sizes, grades — by eliminating the superfluous ones, cutting set-ups, tooling and stock.
  • Diversification adds products or varieties to spread risk, use spare capacity or reach new markets — the opposite pull, which is why the three are studied together: a firm simplifies within a product line while diversifying across lines.

Value engineering (applied at design) and value analysis (applied to an existing product) seek the required function at the lowest total cost without sacrificing quality or reliability: value = function/cost. Economists distinguish use value (what it does), esteem value (what makes it desirable), cost value and exchange value. Functions are described by a verb and a noun — 'transmit torque', 'support load' — and classified as basic or secondary; the function analysis system technique (FAST) diagram orders them by asking how and why. The job plan runs: information (gather facts, costs), function analysis, creative or speculative (brainstorm alternatives), evaluation, development or recommendation, and implementation with follow-up.

Concurrent (simultaneous) engineering replaces the sequential, 'over-the-wall' hand-off from design to process planning to manufacturing with cross-functional teams — design, manufacturing, quality, purchasing, marketing and suppliers — working on the product and its processes in parallel from the start. Problems are found while they are cheap to fix, engineering changes after release fall, and time to market shortens. Design for X names the life-cycle concern the design is optimised for: DFM (manufacture — processes, tolerances and materials that are easy to make), DFA (assembly — fewer parts, self-locating features, top-down insertion, no fasteners where snap fits will do), DFMA combining the two, DFE (environment), DFR (reliability), design for serviceability, disassembly and recycling, and design for cost. The Boothroyd-Dewhurst DFA index = 3N_min/t_total, where N_min is the theoretical minimum number of parts (a part is essential only if it must move, must be of a different material, or must be separate for assembly or service) and 3 s is taken as an ideal handling-and-insertion time per part: 4 essential parts in a 60 s assembly give 3 × 4/60 = 20 %.

3. Taylor and the Gilbreths; productivity; method study, micro-motion study and motion economy

F. W. Taylor's scientific management replaced rule of thumb with systematic study: time study to set a fair day's work, standardised tools and methods, scientific selection and training of workers, a division of responsibility between management (planning) and workers (doing) — including functional foremanship, with separate foremen for each function — and a differential piece-rate that paid more per piece to workers who met the standard. Frank and Lillian Gilbreth founded motion study: they broke manual work into seventeen elemental motions called therbligs (search, select, grasp, transport loaded, position, assemble, use, release, inspect, hold, rest and so on — an eighteenth, find, was added later), filmed work with a clock in view for micro-motion study, recorded both hands against time on a SIMO chart, and studied fatigue. Lillian Gilbreth extended the work to the psychology of management.

Productivity is output divided by input. Partial productivity uses one input (labour productivity = units per labour-hour); total-factor productivity uses labour and capital; total productivity divides the value of all output by the value of all inputs — labour, materials, capital, energy and other expenses: output worth Rs 60 000 from inputs of Rs 10 000, 20 000, 5 000, 3 000 and 2 000 gives 60 000/40 000 = 1.5. A rise in productivity means more output from the same input or the same output from less — not simply more output, which extra input could buy.

Method study systematically records and critically examines existing and proposed ways of doing work to develop easier, more effective methods. Its steps: select the job, record the facts, examine them critically (asking what, where, when, who and how — and why each), develop the best method, define, install it and maintain it. Recording uses the outline process chart; the flow process chart, with five ASME symbols — operation (circle), inspection (square), transport (arrow), delay (D) and storage (triangle); the two-handed chart; the multiple-activity chart for worker-machine interaction; the flow diagram and the string diagram (a thread traced over a scale plan to measure distance travelled); and the travel chart. Micro-motion study analyses short, repetitive, high-volume tasks down to therbligs from film. The principles of motion economy fall in three groups: use of the human body (both hands begin and end together, move symmetrically and simultaneously, use the lowest body member that can do the job, prefer smooth curved motions to sharp changes of direction), arrangement of the workplace (fixed positions for tools and materials, within the normal working area, gravity-feed bins and drop delivery, suitable lighting and chair height), and design of tools and equipment (jigs, fixtures or foot pedals to free the hands, combined tools, pre-positioned tools).

4. Work measurement — time study, work sampling, standard data, PMTS; ergonomics; job evaluation and merit rating

Time study times a qualified worker with a stopwatch over enough cycles, element by element, and rates the observed pace against a concept of normal pace. Normal time = observed time × rating/100, and standard time = normal time × (1 + allowance), where allowances — personal needs, fatigue and unavoidable delay — are normally expressed as a percentage of the normal time. An element observed at 0.80 min with a rating of 110 % has normal time 0.88 min; with 15 % allowances the standard time is 0.88 × 1.15 = 1.012 min. The number of cycles to observe is set statistically from the scatter of the pilot readings and the confidence and accuracy wanted.

