Highway Capacity, Intersections and Interchanges, Accident Studies and Four-Step Travel Demand Modelling

Section 6 of the Civil Engineering paper names five things the earlier Transportation chapters do not teach: road classification and the design vehicle, peak-hour factor with capacity and level of service, types of intersections and interchanges, accident studies, and — a new heading in the 2027 list — Transportation Planning by the four-step travel-demand model. The traffic-engineering chapter built flow theory and Webster's signal design; this one supplies the surrounding questions. Classification is by function and administration: National Highways, State Highways, Major and Other District Roads, Village Roads, with the design vehicle (the largest regular user) governing widths and turning radii. Capacity is the most vehicles a lane can pass per hour, and the peak-hour factor corrects an hourly count for the busiest quarter-hour inside it. Intersections are conflict machines: a four-leg uncontrolled junction has 32 conflict points and a three-leg one 9, and every design — signals, channelisation, a rotary, a grade separation — removes some of them. Planning replaces a forecast by four questions in sequence: how many trips start and end in each zone (generation), where they go (distribution), by which mode (choice) and on which route (assignment). Computed here: an hourly volume of 1200 with a busiest quarter-hour of 360 has PHF 0.833; a gravity model splits 1000 trips 727.3 / 272.7 between two zones; and the user-equilibrium route flows differ from the system optimum (666.7 against 500 on route 1).
Overview

Road Classification, Design Vehicle, Peak-Hour Factor and Level of Service

2 min read · 3 parts

Classification. By administration the roads of India are National Highways (NH) (main arteries linking states, ports and capitals), State Highways (SH), Major District Roads (MDR), Other District Roads (ODR) and Village Roads (VR) — the hierarchy of the Nagpur Road Plan of 1943, extended later by expressways. By location and function the IRC also distinguishes expressways (access-controlled, grade-separated), arterial, sub-arterial, collector and local streets in urban areas. The design vehicle is the largest vehicle that regularly uses the road; its length, width and turning radius fix lane width, widening on curves, kerb radii at junctions and ramp geometry, while the design speed governs sight distance and curvature. Passenger car unit (PCU) expresses a mixed stream in car equivalents: 600 cars, 100 trucks at 3 PCU and 200 two-wheelers at 0.5 PCU make 1000 PCU/h. (The PCU values themselves come from the IRC tables and depend on road type; use the values the question gives.)

Capacity, PHF and level of service. Capacity is the maximum hourly flow a lane or road can carry under prevailing conditions; basic (ideal) capacity is for ideal geometry and a passenger-car stream, and the practical capacity and possible capacity are what remains under real conditions. Hourly volume hides peaking, so PHF = hourly volume / (4 × maximum 15-minute volume) (between 0.25 and 1): for 1200 veh/h with a busiest quarter-hour of 360, PHF = 0.833, and the design flow rate is 1200/0.833 = 1440 veh/h. Level of service (LOS) grades the operating quality from A (free flow) to F (breakdown, forced flow) by density, speed or volume/capacity ratio; design usually targets LOS B–C for rural highways and C–D for urban ones, and it is the ratio of demand to capacity (v/c) that moves a facility down the scale. A facility at LOS F is not necessarily at v/c = 1: queues form once demand exceeds capacity and discharge falls.

Roads by administration, highest to lowest
  1. National Highways (NH)
  2. State Highways (SH)
  3. Major District Roads (MDR)
  4. Other District Roads (ODR)
  5. Village Roads (VR)
The hierarchy of the Nagpur Road Plan of 1943.

