Production Planning and Engineering Economy in Numbers: Forecasting, EOQ and Quantity Discounts, CPM and PERT, Depreciation, Break-Even, Activity-Based Costing and Job Sequencing

Section 7 of the PI paper names forecasting (causal and time-series, moving average, exponential smoothing, trend and seasonality), deterministic inventory models with quantity discount, CPM and PERT with time-cost trade-off, depreciation, break-even, activity-based costing and priority dispatching. A twelve-month series gives a three-month moving-average forecast of 187.7, an exponentially smoothed one (α = 0.3) of 178.3 and a regression one of 199.6. A product with D = 12 000 a year, ordering cost ₹500 and holding cost ₹20 has EOQ = 775; a price-break schedule moves the best order to 1000 units. A seven-activity network has a critical path of 18 days and, with PERT estimates, a 98.3% chance of finishing in 20.
Overview

Forecasting: Moving Average, Exponential Smoothing, Trend, Seasonality and Regression

2 min read · 1 part

Take twelve monthly demands 120, 132, 128, 140, 152, 148, 160, 172, 165, 180, 188, 195. A 3-month moving average forecasts each month by the mean of the previous three; its forecast for month 13 is (180 + 188 + 195)/3 = 187.7. Because the series rises, a moving average lags: its mean error (bias) over months 4–12 is 13.8 (actual above forecast) and its mean absolute deviation (MAD) 13.8. Simple exponential smoothing F_(t+1) = F_t + α(D_t − F_t) with α = 0.3 and F₁ = D₁ gives F₁₃ = 178.3, MAD 17.7; a larger α reacts faster, a smaller one smooths noise, and both lag a trend. Holt's trend method (α = 0.4, β = 0.3) keeps a level and a trend and gives 200.0 for month 13. Linear regression D = a + bt fits the whole history: b = 6.608 per month, a = 113.71, correlation r = 0.983, so month 13 gives 199.6 — the causal form uses a driver (price, advertising) in place of t. Error measures: MAD = Σ|e|/n, MSE = Σe²/n, and the tracking signal Σe/MAD flags bias when it leaves about ±4. Choose a method by the pattern: level only → moving average or smoothing; trend → Holt or regression; seasonal → seasonal indices.

Seasonality: for three years of quarterly demand (200, 250, 180, 300 / 220, 270, 200, 330 / 240, 290, 215, 360) the grand quarterly mean is 254.6, and the seasonal index of each quarter (mean of that quarter / grand mean) is 0.864, 1.061, 0.779, 1.296, summing to 4. A deseasonalised level of 260 for next year's third quarter forecasts 260 × 0.779 = 203. Dividing observed demand by the index removes the season before fitting a trend; multiplying back restores it.

MethodHandlesMonth 13 forecast
3-month moving averageLevel only; lags a trend187.7
Exponential smoothing α = 0.3Level only178.3
Holt trendLevel and trend200.0
Linear regressionTrend or causal driver199.6

Take twelve monthly demands 120, 132, 128, 140, 152, 148, 160, 172, 165, 180, 188, 195. A 3-month moving average forecasts each month by the mean of the previous three; its forecast for…

Deterministic Inventory: EOQ, Production Lot, Shortages, Quantity Discounts and Safety Stock

2 min read · 1 part

The economic order quantity balances ordering cost against holding cost: Q* = √(2DS/H). For D = 12 000 a year, S = ₹500 per order and H = ₹20 per unit per year: Q* = 775 units, the annual ordering-plus-holding cost is √(2DSH) = ₹15,492 (the two halves are equal, ₹7,746 each), there are 15.5 orders a year, one every 23.6 days, and with a 7-day lead time the reorder point is 12 000/365 × 7 = 230 units. The cost curve is flat: ordering 20% off Q* raises the cost by only about 2%. When stock is built at a finite rate p = 24 000 a year (the production lot, EPQ) Q* = √(2DS/(H(1 − D/p))) = 1095, cost ₹10,954; the factor (1 − D/p) shrinks the average stock. With planned shortages (backorder cost B = ₹60/unit/year) Q* = EOQ√((H + B)/B) = 894, with a maximum backlog of Q*H/(H + B) = 224 units. Safety stock covers lead-time demand variability: SS = zσ_L; for a service level of 95% (z = 1.645), weekly σ = 40 and a 2-week lead time, σ_L = 40√2, SS = 93 units.