Work sampling (activity sampling) makes a large number of instantaneous observations at random times and estimates the proportion p of time spent in an activity — idle, working, waiting. Its size follows the binomial: for an absolute accuracy ±e, n = z²p(1 − p)/e²; for a relative accuracy ±s (a fraction of p), n = z²(1 − p)/(s²p). With p = 0.25, z = 2 for about 95 % confidence and s = 0.10, n = 4 × 0.75/(0.01 × 0.25) = 1200 observations. It needs no stopwatch, suits long and irregular work and group activities, and is cheap per observation. Standard data are element times compiled from previous studies, often as formulas of the variables (length, weight), to set standards for new jobs without timing them. Predetermined motion time systems assign times to basic motions from tables: MTM (methods-time measurement, in time measurement units, 1 TMU = 0.00001 h = 0.036 s), Work-Factor and MOST (Maynard operation sequence technique); they set standards before a job exists and need no performance rating, because the rating is built into the tables.

⚠️ Absolute or relative accuracy changes n by a factor of p
'±10 % accuracy' on p = 0.25 means ±0.025 absolute, not ±0.10. Reading it as ±0.10 absolute gives n = 4 × 0.25 × 0.75/0.01 = 75 — sixteen times too few observations. Always ask whether the stated accuracy is a fraction of p or an absolute proportion.

Ergonomics fits the work to the worker. Anthropometry supplies body dimensions by percentile: clearances (door height, leg room) are designed for the 95th percentile so the large can pass, reaches and control forces for the 5th percentile so the small can manage, and adjustable features (seat height) span the range. The work environment — illumination, noise (exposure in dB(A) and its duration), heat and humidity, vibration — and the design of displays and controls (compatibility of movement, coding by shape and colour) determine fatigue, error and injury. Job evaluation ranks jobs, not people, to build a fair wage structure: non-quantitative methods are ranking and grading (classification); quantitative methods are factor comparison and the point method, which scores each job on weighted factors such as skill, effort, responsibility and working conditions. Merit rating (performance appraisal) rates the person in the job: graphic rating scales, straight ranking, paired comparison (each employee compared with every other, N(N − 1)/2 pairs), checklists, forced choice, critical incidents and behaviourally anchored scales.

5. Facility location and the evaluation of alternatives; plant layout types and their evaluation

Location factors: proximity to markets and to raw materials, availability and cost of labour, transport links, utilities (power, water), land and construction cost, taxes, incentives and regulation, community and climate. Evaluation methods: the factor-rating method scores each site on weighted factors and sums them; the centre-of-gravity method places a distribution facility at X = Σx_iW_i/ΣW_i, Y = Σy_iW_i/ΣW_i, W the volume shipped to each point; the load-distance method picks the site minimising Σ(load × distance); locational break-even (cost-volume) analysis compares total cost F + vQ at each site and finds the volume ranges over which each is cheapest; the transportation model optimises shipping from several sources; and the Brown-Gibson model combines objective (cost) and subjective factor measures. For sites A (fixed Rs 2 lakh, variable Rs 10 per unit) and B (Rs 1 lakh, Rs 15), costs cross where 200 000 + 10Q = 100 000 + 15Q, at Q = 20 000: B is cheaper below, A above.

Types of plant layout
LayoutArrangementSuitsTrade-off
Product (line)Machines in the sequence of operationsHigh volume, low varietyMinimal handling and WIP; inflexible, one breakdown stops the line
Process (functional)Similar machines grouped by functionLow volume, high variety (job shop)Flexible, high utilisation of skills; long flows, high WIP
Fixed positionProduct stays, resources come to itVery large or heavy items: ships, aircraftAvoids moving the product; congestion and scheduling of resources
Cellular (group)Dissimilar machines grouped per part familyMedium volume and varietyLine-like flow for batches; needs part families that are stable

Evaluating a layout. Systematic layout planning (Muther) rates the closeness needed between every pair of departments on a relationship chart — A absolutely necessary, E especially important, I important, O ordinary, U unimportant, X undesirable — and builds a layout honouring them. Quantitatively, a layout is scored by the load-distance (flow-distance) total Σf_ij d_ij, or its cost equivalent. CRAFT is an improvement algorithm: starting from an existing layout it swaps pairs of departments whenever the swap lowers the flow-cost total. ALDEP and CORELAP are construction algorithms that build a layout from the relationship chart.

