Planning and Controlling — Setting the Course and Checking It
The Planning Process
- Setting objectives — what the organisation wants to achieve, stated clearly and, where possible, in numbers.
- Developing premises — the assumptions about the future on which the plan rests: expected demand, prices, government policy. Forecasting supplies them.
- Identifying alternative courses of action.
- Evaluating the alternatives — weighing the positive and negative aspects of each.
- Selecting an alternative — the real point of decision-making.
- Implementing the plan — putting it into action.
- Follow-up action — monitoring the plan to ensure it is carried out as intended.
Types of Plans
Plans are first divided by how often they are used. A single-use plan is made for a one-time event that will not recur — a programme or a budget for a particular project. A standing plan is used again and again for repetitive situations — policies, procedures, methods and rules. The eight types the book lists are below; the four in the middle of the table are the ones most often confused.
| Type | What it is | Example |
|---|---|---|
| Objective | The end result the organisation seeks | Increase sales by 10% this year |
| Strategy | A comprehensive plan for the long-term direction, formed in the light of the environment | Enter rural markets with smaller, cheaper packs |
| Policy | A general statement that guides thinking and leaves room for discretion | We prefer to promote from within |
| Procedure | The chronological sequence of steps for carrying out a policy | The steps for processing a customer’s refund request |
| Method | The prescribed way of performing one task within a procedure | Training by lecture rather than by demonstration |
| Rule | A specific statement of what must or must not be done — no discretion | No smoking on the factory floor |
| Programme | A detailed statement about a project — objectives, policies, procedures, rules, tasks, resources and budget together | The plan for setting up a new plant |
| Budget | A plan expressed in numerical terms for a future period | A sales budget of 40,000 units worth ₹2 crore |
Controlling: Importance, Process and Its Link to Planning
Controlling ensures that the organisation’s resources are used effectively and efficiently to achieve its goals. Its importance: accomplishing organisational goals, judging the accuracy of standards (a standard that is always missed or always beaten is badly set), making efficient use of resources, improving employee motivation (people know in advance what they will be judged on), ensuring order and discipline, and facilitating coordination. Its limitations: difficulty in setting quantitative standards for things like employee morale, little control over external factors such as government policy or a competitor’s moves, resistance from employees who feel watched, and cost — a small firm cannot afford elaborate control systems.
- Setting performance standards — the benchmarks, in quantitative terms where possible (units, cost, time).
- Measuring actual performance — objectively and reliably, by personal observation, sample checking or reports.
- Comparing actual performance with standards — to find any deviation.
- Analysing deviations — using critical point control (focus on the key result areas where a deviation matters most) and management by exception (act only on significant deviations beyond a permissible limit; let minor ones pass).
- Taking corrective action — and, if the deviation cannot be corrected, revising the standard.
The relationship. Planning comes first and controlling follows, yet they depend on each other: planning without controlling is meaningless, because nobody would know whether the plan was being achieved; controlling without planning is blind, because there would be no standards to measure against. Planning is prescriptive — it says what should be done; controlling is evaluative — it says whether it was done well. And although planning looks ahead and controlling is often called looking back, the book stresses that both are forward-looking as well as backward-looking: plans are revised in the light of past experience, and controlling aims to improve future performance.
Key takeaways
- Planning is the primary, pervasive, continuous, futuristic, decision-making mental exercise; it provides direction, reduces uncertainty and waste, and sets the standards controlling uses.
- Limitations of planning: rigidity, failure in a dynamic environment, reduced creativity, huge cost, time, and no guarantee of success.
- Planning process: objectives → premises → alternatives → evaluation → selection → implementation → follow-up.
- Policy leaves discretion; rule leaves none; procedure is a sequence of steps; method is how one step is done; budget is a plan in numbers; programme is a complete project plan.
- Controlling process: set standards → measure → compare → analyse deviations (critical point control, management by exception) → correct. Planning without controlling is meaningless; controlling without planning is blind.
Practice questions (10)
Attempt each one before opening the answer. Every explanation names the tempting wrong option as well as the right one, because that is where marks are lost.
"Mobile phones are not allowed on the assembly line; anyone found using one will be fined." This is an example of which type of plan?
