Production Planning and Engineering Economy in Numbers: Forecasting, EOQ and Quantity Discounts, CPM and PERT, Depreciation, Break-Even, Activity-Based Costing and Job Sequencing
Deterministic Inventory: EOQ, Production Lot, Shortages, Quantity Discounts and Safety Stock
The economic order quantity balances ordering cost against holding cost: Q* = √(2DS/H). For D = 12 000 a year, S = ₹500 per order and H = ₹20 per unit per year: Q* = 775 units, the annual ordering-plus-holding cost is √(2DSH) = ₹15,492 (the two halves are equal, ₹7,746 each), there are 15.5 orders a year, one every 23.6 days, and with a 7-day lead time the reorder point is 12 000/365 × 7 = 230 units. The cost curve is flat: ordering 20% off Q* raises the cost by only about 2%. When stock is built at a finite rate p = 24 000 a year (the production lot, EPQ) Q* = √(2DS/(H(1 − D/p))) = 1095, cost ₹10,954; the factor (1 − D/p) shrinks the average stock. With planned shortages (backorder cost B = ₹60/unit/year) Q* = EOQ√((H + B)/B) = 894, with a maximum backlog of Q*H/(H + B) = 224 units. Safety stock covers lead-time demand variability: SS = zσ_L; for a service level of 95% (z = 1.645), weekly σ = 40 and a 2-week lead time, σ_L = 40√2, SS = 93 units.
Quantity discount: the unit price falls with order size (₹100 below 500 units, ₹97 for 500–999, ₹95 from 1000) and holding cost is 20% of price. For each price compute its own EOQ, lift it to the lowest quantity that earns the price if it is too small, and compare total annual cost D·P + DS/Q + (0.2P)Q/2: ₹100 → EOQ 775, order 499, cost ₹1,217,014; ₹97 → EOQ 786, order 786, cost ₹1,179,258; ₹95 → EOQ 795, order 1000, cost ₹1,155,500. The cheapest is ₹95 with an order of 1000 — the biggest discount wins here because the saving on 12 000 units swamps the holding cost, but a small discount on a costly-to-hold item would not.
| Model | Q* | Value here |
|---|---|---|
| EOQ | √(2DS/H) | 775 |
| Production lot | √(2DS/(H(1 − D/p))) | 1095 |
| Planned shortage | EOQ √((H + B)/B) | 894 |
| Reorder point | d × L | 230 |
The economic order quantity balances ordering cost against holding cost: Q* = √(2DS/H). For D = 12 000 a year, S = ₹500 per order and H = ₹20 per unit per year: Q* = 775 units, the annual…
CPM, PERT and the Time-Cost Trade-Off
Seven activities (durations in days; predecessors): A 3; B 4 (A); C 2 (A); D 5 (B); E 3 (C); F 4 (D, E); G 2 (F). A forward pass gives earliest starts and finishes: A 0–3, B 3–7, C 3–5, D 7–12, E 5–8, F 12–16, G 16–18, so the project takes 18 days. The backward pass gives latest times; total float = LS − ES: C and E have 4 days, all others zero. The critical path is the chain of zero-float activities, A–B–D–F–G; a delay of C by 4 days is harmless, 5 days delays the project by 1. Free float is the delay an activity can take without delaying its successors' earliest start. PERT estimates each duration from optimistic a, most likely m and pessimistic b: t_e = (a + 4m + b)/6 and variance ((b − a)/6)². With A (2, 3, 4), B (3, 4, 5), D (3, 5, 7), F (3, 4, 5) and G (1, 2, 3) on the critical path, T_e = 18.0, variance 0.889, σ = 0.943; so P(finish ≤ 20) = Φ((20 − 18.0)/0.943) = Φ(2.12) = 98.3% and P(≤ 19) = 85.6%. PERT sums only the critical-path variances, which understates the risk when a near-critical path exists.
Time-cost trade-off (crashing). Each activity has a normal time and cost and a crash time and cost; its cost slope is (crash cost − normal cost)/(normal time − crash time). Suppose the critical activities cost to crash, per day saved: D ₹1 500 (up to 2 days), B ₹2 500 (1 day), F ₹3 000 (1 day), A ₹4 000 (1 day), G ₹5 000 (1 day). The rule is to shorten the cheapest critical activity first and re-check that no other path becomes critical: 18 → 16 days by crashing D twice costs ₹3 000; 16 → 15 by B costs ₹2 500 more (₹5 500 total); 15 → 14 by F adds ₹3 000 (₹8 500), and the other path A–C–E–F–G (14 days, then 13 after F) stays non-critical. Indirect cost (overheads) falls as the project shortens, direct cost rises, and the optimum duration is where the sum is smallest.
