Planning and Controlling — Setting the Course and Checking It

Planning is deciding in advance what to do, how to do it, when, and who is to do it. It bridges the gap between where an organisation is and where it wants to be, and it is the first function of management because every other function works to a plan. Controlling is the last function: it checks that work is going according to plan and corrects it when it is not. The two are the ends of one loop — the standards planning sets are exactly what controlling measures against, and what controlling finds feeds the next plan. CUET asks the features, importance and limitations of each, the steps of each process, the eight types of plan, and two techniques of control by name. Most of it is set as a short case, so the signal words below matter.

Planning: Features, Importance and Limitations

The three lists, side by side
FeaturesImportanceLimitations
Focuses on achieving objectivesProvides directionLeads to rigidity
Primary function of managementReduces the risks of uncertaintyMay not work in a dynamic environment
Pervasive — at every levelReduces overlapping and wasteful activitiesReduces creativity
ContinuousPromotes innovative ideasInvolves huge costs
Futuristic — looks aheadFacilitates decision-makingTime-consuming
Involves decision-making, and is a mental exercise — thinking before doingEstablishes standards for controllingDoes not guarantee success
⚠️ Rigidity and the dynamic environment are two different limitations
Rigidity is about the people: once a plan is fixed, managers feel bound to follow it even when circumstances call for a change. May not work in a dynamic environment is about the world: conditions change so fast that no plan made in advance can anticipate them. A case in which managers refuse to deviate from the plan is rigidity; a case in which an unforeseeable change makes the plan obsolete is the dynamic environment.

The Planning Process

  1. Setting objectives — what the organisation wants to achieve, stated clearly and, where possible, in numbers.
  2. Developing premises — the assumptions about the future on which the plan rests: expected demand, prices, government policy. Forecasting supplies them.
  3. Identifying alternative courses of action.
  4. Evaluating the alternatives — weighing the positive and negative aspects of each.
  5. Selecting an alternative — the real point of decision-making.
  6. Implementing the plan — putting it into action.
  7. Follow-up action — monitoring the plan to ensure it is carried out as intended.
📖 Which step is this?
A furniture maker wants to raise sales by 25% next year. Its managers assume that housing construction will keep growing and that timber prices will stay stable — those assumptions are premises. They then list three ways to grow: open new showrooms, sell online, or supply hotels — identifying alternatives. They compare the cost and likely return of each — evaluating. They choose online sales — selecting. Putting a website live is implementing, and checking monthly sales against the target is follow-up.

Types of Plans

Plans are first divided by how often they are used. A single-use plan is made for a one-time event that will not recur — a programme or a budget for a particular project. A standing plan is used again and again for repetitive situations — policies, procedures, methods and rules. The eight types the book lists are below; the four in the middle of the table are the ones most often confused.

The eight types of plan
TypeWhat it isExample
ObjectiveThe end result the organisation seeksIncrease sales by 10% this year
StrategyA comprehensive plan for the long-term direction, formed in the light of the environmentEnter rural markets with smaller, cheaper packs
PolicyA general statement that guides thinking and leaves room for discretionWe prefer to promote from within
ProcedureThe chronological sequence of steps for carrying out a policyThe steps for processing a customer’s refund request
MethodThe prescribed way of performing one task within a procedureTraining by lecture rather than by demonstration
RuleA specific statement of what must or must not be done — no discretionNo smoking on the factory floor
ProgrammeA detailed statement about a project — objectives, policies, procedures, rules, tasks, resources and budget togetherThe plan for setting up a new plant
BudgetA plan expressed in numerical terms for a future periodA sales budget of 40,000 units worth ₹2 crore
🧠 The discretion test
Ask whether the manager has any choice. If the statement guides but leaves the decision open — "prefer", "generally", "as far as possible" — it is a policy. If it leaves no choice and carries a penalty for breach, it is a rule. If it lists steps in order, it is a procedure; if it describes how ONE of those steps is done, it is a method.

Controlling: Importance, Process and Its Link to Planning

Controlling ensures that the organisation’s resources are used effectively and efficiently to achieve its goals. Its importance: accomplishing organisational goals, judging the accuracy of standards (a standard that is always missed or always beaten is badly set), making efficient use of resources, improving employee motivation (people know in advance what they will be judged on), ensuring order and discipline, and facilitating coordination. Its limitations: difficulty in setting quantitative standards for things like employee morale, little control over external factors such as government policy or a competitor’s moves, resistance from employees who feel watched, and cost — a small firm cannot afford elaborate control systems.