6. Assembly line balancing and material handling systems

Line balancing assigns tasks to workstations, respecting precedence, so that no station's work exceeds the cycle time C = available production time/required output. The theoretical minimum number of stations is N_min = ⌈Σt_i/C⌉ (rounded up). Line efficiency = Σt_i/(N × C), balance delay = 1 − efficiency, and the smoothness index SI = √[Σ(S_max − S_i)²] measures how evenly the work is spread. Heuristics: the largest candidate rule (assign the longest task whose predecessors are done and that fits), the Kilbridge-Wester column method (group tasks into precedence columns), and the ranked positional weight method (rank tasks by their own time plus the times of all tasks that follow them).

🧠 A line balanced once, end to end
Tasks (min): A 0.5, B 0.8, C 0.6, D 0.9, E 0.4, F 0.5, G 0.5; A precedes B and C, B precedes D, C precedes E, D and E precede F, F precedes G. Demand 400 units in a 480-min shift gives C = 1.2 min; Σt = 4.2 min, so N_min = ⌈3.5⌉ = 4. Largest candidate: station 1 A + C = 1.1 (B would make 1.3); station 2 B + E = 1.2; station 3 D = 0.9 (adding F would make 1.4); station 4 F + G = 1.0. Four stations meet the minimum; efficiency = 4.2/(4 × 1.2) = 87.5 %, balance delay 12.5 %, SI = √(0.1² + 0² + 0.3² + 0.2²) = 0.374.

Material handling adds cost but no value, so the aim is to move less, not to move faster. Its principles: plan the system as a whole; move material in unit loads (pallets, containers) rather than piece by piece; minimise distance and the number of handlings, keeping flow in straight lines; use gravity wherever possible; standardise and mechanise equipment; keep the handled load flexible to changes; and consider energy, safety and ergonomics. Equipment falls into conveyors (belt, roller, chain, overhead trolley — fixed path, high volume), cranes and hoists (EOT, jib and gantry cranes — heavy loads over an area), industrial trucks (forklifts, pallet trucks and automated guided vehicles — variable paths), automated storage and retrieval systems (AS/RS) with computer-controlled stacker cranes, and positioning and unitising equipment.

Key takeaways

  • Worst-case stack ΣT, statistical stack √(ΣT²); Taguchi loss k(y − m)²; value = function/cost; DFA index 3N_min/t_total.
  • Taylor gave time study, functional foremanship and the differential piece-rate; the Gilbreths gave motion study, therbligs, micro-motion film and the SIMO chart.
  • Standard time = observed × rating × (1 + allowance); work sampling n = z²p(1 − p)/e² for absolute and z²(1 − p)/(s²p) for relative accuracy; 1 TMU = 0.036 s; PMTS needs no rating.
  • Centre of gravity X = Σx_iW_i/ΣW_i; locational break-even where the total-cost lines cross; product layout for high volume, process layout for high variety; CRAFT improves, ALDEP and CORELAP construct.
  • Cycle time = available time/demand; N_min = ⌈Σt/C⌉; efficiency = Σt/(NC); move material in unit loads, in straight lines, as little as possible.

Practice questions (18)

Attempt each one before opening the answer. Every explanation names the tempting wrong option as well as the right one, because that is where marks are lost.

  1. Value engineering seeks to

    1. raise the selling price of a product by improving its appearance
    2. provide the required function at the lowest total cost without loss of quality
    3. reduce cost by using cheaper materials whatever the effect on function
    4. add features to increase the esteem value
    Show answer

    Answer: B — provide the required function at the lowest total cost without loss of quality

    Value = function/cost, and value engineering raises it by securing the necessary function more cheaply — never by giving up function, reliability or quality. Cutting cost regardless of function is cost-cutting, not value engineering, and adding esteem features raises cost without addressing the basic function.
  2. At which stage of the product life cycle do sales level off, competition is strongest and the production emphasis shifts to cost reduction?

    1. Introduction
    2. Growth
    3. Maturity
    4. Decline
    Show answer

    Answer: C — Maturity

    In maturity the market is saturated, many competitors fight on price, and efficient high-volume production is what protects the margin. Growth has rapidly rising sales, introduction has low sales and frequent design changes, and decline has falling sales and a rationalising range.
  3. Three parts stacked in an assembly have tolerances of ±0.02, ±0.03 and ±0.06 mm. Assuming independent, normally distributed and centred dimensions, what is the statistical (root-sum-square) tolerance of the assembly?