| Activity | ES – EF | Float |
|---|---|---|
| A | 0 – 3 | 0 |
| B | 3 – 7 | 0 |
| C | 3 – 5 | 4 |
| D | 7 – 12 | 0 |
| E | 5 – 8 | 4 |
| F | 12 – 16 | 0 |
| G | 16 – 18 | 0 |
Seven activities (durations in days; predecessors): A 3; B 4 (A); C 2 (A); D 5 (B); E 3 (C); F 4 (D, E); G 2 (F). A forward pass gives earliest starts and finishes: A 0–3, B 3–7, C 3–5, D…
Depreciation, Break-Even and Activity-Based Costing
Take an asset costing ₹1 00 000 with salvage value ₹10 000 and a life of 5 years. Straight line: (P − S)/n = ₹18,000 every year. Sum of the years' digits: the denominator is 5 × 6/2 = 15, so the charges are 5/15, 4/15, … of ₹90 000: ₹30,000, 24,000, 18,000, 12,000, 6,000. Declining balance with the rate that reaches the salvage value exactly: d = 1 − (S/P)^(1/n) = 36.90% of the opening book value each year, giving charges ₹36,904, 23,285, 14,692, 9,270, 5,849 and a book value of ₹10,000 after year 5. The accelerated methods write off more early, defer tax and match the loss of value of equipment that is most productive when new. Break-even analysis: with fixed cost ₹6 00 000, variable cost ₹80 and price ₹140, the contribution is ₹60 per unit, the break-even volume = FC/(p − v) = 10,000 units, break-even revenue ₹1,400,000, and the margin of safety at 14 000 units is 28.6% of sales; a profit target of ₹3 00 000 needs (600 000 + 300 000)/60 = 15 000 units.
Activity-based costing (ABC) assigns overhead by what causes it rather than by volume. Overhead is ₹3 00 000: ₹2 00 000 of set-up cost driven by the number of set-ups and ₹1 00 000 of inspection cost driven by inspections. Product X is made in 8 000 units with 10 set-ups and 200 inspections; product Y in 2 000 units with 90 set-ups and 300 inspections. Traditional costing by volume loads X with ₹240,000 (₹30 a unit) and Y with ₹60,000 (₹30 a unit). ABC loads X with 200 000 × 10/100 + 100 000 × 200/500 = ₹60,000 (₹7.50 a unit) and Y with ₹240,000 (₹120 a unit): the low-volume product is under-costed fourfold by the traditional method, which can lead to pricing it too low and dropping a profitable high-volume one.
| Year | Straight line (₹) | Sum of digits (₹) | Declining balance (₹) |
|---|---|---|---|
| 1 | 18,000 | 30,000 | 36,904 |
| 2 | 18,000 | 24,000 | 23,285 |
| 3 | 18,000 | 18,000 | 14,692 |
| 4 | 18,000 | 12,000 | 9,270 |
| 5 | 18,000 | 6,000 | 5,849 |
Take an asset costing ₹1 00 000 with salvage value ₹10 000 and a life of 5 years. Straight line: (P − S)/n = ₹18,000 every year. Sum of the years' digits: the denominator is 5 × 6/2 = 15…
Priority Dispatching and Johnson's Rule
Five jobs on one machine, with (processing time, due date): J1 (6, 15), J2 (2, 28), J3 (8, 12), J4 (3, 6), J5 (9, 25). SPT (shortest processing time first) orders J2, J4, J1, J3, J5 with mean flow time 13.0, mean tardiness 2.0 and 2 late jobs; EDD (earliest due date) orders J4, J3, J1, J5, J2 with mean flow time 17.0, mean tardiness 0.6, maximum lateness 2 and 2 late jobs; FCFS gives flow time 15.4. SPT minimises mean flow time (and so work in process); EDD minimises maximum lateness. Critical ratio = time remaining / work remaining; a ratio below 1 means the job is behind. Johnson's rule minimises the makespan of n jobs through two machines in series: list jobs whose first-machine time is shorter than the second in increasing first-machine time, then the others in decreasing second-machine time. For jobs (M1, M2) A (5, 2), B (1, 6), C (9, 7), D (3, 8), E (10, 4) the sequence is B–D–C–E–A with a makespan of 30 h, against 34 h in the order A–E — the result matches a search over all 120 orders.
| Rule | Minimises | Here |
|---|---|---|
| SPT | Mean flow time | 13.0 |
| EDD | Maximum lateness | 2 |
| Johnson's rule | Two-machine makespan | 30 h |
Five jobs on one machine, with (processing time, due date): J1 (6, 15), J2 (2, 28), J3 (8, 12), J4 (3, 6), J5 (9, 25). SPT (shortest processing time first) orders J2, J4, J1, J3, J5 with…
Key takeaways
- Moving average and smoothing lag a trend; Holt and regression follow it; a seasonal index is the quarter mean over the grand mean.