  1. Setting performance standards — the benchmarks, in quantitative terms where possible (units, cost, time).
  2. Measuring actual performance — objectively and reliably, by personal observation, sample checking or reports.
  3. Comparing actual performance with standards — to find any deviation.
  4. Analysing deviations — using critical point control (focus on the key result areas where a deviation matters most) and management by exception (act only on significant deviations beyond a permissible limit; let minor ones pass).
  5. Taking corrective action — and, if the deviation cannot be corrected, revising the standard.
⚠️ Critical point control or management by exception?
Both tell a manager not to watch everything, but they decide WHAT to ignore differently. Critical point control picks the AREAS that matter: in a car plant, a 3% rise in the price of steel matters far more than a 20% rise in spending on stationery, so steel is watched closely. Management by exception picks the SIZE of deviation that matters: "report cost overruns above 2%; below that, do not trouble me". If the case names a threshold or a permissible limit, it is management by exception.

The relationship. Planning comes first and controlling follows, yet they depend on each other: planning without controlling is meaningless, because nobody would know whether the plan was being achieved; controlling without planning is blind, because there would be no standards to measure against. Planning is prescriptive — it says what should be done; controlling is evaluative — it says whether it was done well. And although planning looks ahead and controlling is often called looking back, the book stresses that both are forward-looking as well as backward-looking: plans are revised in the light of past experience, and controlling aims to improve future performance.

Key takeaways

  • Planning is the primary, pervasive, continuous, futuristic, decision-making mental exercise; it provides direction, reduces uncertainty and waste, and sets the standards controlling uses.
  • Limitations of planning: rigidity, failure in a dynamic environment, reduced creativity, huge cost, time, and no guarantee of success.
  • Planning process: objectives → premises → alternatives → evaluation → selection → implementation → follow-up.
  • Policy leaves discretion; rule leaves none; procedure is a sequence of steps; method is how one step is done; budget is a plan in numbers; programme is a complete project plan.
  • Controlling process: set standards → measure → compare → analyse deviations (critical point control, management by exception) → correct. Planning without controlling is meaningless; controlling without planning is blind.

Practice questions (10)

Attempt each one before opening the answer. Every explanation names the tempting wrong option as well as the right one, because that is where marks are lost.

  1. "Mobile phones are not allowed on the assembly line; anyone found using one will be fined." This is an example of which type of plan?

    1. Policy
    2. Procedure
    3. Rule
    4. Method
    Show answer

    Answer: C — Rule

    A specific statement of what must not be done, leaving no discretion and carrying a penalty, is a rule. A policy would guide thinking but leave room for judgement. A procedure lists the steps of an activity in order, and a method is the way of doing one task; the statement does neither.
  2. While preparing next year’s plan, the managers of a cement company assume that government spending on roads will continue to rise and that coal prices will remain stable. This step of the planning process is:

    1. Developing premises
    2. Setting objectives
    3. Evaluating alternative courses
    4. Follow-up action
    Show answer

    Answer: A — Developing premises

    Assumptions about future conditions on which the plan will rest are its premises, and forecasting is how they are developed. Setting objectives would state what the company wants to achieve, not what it expects the world to do. Evaluating alternatives compares options already identified, and follow-up comes after the plan is implemented.
  3. A company states: "As far as possible, we will buy raw material from suppliers who follow environment-friendly practices." Purchase managers decide in each case which suppliers qualify. This is an example of a:

    1. Rule
    2. Procedure
    3. Method
    4. Policy
    Show answer

    Answer: D — Policy

    A general statement that guides decisions while leaving managers discretion — signalled by "as far as possible" and by managers deciding case by case — is a policy. A rule would leave no choice at all. A procedure would set out the sequence of steps in purchasing, and a method the way of doing one of those steps.
  4. Before launching a new product, a company spent a large sum on market surveys, expert consultants and detailed forecasts, and its finance head complained that the plan had cost more than some of the benefits it would bring. Which limitation of planning does this illustrate?