Show answer
Answer: C — Rule
A specific statement of what must not be done, leaving no discretion and carrying a penalty, is a rule. A policy would guide thinking but leave room for judgement. A procedure lists the steps of an activity in order, and a method is the way of doing one task; the statement does neither.While preparing next year’s plan, the managers of a cement company assume that government spending on roads will continue to rise and that coal prices will remain stable. This step of the planning process is:
Show answer
Answer: A — Developing premises
Assumptions about future conditions on which the plan will rest are its premises, and forecasting is how they are developed. Setting objectives would state what the company wants to achieve, not what it expects the world to do. Evaluating alternatives compares options already identified, and follow-up comes after the plan is implemented.A company states: "As far as possible, we will buy raw material from suppliers who follow environment-friendly practices." Purchase managers decide in each case which suppliers qualify. This is an example of a:
Show answer
Answer: D — Policy
A general statement that guides decisions while leaving managers discretion — signalled by "as far as possible" and by managers deciding case by case — is a policy. A rule would leave no choice at all. A procedure would set out the sequence of steps in purchasing, and a method the way of doing one of those steps.Before launching a new product, a company spent a large sum on market surveys, expert consultants and detailed forecasts, and its finance head complained that the plan had cost more than some of the benefits it would bring. Which limitation of planning does this illustrate?
Show answer
Answer: B — Planning involves huge costs
Spending heavily on surveys, consultants and forecasts, so that the cost of planning rivals its benefit, is the limitation that planning involves huge costs. Rigidity is about managers feeling unable to deviate from a plan, and reduced creativity about subordinates simply carrying out plans made above them. "No guarantee of success" would need the plan to have failed, which the case does not say.A statement of expected results for the coming year expressed in numerical terms — for example, sales of 60,000 units worth ₹3 crore — is called a:
Show answer
Answer: C — Budget
A budget is a plan that states expected results in numerical terms for a future period. A programme is a fuller statement about a whole project — its objectives, policies, procedures, resources and its budget too — so the budget is one part of it. A strategy sets long-term direction, and a policy is a general guide to decisions; neither is defined by being expressed in numbers.What is the FIRST step in the controlling process?
Show answer
Answer: B — Setting performance standards
Controlling begins by setting the standards against which performance will be judged; without them there is nothing to measure against. Measurement is the second step, comparison the third, analysing deviations the fourth, and corrective action the last. Starting with measurement is the usual slip, because measuring feels like the first practical task.The production head of a garment unit tells his supervisors: "If material wastage stays within 2% of the standard, do not report it; anything above 2% must be brought to my notice immediately." Which technique of control is he using?
Show answer
Answer: D — Management by exception
Acting only on deviations beyond a permissible limit and letting minor ones pass is management by exception, and the 2% threshold is its signal. Critical point control is the close distractor, but it chooses the key AREAS to watch rather than a size of deviation below which nothing is reported. Setting standards is a step in the process, not a technique for analysing deviations, and budgetary planning is not what the instruction describes.In a car factory, the manager watches the cost of steel and engine components very closely but pays little attention to spending on stationery, since a small rise in steel cost hurts profit far more than a large rise in stationery. This approach is:
Show answer
Answer: A — Critical point control
Concentrating control on the key result areas whose deviation affects the organisation most — here steel and engine parts — is critical point control. Management by exception sets a threshold size of deviation for every area rather than choosing which areas matter, so it fits a case that names a permissible limit, not this one. Follow-up is the last step of planning, and measurement is a step of controlling rather than a way of choosing what to watch.Which of the following statements correctly describes the relationship between planning and controlling?
Show answer
Answer: C — Planning without controlling is meaningless, and controlling without planning is blind
The two depend on each other: without control nobody knows whether a plan is being achieved, and without a plan there are no standards to control against. Calling planning evaluative and controlling prescriptive swaps the labels — planning is prescriptive and controlling evaluative. The claim that controlling can work without planning ignores that it needs standards, which only planning supplies. And "planning looks only forward, controlling only backward" is the half-truth the book corrects: both are forward-looking and backward-looking, since plans draw on past experience and control aims to improve the future.For six months running, every machine operator in a plant fell well short of the output standard despite working steadily. On review, management found the standard had been set without allowing for machine set-up time, and revised it. Which importance of controlling does this illustrate?
Show answer
Answer: B — Judging the accuracy of standards
A good control system reveals whether the standards themselves are realistic; a standard that every steady worker misses is badly set, and revising it is the payoff. Order and discipline would concern checking dishonest or careless behaviour, which the case rules out by saying the operators worked steadily. Motivation and coordination are real benefits of control, but neither is what the revision of an unrealistic standard shows.