- EOQ = √(2DS/H); at the optimum ordering cost equals holding cost; EPQ multiplies by 1/√(1 − D/p); with discounts compare total cost at each feasible price.
- CPM: forward and backward passes give float; PERT uses t_e = (a + 4m + b)/6 and variance ((b − a)/6)²; crash the cheapest critical activity first.
- Straight-line depreciation (P − S)/n, SYD uses n(n + 1)/2, break-even FC/(p − v); ABC allocates overhead by activity drivers, not volume.
- SPT minimises mean flow time, EDD minimises maximum lateness, Johnson's rule minimises two-machine makespan.
Practice questions (24)
Attempt each one before opening the answer. Every explanation names the tempting wrong option as well as the right one, because that is where marks are lost.
Monthly demand for the last three months was 180, 188 and 195. The three-month moving-average forecast for next month (one decimal) is:
Numerical answer — type the value.
Show answer
Answer: 187.7
(180 + 188 + 195)/3 = 187.7. The series is rising, so the true value will probably be higher — the moving average lags a trend.In simple exponential smoothing, increasing α from 0.1 to 0.5:
Show answer
Answer: D — Makes the forecast respond faster to recent demand and follow noise more
The weight on the latest observation is α, so a large α tracks changes quickly but passes the noise through; a small α smooths but lags. Neither removes the lag behind a trend.For annual demand 12 000 units, ordering cost ₹500 and holding cost ₹20 per unit per year, the economic order quantity (nearest integer) is:
Numerical answer — type the value.
Show answer
Answer: 775
EOQ = √(2 × 12 000 × 500/20) = √600 000 = 775. The annual cost is √(2DSH) = ₹15,492, half of it ordering and half holding.
Show the other 21 questions
If the stock is built at a rate of 24 000 units a year (demand 12 000), the economic production lot for the same costs (nearest integer) is:
Numerical answer — type the value.
Show answer
Answer: 1095
EPQ = EOQ/√(1 − D/p) = 775/√0.5 = 1095. The lot is larger than EOQ because stock builds up slowly, so average inventory is lower for a given lot.In the seven-activity network (A 3; B 4 after A; C 2 after A; D 5 after B; E 3 after C; F 4 after D and E; G 2 after F), the project duration in days is:
Numerical answer — type the value.
Show answer
Answer: 18
The longest path A–B–D–F–G is 3 + 4 + 5 + 4 + 2 = 18 days; the other path A–C–E–F–G is 14 days, so C and E have 4 days of float.A PERT activity has optimistic 3, most likely 5 and pessimistic 7 days. Its expected time and variance are:
Show answer
Answer: C — 5 days and 0.444
t_e = (3 + 20 + 7)/6 = 5 and variance = ((7 − 3)/6)² = 0.444; the standard deviation is 0.667, which is a common wrong choice for the variance.The critical path has expected duration 18 days and variance 0.889 (σ = 0.943). The probability of finishing within 20 days, in per cent (one decimal), is:
Numerical answer — type the value.
Show answer
Answer: 98.3
z = (20 − 18)/0.943 = 2.12; Φ(z) = 0.9831 = 98.3%. Dividing by the variance instead of σ would give z = 2.25 and a wrong 98.8%.An asset costing ₹1 00 000 has salvage value ₹10 000 and a 5-year life. The sum-of-the-years'-digits depreciation charge in year 2 (₹) is:
Numerical answer — type the value.
Show answer
Answer: 24000
SYD denominator 5 × 6/2 = 15; year 2 uses 4/15: 4/15 × 90 000 = 24,000. Year 1 would be 30 000 and straight line is 18 000 a year.With fixed cost ₹6 00 000, variable cost ₹80 per unit and selling price ₹140, the break-even volume in units is:
Numerical answer — type the value.
Show answer
Answer: 10000
Contribution per unit is 140 − 80 = 60; break-even = 600 000/60 = 10,000 units, i.e. revenue ₹1,400,000. Dividing by the price instead gives the wrong 4 286.Compared with volume-based overhead allocation, activity-based costing typically shows that low-volume, complex products:
Show answer
Answer: C — Cost much more than the traditional method reported
Set-ups and inspections follow the number of batches, not units; Y, with 90 of 100 set-ups, carries ₹120 a unit under ABC against ₹30 under the volume method — the traditional method subsidises the complex product.The jobs (processing time, due date) J1 (6, 15), J2 (2, 28), J3 (8, 12), J4 (3, 6), J5 (9, 25) run on one machine in SPT order. The mean flow time is:
Numerical answer — type the value.