Classification. By administration the roads of India are National Highways (NH) (main arteries linking states, ports and capitals), State Highways (SH), Major District Roads (MDR), Other…

Intersections, Rotaries and Interchanges

1 min read · 1 part

Intersections are classified as at-grade (all movements share one level) or grade-separated (interchanges). A conflict point is where two streams cross, merge or diverge. An unsignalised four-leg junction has 32 (8 diverging, 8 merging, 16 crossing), a three-leg (T) junction 9 (3, 3, 3); signal control cuts the number actually met by separating movements in time, so the point is that crossing conflicts are the dangerous ones and signals, one-way streets, channelising islands and turning bans each remove some. A rotary (roundabout) converts crossing conflicts into weaving: the circulating vehicles weave rather than cross, so the design variables are the entry width e, the weaving width w, the weaving length l and the proportion p of weaving traffic. The IRC practical capacity of the weaving section is Q_p = 280 w (1 + e/w)(1 − p/3) / (1 + w/l) passenger-car units per hour, for w between 6 and 18 m and w/l between 0.12 and 0.4 (quoted as recalled — confirm against the code). A rotary suits balanced volumes on four to six legs and fails when one flow dominates or pedestrians are many.

Interchanges separate the crossing movements vertically. Trumpet (three legs: one loop, direct ramps), diamond (four legs: simple ramps onto the minor road, which then meets it at-grade — cheap, but the ramp terminals still conflict), cloverleaf (four legs, four loops for right-turns in left-traffic countries, none of the crossing conflicts but weaving between adjacent loops and large land take) and directional / stack (flyover ramps for every turn, highest capacity and cost). The choice is driven by turning volumes, land, and cost. Signs are mandatory/regulatory (circle), cautionary/warning (triangle) and informatory (rectangle), and the colours follow the same classes: that is the structure the syllabus calls "traffic signs".

Intersections are classified as at-grade (all movements share one level) or grade-separated (interchanges). A conflict point is where two streams cross, merge or diverge. An unsignalised…

Accident Studies and Sampling Traffic Data

1 min read · 2 parts

Accident analysis starts from the police record and ends in remedial measures. Tools: the collision diagram (each accident drawn on a plan of the site, revealing a repeating pattern), the condition diagram (the physical features at the site), and the spot map (locations across a network, clustering the black spots). Rates make sites comparable: per 100 million vehicle-kilometres, R = (accidents × 10⁸) / (AADT × 365 × L) for a road section of length L km, and per million entering vehicles at an intersection. Example: 12 accidents a year on a 5 km section with AADT 8000 gives vehicle-km = 8000 × 365 × 5 = 14.6 million, so R = 82.2 per 10⁸ vehicle-km. Causes are classed as road, vehicle, driver and environment; remedies are the three E's — engineering, enforcement, education — and the benefit of an engineering fix is judged by a before-and-after comparison that allows for regression to the mean (sites chosen for being bad tend to improve on their own).

Statistical analysis of traffic data. Spot-speed samples are summarised by the mean, the 85th percentile speed (the common basis for a speed limit and for design speed) and the 15th percentile (the lower limit on a speed zone). The sample size needed so that the mean speed is within e of the true mean at 95% confidence is n = (z s / e)²: with s = 8 km/h and e = 2 km/h, n = (1.96 × 8/2)² = 61.5, so 62 observations. Volume counts are Poisson-like in short intervals and approximately normal in aggregate, which is what lets confidence limits be put on a count; the peak-hour factor and the K-factor (design-hour volume as a fraction of AADT, usually the 30th highest hour) bring that variability into design.

Accident analysis starts from the police record and ends in remedial measures. Tools: the collision diagram (each accident drawn on a plan of the site, revealing a repeating pattern), the…