Quantity discount: the unit price falls with order size (₹100 below 500 units, ₹97 for 500–999, ₹95 from 1000) and holding cost is 20% of price. For each price compute its own EOQ, lift it to the lowest quantity that earns the price if it is too small, and compare total annual cost D·P + DS/Q + (0.2P)Q/2: ₹100 → EOQ 775, order 499, cost ₹1,217,014; ₹97 → EOQ 786, order 786, cost ₹1,179,258; ₹95 → EOQ 795, order 1000, cost ₹1,155,500. The cheapest is ₹95 with an order of 1000 — the biggest discount wins here because the saving on 12 000 units swamps the holding cost, but a small discount on a costly-to-hold item would not.

ModelQ*Value here
EOQ√(2DS/H)775
Production lot√(2DS/(H(1 − D/p)))1095
Planned shortageEOQ √((H + B)/B)894
Reorder pointd × L230

The economic order quantity balances ordering cost against holding cost: Q* = √(2DS/H). For D = 12 000 a year, S = ₹500 per order and H = ₹20 per unit per year: Q* = 775 units, the annual…

CPM, PERT and the Time-Cost Trade-Off

2 min read · 1 part

Seven activities (durations in days; predecessors): A 3; B 4 (A); C 2 (A); D 5 (B); E 3 (C); F 4 (D, E); G 2 (F). A forward pass gives earliest starts and finishes: A 0–3, B 3–7, C 3–5, D 7–12, E 5–8, F 12–16, G 16–18, so the project takes 18 days. The backward pass gives latest times; total float = LS − ES: C and E have 4 days, all others zero. The critical path is the chain of zero-float activities, A–B–D–F–G; a delay of C by 4 days is harmless, 5 days delays the project by 1. Free float is the delay an activity can take without delaying its successors' earliest start. PERT estimates each duration from optimistic a, most likely m and pessimistic b: t_e = (a + 4m + b)/6 and variance ((b − a)/6)². With A (2, 3, 4), B (3, 4, 5), D (3, 5, 7), F (3, 4, 5) and G (1, 2, 3) on the critical path, T_e = 18.0, variance 0.889, σ = 0.943; so P(finish ≤ 20) = Φ((20 − 18.0)/0.943) = Φ(2.12) = 98.3% and P(≤ 19) = 85.6%. PERT sums only the critical-path variances, which understates the risk when a near-critical path exists.

Time-cost trade-off (crashing). Each activity has a normal time and cost and a crash time and cost; its cost slope is (crash cost − normal cost)/(normal time − crash time). Suppose the critical activities cost to crash, per day saved: D ₹1 500 (up to 2 days), B ₹2 500 (1 day), F ₹3 000 (1 day), A ₹4 000 (1 day), G ₹5 000 (1 day). The rule is to shorten the cheapest critical activity first and re-check that no other path becomes critical: 18 → 16 days by crashing D twice costs ₹3 000; 16 → 15 by B costs ₹2 500 more (₹5 500 total); 15 → 14 by F adds ₹3 000 (₹8 500), and the other path A–C–E–F–G (14 days, then 13 after F) stays non-critical. Indirect cost (overheads) falls as the project shortens, direct cost rises, and the optimum duration is where the sum is smallest.

ActivityES – EFFloat
A0 – 30
B3 – 70
C3 – 54
D7 – 120
E5 – 84
F12 – 160
G16 – 180

Seven activities (durations in days; predecessors): A 3; B 4 (A); C 2 (A); D 5 (B); E 3 (C); F 4 (D, E); G 2 (F). A forward pass gives earliest starts and finishes: A 0–3, B 3–7, C 3–5, D…

Depreciation, Break-Even and Activity-Based Costing

2 min read · 1 part

Take an asset costing ₹1 00 000 with salvage value ₹10 000 and a life of 5 years. Straight line: (P − S)/n = ₹18,000 every year. Sum of the years' digits: the denominator is 5 × 6/2 = 15, so the charges are 5/15, 4/15, … of ₹90 000: ₹30,000, 24,000, 18,000, 12,000, 6,000. Declining balance with the rate that reaches the salvage value exactly: d = 1 − (S/P)^(1/n) = 36.90% of the opening book value each year, giving charges ₹36,904, 23,285, 14,692, 9,270, 5,849 and a book value of ₹10,000 after year 5. The accelerated methods write off more early, defer tax and match the loss of value of equipment that is most productive when new. Break-even analysis: with fixed cost ₹6 00 000, variable cost ₹80 and price ₹140, the contribution is ₹60 per unit, the break-even volume = FC/(p − v) = 10,000 units, break-even revenue ₹1,400,000, and the margin of safety at 14 000 units is 28.6% of sales; a profit target of ₹3 00 000 needs (600 000 + 300 000)/60 = 15 000 units.