Show answer
Answer: 13.0
SPT order J2, J4, J1, J3, J5 completes at 2, 5, 11, 19, 28; mean = 65/5 = 13.0. FCFS would give 15.4; SPT always minimises the mean flow time.Johnson's rule is used to:
Show answer
Answer: D — Minimise the makespan of n jobs through two machines in series
Johnson's rule gives the optimal sequence for the two-machine flow shop: short-first-machine jobs go early and short-second-machine jobs go late. Mean tardiness has no simple optimal rule.With annual demand 1200 units, ordering cost ₹100 and holding cost ₹4 per unit per year, the EOQ = √(2DS/H), in units (nearest integer), is ____.
Numerical answer — type the value.
Show answer
Answer: 245
EOQ = √(2 × 1200 × 100/4) = √60000 = 244.9 ≈ 245. Forgetting the square root (60 000) confuses the squared quantity with the EOQ.Exponential smoothing with α = 0.3 has last actual demand 110 and last forecast 100. The new forecast is ____.
Numerical answer — type the value.
Show answer
Answer: 103
F_new = αA + (1 − α)F = 0.3 × 110 + 0.7 × 100 = 33 + 70 = 103. Swapping the weights (0.7 on actual) gives 107, over-reacting to the latest value.In CPM, the total float of an activity is
Show answer
Answer: A — the time it can be delayed without delaying project completion
Total float = LS − ES = LF − EF, the slack before the project end is affected. Critical activities have zero float, but not every activity, so "always zero" is the tempting error.Johnson’s rule is used to sequence jobs on
Show answer
Answer: D — two machines to minimise total makespan
Johnson’s rule optimally sequences n jobs through two machines (and some three-machine cases) to minimise makespan. It is not a one-machine cost rule or a general n-machine method, the tempting overreach.With an annual demand of 1200 units and an EOQ of 245 units, the number of orders placed per year (one decimal) is ____.
Numerical answer — type the value.
Show answer
Answer: 4.9
N = D/Q = 1200/245 = 4.9 orders per year. Multiplying D × Q instead of dividing gives a meaningless large number.For D = 1200, S = ₹100, H = ₹4/unit/yr, the minimum total ordering-plus-holding cost at the EOQ, TC = √(2DSH), in ₹ (nearest integer), is ____.
Numerical answer — type the value.
Show answer
Answer: 980
At the EOQ ordering cost = holding cost, and total = √(2DSH) = √(2 × 1200 × 100 × 4) = √960000 = 980. This equals the ₹490 ordering plus ₹490 holding; taking only one component halves it.Forecast errors over three periods are 2, −2 and 0 (actual − forecast). The mean absolute deviation (MAD), to three decimals, is ____.
Numerical answer — type the value.
Show answer
Answer: 1.333
MAD = (|2| + |−2| + |0|)/3 = 4/3 = 1.333. Taking the mean error (2 − 2 + 0)/3 = 0 cancels the signs and hides the error, which is why absolute values are used.An asset costs ₹100000, has a salvage value of ₹10000 and a useful life of 9 years. The annual straight-line depreciation, in ₹, is ____.
Numerical answer — type the value.
Show answer
Answer: 10000
D = (cost − salvage)/life = (100000 − 10000)/9 = 90000/9 = 10000. Dividing the full cost by life (100000/9 = 11111) ignores the salvage value.In PERT, the expected time of an activity from optimistic (a), most likely (m) and pessimistic (b) estimates is
Show answer
Answer: A — (a + 4m + b)/6
PERT uses the beta-distribution estimate t_e = (a + 4m + b)/6. The plain average (a + m + b)/3 ignores the heavier weight on the most likely time, the tempting simplification.An activity has optimistic time 4, most likely 6 and pessimistic 14 days. Its PERT expected time, in days, is ____.
Numerical answer — type the value.
Show answer
Answer: 7
t_e = (4 + 4×6 + 14)/6 = (4 + 24 + 14)/6 = 42/6 = 7 days. The simple mean (4 + 6 + 14)/3 = 8 over-weights the pessimistic tail.A loan of ₹10000 is repaid in equal annual instalments over 5 years at 10% interest. The annual payment, A = P·[i(1+i)ⁿ]/[(1+i)ⁿ − 1], in ₹ (nearest integer), is ____.
Numerical answer — type the value.
Show answer
Answer: 2638
A = 10000 × [0.1 × 1.1⁵]/[1.1⁵ − 1] = 10000 × 0.16105/0.61051 = 2638. Dividing the principal evenly (10000/5 = 2000) ignores the interest, understating the payment.For the PERT activity with a = 4 and b = 14 days, the variance of the activity time, σ² = [(b − a)/6]², to three decimals, is ____.
Numerical answer — type the value.
Show answer
Answer: 2.778
σ² = [(14 − 4)/6]² = (10/6)² = 2.778 days². Forgetting to square (10/6 = 1.667) gives the standard deviation, not the variance.