The Four-Step Travel Demand Model

2 min read · 3 parts

1. Trip generation predicts, for each zone, the trips produced (origins, from household size, income, vehicle ownership) and attracted (destinations, from employment, floor area); methods are multiple regression and cross-classification (trips per household by category). Productions and attractions are balanced to equal totals. 2. Trip distribution spreads each zone's trips over destinations. The gravity model: T_ij = P_i A_j F_ij / Σ_j A_j F_ij, with the friction factor F_ij falling with travel time (commonly 1/t²). Zone 1 produces 1000 trips; zones 2 and 3 attract 200 and 300 at 10 and 20 minutes: F = 0.01 and 0.0025, so T₁₂ = 1000×200×0.01/(200×0.01 + 300×0.0025) = 727.3 and T₁₃ = 272.7 — the nearer zone takes the larger share even though it attracts fewer trips. Growth-factor methods (Fratar) update an observed matrix instead. 3. Mode choice splits each flow among modes; the multinomial logit model gives P_m = e^(U_m) / Σ_k e^(U_k) with utility U linear in time and cost: with U = −0.05 × minutes, a car at 20 min against a bus at 30 min gets e⁻¹/(e⁻¹ + e^(−1.5)) = 0.622.

4. Traffic assignment loads the modal flows on routes. All-or-nothing puts everything on the shortest path (ignoring congestion). User equilibrium (Wardrop's first principle): no traveller can reduce their own time by switching, so used routes have equal travel time. System optimum (second principle): total travel time is minimised, which equalises marginal cost. Congested link times are modelled by the BPR function t = t₀ [1 + 0.15 (v/c)⁴]: 1.15 t₀ at capacity and 1.759 t₀ at v/c = 1.5. Example: 1000 vehicles choose between route 1 with t₁ = 10 + 0.01x₁ and route 2 with t₂ = 15 + 0.005x₂ (minutes). Equilibrium: 10 + 0.01x₁ = 15 + 0.005(1000 − x₁) gives x₁ = 666.7, x₂ = 333.3, both routes 16.67 min, total 16667 veh-min. Optimum: equal marginal times 10 + 0.02x₁ = 15 + 0.01x₂ give x₁ = 500, x₂ = 500, total 16250 veh-min — lower than the equilibrium, because each driver ignores the delay they impose on others, which is the case for congestion pricing.

The four-step travel demand model
  1. Trip generationTrips produced and attracted
  2. Trip distributionGravity model
  3. Mode choice
  4. Traffic assignmentFlows loaded on routes

1. Trip generation predicts, for each zone, the trips produced (origins, from household size, income, vehicle ownership) and attracted (destinations, from employment, floor area); methods…

Peak-Hour Factor, Accident Rate and the Gravity Model, Computed

1 min read · 2 parts
The four-step demand model
StepQuestion answered
Trip generationhow many trips start and end in each zone
Trip distributionbetween which zones (gravity model)
Mode splitby which mode
Assignmenton which route

Peak-hour factor PHF = V / (4 × V₁₅): a peak hour of 1200 veh with a busiest 15-minute count of 360 gives 1200/1440 = 0.833, so the design flow rate is V/PHF = 1440 veh/h. Accident rate per 100 million vehicle-km = accidents × 10⁸ / (ADT × 365 × years × length): 25 accidents in 5 years on 10 km with ADT 4000 give 25 × 10⁸ / (4000 × 365 × 5 × 10) = 34.2. The gravity model distributes trips as T_ij = P_i A_j F_ij / Σ_j A_j F_ij, where P_i is the production of zone i, A_j the attraction of j and F_ij a friction factor that falls with travel time.

⚠️ A rate is not a count
A road with more accidents is not necessarily more dangerous: compare rates per vehicle-kilometre, not raw counts, since a busy road accumulates counts from exposure. A PHF near 1 means flow is uniform through the hour, and a low PHF means a sharp peak that the design must still carry.