Activity-based costing (ABC) assigns overhead by what causes it rather than by volume. Overhead is ₹3 00 000: ₹2 00 000 of set-up cost driven by the number of set-ups and ₹1 00 000 of inspection cost driven by inspections. Product X is made in 8 000 units with 10 set-ups and 200 inspections; product Y in 2 000 units with 90 set-ups and 300 inspections. Traditional costing by volume loads X with ₹240,000 (₹30 a unit) and Y with ₹60,000 (₹30 a unit). ABC loads X with 200 000 × 10/100 + 100 000 × 200/500 = ₹60,000 (₹7.50 a unit) and Y with ₹240,000 (₹120 a unit): the low-volume product is under-costed fourfold by the traditional method, which can lead to pricing it too low and dropping a profitable high-volume one.

YearStraight line (₹)Sum of digits (₹)Declining balance (₹)
118,00030,00036,904
218,00024,00023,285
318,00018,00014,692
418,00012,0009,270
518,0006,0005,849

Take an asset costing ₹1 00 000 with salvage value ₹10 000 and a life of 5 years. Straight line: (P − S)/n = ₹18,000 every year. Sum of the years' digits: the denominator is 5 × 6/2 = 15…

Priority Dispatching and Johnson's Rule

1 min read · 1 part

Five jobs on one machine, with (processing time, due date): J1 (6, 15), J2 (2, 28), J3 (8, 12), J4 (3, 6), J5 (9, 25). SPT (shortest processing time first) orders J2, J4, J1, J3, J5 with mean flow time 13.0, mean tardiness 2.0 and 2 late jobs; EDD (earliest due date) orders J4, J3, J1, J5, J2 with mean flow time 17.0, mean tardiness 0.6, maximum lateness 2 and 2 late jobs; FCFS gives flow time 15.4. SPT minimises mean flow time (and so work in process); EDD minimises maximum lateness. Critical ratio = time remaining / work remaining; a ratio below 1 means the job is behind. Johnson's rule minimises the makespan of n jobs through two machines in series: list jobs whose first-machine time is shorter than the second in increasing first-machine time, then the others in decreasing second-machine time. For jobs (M1, M2) A (5, 2), B (1, 6), C (9, 7), D (3, 8), E (10, 4) the sequence is B–D–C–E–A with a makespan of 30 h, against 34 h in the order A–E — the result matches a search over all 120 orders.

RuleMinimisesHere
SPTMean flow time13.0
EDDMaximum lateness2
Johnson's ruleTwo-machine makespan30 h
🎯 Break-even and sequencing, worked
The break-even quantity is F/(p − v): fixed cost ₹50 000, price ₹100 and variable cost ₹60 give 50 000/40 = 1250 units, or revenue ₹1 25 000. For job sequencing on one machine the shortest-processing-time rule minimises mean flow time: jobs of 4, 2 and 6 days run in the order 2, 4, 6, with completion times 2, 6 and 12 and mean 6.67, against 7.33 for the order 4, 2, 6. The earliest-due-date rule minimises the maximum lateness instead, so the objective decides the rule.

Five jobs on one machine, with (processing time, due date): J1 (6, 15), J2 (2, 28), J3 (8, 12), J4 (3, 6), J5 (9, 25). SPT (shortest processing time first) orders J2, J4, J1, J3, J5 with…

Key takeaways

  • Moving average and smoothing lag a trend; Holt and regression follow it; a seasonal index is the quarter mean over the grand mean.
  • EOQ = √(2DS/H); at the optimum ordering cost equals holding cost; EPQ multiplies by 1/√(1 − D/p); with discounts compare total cost at each feasible price.
  • CPM: forward and backward passes give float; PERT uses t_e = (a + 4m + b)/6 and variance ((b − a)/6)²; crash the cheapest critical activity first.
  • Straight-line depreciation (P − S)/n, SYD uses n(n + 1)/2, break-even FC/(p − v); ABC allocates overhead by activity drivers, not volume.
  • SPT minimises mean flow time, EDD minimises maximum lateness, Johnson's rule minimises two-machine makespan.

Practice questions (24)

Attempt each one before opening the answer. Every explanation names the tempting wrong option as well as the right one, because that is where marks are lost.

  1. Monthly demand for the last three months was 180, 188 and 195. The three-month moving-average forecast for next month (one decimal) is:

    Numerical answer — type the value.