    1. ±0.11 mm
    2. ±0.07 mm
    3. ±0.037 mm
    4. ±0.049 mm
    Show answer

    Answer: B — ±0.07 mm

    T = √(0.02² + 0.03² + 0.06²) = √(0.0004 + 0.0009 + 0.0036) = √0.0049 = ±0.07 mm. ±0.11 mm is the worst-case (linear) sum, and ±0.049 is 0.0049 without the square root — the slip of forgetting to take the root.
  4. Using Taguchi's quadratic loss function, a deviation of 0.5 mm from target costs Rs 100. What loss, in rupees, does a deviation of 0.2 mm cause?

    Numerical answer — type the value.

    Show answer

    Answer: 16

    L = k(y − m)², so k = 100/0.5² = 400 Rs/mm² and L(0.2) = 400 × 0.04 = Rs 16. Scaling linearly with the deviation gives Rs 40, which forgets that the loss grows as the square — the defining feature of Taguchi's function.
  5. An assembly of 12 parts takes 60 s to assemble, and analysis shows that only 4 parts are theoretically essential. What is its Boothroyd-Dewhurst DFA index, taking 3 s as the ideal time per part?

    1. 20 %
    2. 33 %
    3. 60 %
    4. 6.7 %
    Show answer

    Answer: A — 20 %

    DFA index = 3N_min/t_total = 3 × 4/60 = 0.20, i.e. 20 %. 33 % is simply 4/12, the fraction of parts that are essential, which ignores assembly time; 60 % uses all 12 parts in the numerator, which defeats the purpose of counting essential parts.
  6. Which of the following statements about product development are correct?

    1. Concurrent engineering uses cross-functional teams working on product and process design in parallel
    2. Simplification reduces the number of varieties of a product
    3. Concurrent engineering typically lengthens time to market because more departments are involved
    4. Design for assembly aims to reduce the number of parts
    Show answer

    Answer: A — Concurrent engineering uses cross-functional teams working on product and process design in parallel; B — Simplification reduces the number of varieties of a product; D — Design for assembly aims to reduce the number of parts

    Concurrent engineering works in parallel with cross-functional teams, simplification cuts varieties, and DFA's first rule is fewer parts. The whole point of concurrent engineering is that parallel work and early problem-finding SHORTEN time to market and reduce late engineering changes, so the third statement is false.
  7. The subdivision of manual work into elemental motions called therbligs, and their study from film, is due to

    1. F. W. Taylor
    2. Frank and Lillian Gilbreth
    3. Henry Gantt
    4. Elton Mayo
    Show answer

    Answer: B — Frank and Lillian Gilbreth

    The Gilbreths founded motion study; 'therblig' is Gilbreth spelled nearly backwards, and micro-motion study with a clock in the film frame is theirs. Taylor's contribution was time study and scientific management, Gantt is known for his chart and task-and-bonus plan, and Mayo for the Hawthorne studies of human relations.
  8. In an ASME flow process chart, which symbol denotes inspection?

    1. Circle
    2. Square
    3. Arrow
    4. Inverted triangle
    Show answer

    Answer: B — Square

    The five symbols are: circle for operation, square for inspection, arrow for transport, a capital D for delay and a triangle for storage. The circle is the tempting wrong answer because operations are the most frequent entry on any chart.
  9. An element is observed to take 0.80 min on average, the worker is rated at 110 %, and allowances are 15 % of normal time. What is the standard time in minutes? (Answer to three decimal places.)

    Numerical answer — type the value.

    Show answer

    Answer: 1.012

    Normal time = 0.80 × 1.10 = 0.88 min; standard time = 0.88 × (1 + 0.15) = 1.012 min. Applying the allowance to the observed time instead, 0.80 × 1.15 = 0.92 min, skips the rating; treating the allowance as a fraction of the standard time, 0.88/0.85 = 1.035 min, uses the other convention, which the question rules out.
  10. A pilot work-sampling study shows a machine idle 25 % of the time. How many observations are needed to estimate the idle proportion within ±10 % of its true value (relative accuracy) at a confidence level for which z = 2?

    Numerical answer — type the value.

    Show answer

    Answer: 1200

    Relative accuracy s = 0.10 means an absolute error of 0.10 × 0.25 = 0.025. n = z²p(1 − p)/e² = 4 × 0.25 × 0.75/0.025² = 0.75/0.000625 = 1200, the same as z²(1 − p)/(s²p). Reading ±10 % as ±0.10 absolute gives only 75 observations — sixteen times too few.
  11. In methods-time measurement, one time measurement unit (TMU) equals

    1. 0.0001 hour
    2. 0.036 second
    3. 0.36 second
    4. 0.001 minute
    Show answer

    Answer: B — 0.036 second

    1 TMU = 0.00001 hour = 0.0006 minute = 0.036 second, chosen so that basic motions have convenient whole-number values. 0.0001 hour and 0.36 s are ten times too large, and 0.001 minute is 0.06 s — none is the defined unit.
  12. Which of the following statements about ergonomics, job evaluation and merit rating are correct?