    1. Planning reduces creativity
    2. Planning involves huge costs
    3. Planning leads to rigidity
    4. Planning does not guarantee success
    Show answer

    Answer: B — Planning involves huge costs

    Spending heavily on surveys, consultants and forecasts, so that the cost of planning rivals its benefit, is the limitation that planning involves huge costs. Rigidity is about managers feeling unable to deviate from a plan, and reduced creativity about subordinates simply carrying out plans made above them. "No guarantee of success" would need the plan to have failed, which the case does not say.
  5. A statement of expected results for the coming year expressed in numerical terms — for example, sales of 60,000 units worth ₹3 crore — is called a:

    1. Strategy
    2. Programme
    3. Budget
    4. Policy
    Show answer

    Answer: C — Budget

    A budget is a plan that states expected results in numerical terms for a future period. A programme is a fuller statement about a whole project — its objectives, policies, procedures, resources and its budget too — so the budget is one part of it. A strategy sets long-term direction, and a policy is a general guide to decisions; neither is defined by being expressed in numbers.
  6. What is the FIRST step in the controlling process?

    1. Measuring actual performance
    2. Setting performance standards
    3. Analysing deviations
    4. Taking corrective action
    Show answer

    Answer: B — Setting performance standards

    Controlling begins by setting the standards against which performance will be judged; without them there is nothing to measure against. Measurement is the second step, comparison the third, analysing deviations the fourth, and corrective action the last. Starting with measurement is the usual slip, because measuring feels like the first practical task.
  7. The production head of a garment unit tells his supervisors: "If material wastage stays within 2% of the standard, do not report it; anything above 2% must be brought to my notice immediately." Which technique of control is he using?

    1. Critical point control
    2. Budgetary planning
    3. Setting performance standards
    4. Management by exception
    Show answer

    Answer: D — Management by exception

    Acting only on deviations beyond a permissible limit and letting minor ones pass is management by exception, and the 2% threshold is its signal. Critical point control is the close distractor, but it chooses the key AREAS to watch rather than a size of deviation below which nothing is reported. Setting standards is a step in the process, not a technique for analysing deviations, and budgetary planning is not what the instruction describes.
  8. In a car factory, the manager watches the cost of steel and engine components very closely but pays little attention to spending on stationery, since a small rise in steel cost hurts profit far more than a large rise in stationery. This approach is:

    1. Critical point control
    2. Management by exception
    3. Follow-up action
    4. Measuring actual performance
    Show answer

    Answer: A — Critical point control

    Concentrating control on the key result areas whose deviation affects the organisation most — here steel and engine parts — is critical point control. Management by exception sets a threshold size of deviation for every area rather than choosing which areas matter, so it fits a case that names a permissible limit, not this one. Follow-up is the last step of planning, and measurement is a step of controlling rather than a way of choosing what to watch.
  9. Which of the following statements correctly describes the relationship between planning and controlling?

    1. Controlling can be performed without planning, since it only looks at past results
    2. Planning is evaluative and controlling is prescriptive
    3. Planning without controlling is meaningless, and controlling without planning is blind
    4. Planning looks only forward and controlling looks only backward
    Show answer

    Answer: C — Planning without controlling is meaningless, and controlling without planning is blind

    The two depend on each other: without control nobody knows whether a plan is being achieved, and without a plan there are no standards to control against. Calling planning evaluative and controlling prescriptive swaps the labels — planning is prescriptive and controlling evaluative. The claim that controlling can work without planning ignores that it needs standards, which only planning supplies. And "planning looks only forward, controlling only backward" is the half-truth the book corrects: both are forward-looking and backward-looking, since plans draw on past experience and control aims to improve the future.
  10. For six months running, every machine operator in a plant fell well short of the output standard despite working steadily. On review, management found the standard had been set without allowing for machine set-up time, and revised it. Which importance of controlling does this illustrate?

    1. Ensuring order and discipline
    2. Judging the accuracy of standards
    3. Improving employee motivation
    4. Facilitating coordination
    Show answer

    Answer: B — Judging the accuracy of standards

    A good control system reveals whether the standards themselves are realistic; a standard that every steady worker misses is badly set, and revising it is the payoff. Order and discipline would concern checking dishonest or careless behaviour, which the case rules out by saying the operators worked steadily. Motivation and coordination are real benefits of control, but neither is what the revision of an unrealistic standard shows.