    Show answer

    Answer: 187.7

    (180 + 188 + 195)/3 = 187.7. The series is rising, so the true value will probably be higher — the moving average lags a trend.
  2. In simple exponential smoothing, increasing α from 0.1 to 0.5:

    1. Makes the forecast smoother
    2. Has no effect
    3. Removes the lag completely
    4. Makes the forecast respond faster to recent demand and follow noise more
    Show answer

    Answer: D — Makes the forecast respond faster to recent demand and follow noise more

    The weight on the latest observation is α, so a large α tracks changes quickly but passes the noise through; a small α smooths but lags. Neither removes the lag behind a trend.
  3. For annual demand 12 000 units, ordering cost ₹500 and holding cost ₹20 per unit per year, the economic order quantity (nearest integer) is:

    Numerical answer — type the value.

    Show answer

    Answer: 775

    EOQ = √(2 × 12 000 × 500/20) = √600 000 = 775. The annual cost is √(2DSH) = ₹15,492, half of it ordering and half holding.
Show the other 21 questions
  1. If the stock is built at a rate of 24 000 units a year (demand 12 000), the economic production lot for the same costs (nearest integer) is:

    Numerical answer — type the value.

    Show answer

    Answer: 1095

    EPQ = EOQ/√(1 − D/p) = 775/√0.5 = 1095. The lot is larger than EOQ because stock builds up slowly, so average inventory is lower for a given lot.
  2. In the seven-activity network (A 3; B 4 after A; C 2 after A; D 5 after B; E 3 after C; F 4 after D and E; G 2 after F), the project duration in days is:

    Numerical answer — type the value.

    Show answer

    Answer: 18

    The longest path A–B–D–F–G is 3 + 4 + 5 + 4 + 2 = 18 days; the other path A–C–E–F–G is 14 days, so C and E have 4 days of float.
  3. A PERT activity has optimistic 3, most likely 5 and pessimistic 7 days. Its expected time and variance are:

    1. 5 days and 4
    2. 5 days and 0.667
    3. 5 days and 0.444
    4. 4.67 days and 0.444
    Show answer

    Answer: C — 5 days and 0.444

    t_e = (3 + 20 + 7)/6 = 5 and variance = ((7 − 3)/6)² = 0.444; the standard deviation is 0.667, which is a common wrong choice for the variance.
  4. The critical path has expected duration 18 days and variance 0.889 (σ = 0.943). The probability of finishing within 20 days, in per cent (one decimal), is:

    Numerical answer — type the value.

    Show answer

    Answer: 98.3

    z = (20 − 18)/0.943 = 2.12; Φ(z) = 0.9831 = 98.3%. Dividing by the variance instead of σ would give z = 2.25 and a wrong 98.8%.
  5. An asset costing ₹1 00 000 has salvage value ₹10 000 and a 5-year life. The sum-of-the-years'-digits depreciation charge in year 2 (₹) is:

    Numerical answer — type the value.

    Show answer

    Answer: 24000

    SYD denominator 5 × 6/2 = 15; year 2 uses 4/15: 4/15 × 90 000 = 24,000. Year 1 would be 30 000 and straight line is 18 000 a year.
  6. With fixed cost ₹6 00 000, variable cost ₹80 per unit and selling price ₹140, the break-even volume in units is:

    Numerical answer — type the value.

    Show answer

    Answer: 10000

    Contribution per unit is 140 − 80 = 60; break-even = 600 000/60 = 10,000 units, i.e. revenue ₹1,400,000. Dividing by the price instead gives the wrong 4 286.
  7. Compared with volume-based overhead allocation, activity-based costing typically shows that low-volume, complex products:

    1. Cost less
    2. Cost exactly the same
    3. Cost much more than the traditional method reported
    4. Have no overhead
    Show answer

    Answer: C — Cost much more than the traditional method reported

    Set-ups and inspections follow the number of batches, not units; Y, with 90 of 100 set-ups, carries ₹120 a unit under ABC against ₹30 under the volume method — the traditional method subsidises the complex product.
  8. The jobs (processing time, due date) J1 (6, 15), J2 (2, 28), J3 (8, 12), J4 (3, 6), J5 (9, 25) run on one machine in SPT order. The mean flow time is:

    Numerical answer — type the value.