    1. The point method of job evaluation is a quantitative method
    2. The ranking method of job evaluation assigns weighted points to each job factor
    3. A door height should be designed for about the 95th percentile of stature
    4. Paired-comparison merit rating of 6 employees needs 15 comparisons
    Show answer

    Answer: A — The point method of job evaluation is a quantitative method; C — A door height should be designed for about the 95th percentile of stature; D — Paired-comparison merit rating of 6 employees needs 15 comparisons

    The point method scores weighted factors, so it is quantitative; clearances are designed for the large, around the 95th percentile; paired comparison needs N(N − 1)/2 = 6 × 5/2 = 15 comparisons. Ranking simply orders whole jobs by judgement with no factor points — it is the simplest non-quantitative method, so the second statement is false.
  13. A warehouse is to serve three stores at coordinates (2, 3), (5, 1) and (8, 6) km, receiving 100, 200 and 300 tonnes a month respectively. Where does the centre-of-gravity method place it?

    1. (5.00, 3.33)
    2. (6.00, 3.83)
    3. (6.50, 4.17)
    4. (5.50, 3.50)
    Show answer

    Answer: B — (6.00, 3.83)

    X = (2 × 100 + 5 × 200 + 8 × 300)/600 = 3600/600 = 6.00 and Y = (3 × 100 + 1 × 200 + 6 × 300)/600 = 2300/600 = 3.83. (5.00, 3.33) is the unweighted average of the three points, which ignores that the largest store pulls the warehouse towards itself.
  14. Site A has fixed costs of Rs 2 00 000 a year and a variable cost of Rs 10 per unit; site B has Rs 1 00 000 and Rs 15. For an expected volume of 30 000 units a year, which site is cheaper, and what is the break-even volume?

    1. A; 20 000 units
    2. B; 20 000 units
    3. A; 12 000 units
    4. B; 30 000 units
    Show answer

    Answer: A — A; 20 000 units

    The cost lines cross where 200 000 + 10Q = 100 000 + 15Q, i.e. Q = 100 000/5 = 20 000 units. At 30 000 units A costs 200 000 + 300 000 = Rs 5 00 000 and B costs 100 000 + 450 000 = Rs 5 50 000, so A is cheaper: above the break-even, the site with the lower variable cost wins. Choosing B because its fixed cost is lower is the trap.
  15. A job shop makes a wide variety of products in small batches, each with a different routing. Which layout suits it?

    1. Product (line) layout
    2. Process (functional) layout
    3. Fixed-position layout
    4. A single continuous flow line
    Show answer

    Answer: B — Process (functional) layout

    With many routings and low volumes, grouping similar machines by function lets every job visit the departments it needs in its own order. A product layout needs high volume of a standard product to justify dedicating equipment, and a fixed-position layout is for items too large to move.
  16. Seven assembly tasks total 4.2 min of work. The line must produce 400 units in a 480-minute shift and is balanced into 4 workstations. What is the line efficiency in percent? (Answer to one decimal place.)

    Numerical answer — type the value.

    Show answer

    Answer: 87.5

    Cycle time C = 480/400 = 1.2 min. Efficiency = Σt/(N × C) = 4.2/(4 × 1.2) = 0.875 = 87.5 %, so the balance delay is 12.5 %. Using the longest station time instead of the cycle time would measure the balance of the stations rather than the line's efficiency against demand.
  17. Tasks totalling 4.2 min are to be balanced for a cycle time of 1.2 min. What is the theoretical minimum number of workstations?

    1. 3
    2. 3.5
    3. 4
    4. 5
    Show answer

    Answer: C — 4

    N_min = ⌈Σt/C⌉ = ⌈4.2/1.2⌉ = ⌈3.5⌉ = 4. Stations are whole, so the ratio is always rounded UP: three stations of 1.2 min provide only 3.6 min of capacity for 4.2 min of work. Whether 4 is actually achievable depends on the precedence and task times.
  18. Which principle of material handling recommends moving material on pallets or in containers rather than piece by piece?

    1. Gravity principle
    2. Unit load principle
    3. Straight-line flow principle
    4. Standardisation principle
    Show answer

    Answer: B — Unit load principle

    The unit load principle says to handle as large a unit as practical — a pallet or container of parts — to reduce the number of moves. Gravity means using gravity to move material, straight-line flow means avoiding backtracking, and standardisation concerns the equipment and methods.