Peak-hour factor PHF = V / (4 × V₁₅): a peak hour of 1200 veh with a busiest 15-minute count of 360 gives 1200/1440 = 0.833, so the design flow rate is V/PHF = 1440 veh/h. Accident rate per…

Key takeaways

  • Road hierarchy: NH, SH, MDR, ODR, VR; the design vehicle fixes widths and turning radii. PHF = hourly volume/(4 × peak 15-min volume); design flow rate = volume/PHF; LOS A–F grades quality.
  • Conflict points: 32 at an uncontrolled four-leg junction, 9 at a T-junction; crossing conflicts are the dangerous ones; a rotary converts crossing into weaving; interchanges separate movements vertically.
  • Accident rate = accidents × 10⁸/(AADT × 365 × L) per 100 million vehicle-km; collision diagrams reveal patterns; sample size n = (zs/e)²; speed limits use the 85th percentile.
  • Four steps: generation (productions and attractions) → distribution (gravity T_ij = P_iA_jF_ij/ΣA_jF_ij) → mode choice (logit e^U/Σe^U) → assignment (all-or-nothing, user equilibrium = equal times, system optimum = equal marginal times).
  • BPR link time t = t₀[1 + 0.15(v/c)⁴]; user equilibrium total delay is at least the system optimum, which is the argument for congestion pricing.

Practice questions (24)

Attempt each one before opening the answer. Every explanation names the tempting wrong option as well as the right one, because that is where marks are lost.

  1. The Nagpur Road Plan of 1943 classified roads into:

    1. National Highways, State Highways, Major District Roads, Other District Roads and Village Roads
    2. Class I, II and III roads
    3. Urban and rural roads only
    4. Expressways, arterials, collectors and locals
    Show answer

    Answer: A — National Highways, State Highways, Major District Roads, Other District Roads and Village Roads

    The five-tier administrative hierarchy NH, SH, MDR, ODR, VR dates from the Nagpur Plan. The arterial/collector/local scheme is the urban functional classification.
  2. An hourly volume of 1200 vehicles has a busiest 15-minute count of 360. The peak-hour factor and the design flow rate are:

    1. 0.833 and 1440 veh/h
    2. 1.2 and 1000 veh/h
    3. 0.25 and 4800 veh/h
    4. 0.833 and 1200 veh/h
    Show answer

    Answer: A — 0.833 and 1440 veh/h

    PHF = 1200/(4 × 360) = 0.833; the flow rate that the busiest quarter-hour implies is 1200/0.833 = 1440 veh/h (= 4 × 360). PHF cannot exceed 1.
  3. How many conflict points does an unsignalised four-leg intersection with two-way traffic have?

    1. 16
    2. 9
    3. 24
    4. 32
    Show answer

    Answer: D — 32

    8 diverging + 8 merging + 16 crossing = 32. A T-junction has 3 + 3 + 3 = 9. Crossing conflicts are the most severe, which is what signals and rotaries aim to remove.
Show the other 21 questions
  1. A rotary is designed to:

    1. remove all conflict points
    2. separate movements vertically
    3. give priority to the minor road
    4. convert crossing conflicts into weaving (merging and diverging) movements
    Show answer

    Answer: D — convert crossing conflicts into weaving (merging and diverging) movements

    Circulating vehicles merge and diverge instead of crossing, which reduces the severity of conflicts, though not their number to zero. Vertical separation is an interchange.
  2. A 5 km road section with AADT 8000 records 12 accidents in a year. Find the accident rate per 100 million vehicle-km (nearest integer).

    Numerical answer — type the value.

    Show answer

    Answer: 82

    Vehicle-km = 8000 × 365 × 5 = 14.6 million; R = 12 × 10⁸/(14.6 × 10⁶) = 82.2 per 10⁸ vehicle-km.
  3. The speed used as the usual basis for a speed limit is the:

    1. 85th percentile speed
    2. 15th percentile speed
    3. maximum observed speed
    4. mean speed
    Show answer

    Answer: A — 85th percentile speed

    The 85th percentile is the speed that all but the fastest 15% of drivers stay below, taken as the safe limit of reasonable behaviour. The 15th percentile sets the minimum limit on a high-speed road.
  4. In a gravity model, zone 1 produces 1000 trips; zones 2 and 3 attract 200 and 300 trips and are 10 and 20 minutes away (friction factor 1/t²). The trips from zone 1 to zone 2 are nearest to:

    1. 727
    2. 500
    3. 600
    4. 400
    Show answer

    Answer: A — 727

    T₁₂ = 1000 × 200 × 0.01 / (200 × 0.01 + 300 × 0.0025) = 2000/2.75 = 727.3. The 400 split goes by attractions alone and ignores that zone 2 is nearer.
  5. In a logit mode-choice model with U = −0.05 × travel time (min), car takes 20 min and bus 30 min. The probability of choosing the car is nearest to:

    1. 0.500
    2. 0.622
    3. 0.600
    4. 0.400
    Show answer

    Answer: B — 0.622

    P_car = e^(−1)/(e^(−1) + e^(−1.5)) = 1/(1 + e^(−0.5)) = 0.622. The 0.600 option is an inverse-time share, 30/(20 + 30), which is not a logit: logit shares depend on the difference of utilities, not on their ratio.
  6. Two routes carry 1000 vehicles in total; t₁ = 10 + 0.01x₁ and t₂ = 15 + 0.005x₂ minutes. At user equilibrium the flow on route 1 is nearest to:

    1. 667
    2. 333
    3. 500
    4. 800
    Show answer

    Answer: A — 667

    Equal times: 10 + 0.01x₁ = 15 + 0.005(1000 − x₁) → 0.015x₁ = 10 → x₁ = 666.7, each route taking 16.67 min. The system optimum (equal marginal times) would be 500.
  7. A 4 km road section with an AADT of 10 000 vehicles records 20 accidents in one year. The accident rate per 100 million vehicle-km, to the nearest integer, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 137

    Vehicle-km = 10 000 × 365 × 4 = 1.46×10⁷, so the rate = 20 × 10⁸/1.46×10⁷ = 137. Forgetting to multiply by 365 gives an annual-count mismatch (50 000).
  8. A peak-hour volume of 1000 vehicles has a maximum 15-minute count of 300 vehicles. The peak hour factor, to three decimal places, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 0.833

    PHF = V/(4 × V₁₅) = 1000/(4 × 300) = 0.833. Dividing 300/1000 = 0.3 gives the share of the peak quarter, not the factor.
  9. A traffic stream has 200 cars (1 PCU each) and 100 trucks (3 PCU each). The total flow, in PCU, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 500

    PCU = 200 × 1 + 100 × 3 = 500. Counting 300 vehicles ignores the heavier effect of trucks on the stream. Substituting the answer back into the relation confirms it.
  10. In the conventional four-step travel demand model, the correct sequence of steps is:

    1. trip distribution, trip generation, trip assignment, modal split
    2. trip assignment, modal split, trip distribution, trip generation
    3. trip generation, trip distribution, modal split, trip assignment
    4. modal split, trip generation, trip assignment, trip distribution
    Show answer

    Answer: C — trip generation, trip distribution, modal split, trip assignment

    Trips are first produced and attracted by zones, then paired between zones, then split among modes, and finally loaded on routes. The reversed order begins with a step that needs the earlier ones as input.
  11. An unsignalised T-junction with two-way traffic on all three legs has a total of ____ conflict points.

    Numerical answer — type the value.

    Show answer

    Answer: 9

    A three-leg junction has 3 diverging, 3 merging and 3 crossing conflicts, 9 in all. The four-leg junction has 32, which is the tempting value to recall.
  12. The total traffic count over seven consecutive days at a section is 56 000 vehicles. The average daily traffic, in vehicles per day, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 8000

    ADT = total count/number of days = 56 000/7 = 8000. Multiplying by 7 gives the weekly total. Substituting the answer back into the relation confirms it.
  13. In a gravity model with friction factor F = 1/t², zone 1 produces 2000 trips. Zone A attracts 400 trips and is 10 min away, zone B attracts 600 trips and is 20 min away. The trips from zone 1 to zone A, to the nearest integer, are ____.

    Numerical answer — type the value.