    Show answer

    Answer: 13.0

    SPT order J2, J4, J1, J3, J5 completes at 2, 5, 11, 19, 28; mean = 65/5 = 13.0. FCFS would give 15.4; SPT always minimises the mean flow time.
  9. Johnson's rule is used to:

    1. Balance an assembly line
    2. Minimise mean tardiness on one machine
    3. Compute the EOQ
    4. Minimise the makespan of n jobs through two machines in series
    Show answer

    Answer: D — Minimise the makespan of n jobs through two machines in series

    Johnson's rule gives the optimal sequence for the two-machine flow shop: short-first-machine jobs go early and short-second-machine jobs go late. Mean tardiness has no simple optimal rule.
  10. With annual demand 1200 units, ordering cost ₹100 and holding cost ₹4 per unit per year, the EOQ = √(2DS/H), in units (nearest integer), is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 245

    EOQ = √(2 × 1200 × 100/4) = √60000 = 244.9 ≈ 245. Forgetting the square root (60 000) confuses the squared quantity with the EOQ.
  11. Exponential smoothing with α = 0.3 has last actual demand 110 and last forecast 100. The new forecast is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 103

    F_new = αA + (1 − α)F = 0.3 × 110 + 0.7 × 100 = 33 + 70 = 103. Swapping the weights (0.7 on actual) gives 107, over-reacting to the latest value.
  12. In CPM, the total float of an activity is

    1. the time it can be delayed without delaying project completion
    2. the longest path
    3. its duration
    4. always zero
    Show answer

    Answer: A — the time it can be delayed without delaying project completion

    Total float = LS − ES = LF − EF, the slack before the project end is affected. Critical activities have zero float, but not every activity, so "always zero" is the tempting error.
  13. Johnson’s rule is used to sequence jobs on

    1. one machine to minimise cost
    2. parallel machines for load balancing
    3. any number of machines for maximum profit
    4. two machines to minimise total makespan
    Show answer

    Answer: D — two machines to minimise total makespan

    Johnson’s rule optimally sequences n jobs through two machines (and some three-machine cases) to minimise makespan. It is not a one-machine cost rule or a general n-machine method, the tempting overreach.
  14. With an annual demand of 1200 units and an EOQ of 245 units, the number of orders placed per year (one decimal) is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 4.9

    N = D/Q = 1200/245 = 4.9 orders per year. Multiplying D × Q instead of dividing gives a meaningless large number.
  15. For D = 1200, S = ₹100, H = ₹4/unit/yr, the minimum total ordering-plus-holding cost at the EOQ, TC = √(2DSH), in ₹ (nearest integer), is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 980

    At the EOQ ordering cost = holding cost, and total = √(2DSH) = √(2 × 1200 × 100 × 4) = √960000 = 980. This equals the ₹490 ordering plus ₹490 holding; taking only one component halves it.
  16. Forecast errors over three periods are 2, −2 and 0 (actual − forecast). The mean absolute deviation (MAD), to three decimals, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 1.333

    MAD = (|2| + |−2| + |0|)/3 = 4/3 = 1.333. Taking the mean error (2 − 2 + 0)/3 = 0 cancels the signs and hides the error, which is why absolute values are used.
  17. An asset costs ₹100000, has a salvage value of ₹10000 and a useful life of 9 years. The annual straight-line depreciation, in ₹, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 10000

    D = (cost − salvage)/life = (100000 − 10000)/9 = 90000/9 = 10000. Dividing the full cost by life (100000/9 = 11111) ignores the salvage value.
  18. In PERT, the expected time of an activity from optimistic (a), most likely (m) and pessimistic (b) estimates is

    1. (a + 4m + b)/6
    2. 4m
    3. (a + m + b)/3
    4. (a + b)/2
    Show answer

    Answer: A — (a + 4m + b)/6

    PERT uses the beta-distribution estimate t_e = (a + 4m + b)/6. The plain average (a + m + b)/3 ignores the heavier weight on the most likely time, the tempting simplification.
  19. An activity has optimistic time 4, most likely 6 and pessimistic 14 days. Its PERT expected time, in days, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 7

    t_e = (4 + 4×6 + 14)/6 = (4 + 24 + 14)/6 = 42/6 = 7 days. The simple mean (4 + 6 + 14)/3 = 8 over-weights the pessimistic tail.
  20. A loan of ₹10000 is repaid in equal annual instalments over 5 years at 10% interest. The annual payment, A = P·[i(1+i)ⁿ]/[(1+i)ⁿ − 1], in ₹ (nearest integer), is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 2638

    A = 10000 × [0.1 × 1.1⁵]/[1.1⁵ − 1] = 10000 × 0.16105/0.61051 = 2638. Dividing the principal evenly (10000/5 = 2000) ignores the interest, understating the payment.
  21. For the PERT activity with a = 4 and b = 14 days, the variance of the activity time, σ² = [(b − a)/6]², to three decimals, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 2.778

    σ² = [(14 − 4)/6]² = (10/6)² = 2.778 days². Forgetting to square (10/6 = 1.667) gives the standard deviation, not the variance.