    Show answer

    Answer: 1455

    A·F: zone A = 400/100 = 4.0, zone B = 600/400 = 1.5, so share of A = 4/5.5 = 0.727 and T = 2000 × 0.727 = 1455. Splitting by attractions alone (40 : 60) would give 800.
  14. In a binary logit model the utility is V = −0.04 t − 0.02 c (t in min, c in ₹). A car trip has t = 25, c = 60 and a bus trip has t = 40, c = 20. The probability of choosing the car, to three decimal places, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 0.45

    V_car = −1.0 − 1.2 = −2.2 and V_bus = −1.6 − 0.4 = −2.0, so P_car = e^−2.2/(e^−2.2 + e^−2.0) = 0.450. Comparing time alone (car faster) would suggest a car share above 0.5.
  15. A total of 2000 vehicles choose between two routes with travel times t₁ = 20 + 0.02x₁ and t₂ = 30 + 0.01x₂ (minutes, x in vehicles). At user equilibrium the travel time on each route, in minutes, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 40

    Equal times: 20 + 0.02x = 30 + 0.01(2000 − x) gives 0.03x = 30, x₁ = 1000 = x₂, so t = 20 + 20 = 40 min on both. Splitting the flow in proportion to free-flow times would not equalise them.
  16. In a year a district records 200 road accidents in which 25 persons were killed. The accident severity (persons killed per 100 accidents) is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 12.5

    Severity = 25/200 × 100 = 12.5 persons killed per 100 accidents. Quoting 25 gives the raw number of deaths. Substituting the answer back into the relation confirms it.
  17. A bus lane carries 120 buses per hour with an average of 60 passengers per bus. The passenger flow, in passengers per hour per direction, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 7200

    Passenger flow = 120 × 60 = 7200 pphpd, several times what a general lane of cars carries. Quoting 180 adds the two numbers.
  18. The practical capacity of a rotary weaving section by the TRRL formula Q_p = 280 w (1 + e/w)(1 − p/3)/(1 + w/l) is required, with weaving width w = 10 m, average entry width e = 7 m, proportion of weaving traffic p = 0.4 and weaving length l = 30 m. The capacity, in PCU/h, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 3094

    Q_p = 280 × 10 × 1.7 × (1 − 0.1333)/(1 + 0.3333) = 4760 × 0.8667/1.3333 = 3094 PCU/h. Using p = 0.4 without dividing by 3 gives 2142, over-penalising the weaving share.
  19. Two routes carry 1000 vehicles with travel times t₁ = 10 + 0.01x₁ and t₂ = 15 + 0.005x₂ (minutes). The total system travel time at the system optimum (minimising Σ xᵢtᵢ), in vehicle-minutes, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 16250

    The marginal costs are 10 + 0.02x₁ and 15 + 0.01x₂; equating them with x₂ = 1000 − x₁ gives x₁ = 500, so total time = 500 × 15 + 500 × 17.5 = 16 250 veh-min. The user equilibrium split (667/333) gives the larger 16 667.
  20. At a junction, accidents fell from 40 per year before a safety treatment to 28 per year after it. At comparable control sites accidents fell from 100 to 90 per year over the same period. The percentage reduction attributable to the treatment, to one decimal place, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 22.2

    Without treatment the junction would be expected to fall by the control ratio 0.9 to 40 × 0.9 = 36 accidents, so the treatment effect is (36 − 28)/36 = 22.2 %. The raw reduction (12/40 = 30 %) wrongly credits the whole fall to the treatment.
  21. The signal change interval is y = t + v/(2a + 2gG). For a perception–reaction time t = 1 s, approach speed v = 15 m/s, deceleration a = 3 m/s² and a level approach (G = 0), the yellow time, in s to one decimal place, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 3.5

    y = 1 + 15/(2 × 3) = 1 + 2.5 = 3.5 s. Using v/a = 5 s and forgetting the factor 2 in the denominator overstates the interval to 6 s.