Project Networks (AOA and AON), Updating and Monitoring, and Construction Equipment
Project Updating and Monitoring: S-Curves and Earned Value
A plan is useful only while it is current, so a project is monitored (measure progress against the baseline) and updated (revise the remaining schedule and cost from actual progress). The S-curve plots cumulative cost or progress against time: slow start, steep middle, tapering end; the actual curve lying below the planned one signals delay. Earned value management makes this quantitative with three numbers at a status date: PV (planned value: budgeted cost of work scheduled), EV (earned value: budgeted cost of work actually performed) and AC (actual cost). Then CV = EV − AC, SV = EV − PV, CPI = EV/AC (cost efficiency, below 1 means over budget) and SPI = EV/PV (schedule efficiency, below 1 means behind). For BAC = 1000, PV = 400, EV = 350, AC = 450: CV = -100, SV = -50, CPI = 0.778, SPI = 0.875 — over budget and behind schedule. The forecast at completion assuming the present cost efficiency continues is EAC = BAC/CPI = 1286, so the estimate to complete is ETC = EAC − AC = 836.
Crashing shortens the schedule at a price: each activity has a cost slope = (crash cost − normal cost)/(normal duration − crash duration); an activity normally 9 days at 1500 that can be crashed to 6 days at 2400 has slope (2400 − 1500)/(9 − 6) = 300 per day. Crash only critical activities, the cheapest slope first, and re-check, because a second path becomes critical as the first shortens. Resource levelling moves non-critical activities within their float to flatten the demand histogram; it can never use more than the float and so cannot lengthen the project.
A plan is useful only while it is current, so a project is monitored (measure progress against the baseline) and updated (revise the remaining schedule and cost from actual progress). The…
Construction Equipment: Earthwork, Concreting, Hoisting and Transport
| Operation | Equipment | What it is suited to |
|---|---|---|
| Clearing, short push, spreading | Bulldozer (crawler or wheeled) | pushes soil up to about 100 m economically; ripping with a ripper |
| Excavation, loading | Power shovel / hoe (backhoe) / front-end loader | shovel digs above its tracks; backhoe digs below grade (trenches, foundations) |
| Long reach, wet ground | Dragline, clamshell | dragline digs below and far; clamshell for deep vertical shafts |
| Excavate, haul and spread | Scraper | medium hauls of a few hundred metres to a few kilometres |
| Compaction | Smooth-wheel, sheepsfoot, pneumatic and vibratory rollers | sheepsfoot for cohesive soil, vibratory for granular |
| Concrete production and placing | Batching plant, transit mixer, concrete pump, needle vibrator | pump for height or reach; vibrator to remove entrapped air |
| Hoisting | Tower crane, mobile/crawler crane, hoist | tower crane for tall buildings (reach and height), mobile crane for varied sites |
| Material transport | Dumper, tipper, belt conveyor, wheelbarrow, forklift | conveyor for continuous bulk flow; trucks for variable routes |

Operation
Equipment Output: Cycle Time, Swell and Shrinkage
Output = capacity per cycle × cycles per hour × efficiency. A 1.2 m³ bucket with a 20 s cycle makes 3600/20 = 180 cycles/h; with a fill factor of 0.9 and a working efficiency of 50 min/h (0.833), the loose-soil output is 180 × 1.2 × 0.9 × 0.833 = 162.0 m³/h. Soil changes volume between states: bank (in place), loose (excavated, swelled) and compacted (placed, usually shrunk below bank). Swell = (loose − bank)/bank, so loose = bank × (1 + swell); shrinkage = (bank − compacted)/bank, so compacted = bank × (1 − shrinkage). With swell 25%, 162.0 loose m³/h is 129.6 bank m³/h, and one bank m³ becomes 0.90 compacted m³ at 10% shrinkage — which is why a fill needs more bank volume than its finished volume. Trucks are priced by loose volume (what they carry), earthwork pay-items by bank or compacted volume.
Matching haulers to loaders. A truck of 8 m³ loose is loaded by that excavator in 8/162.0 h = 3.0 min. With a haul-dump-return time of 14 min the truck's full cycle is 17.0 min, so the number of trucks that keeps the excavator busy is the cycle over the load time, rounded up: 6 trucks. Too few trucks idle the excavator; too many queue at the loader — and in both cases the output is set by the weaker link, not the stronger. The same arithmetic applies to scrapers and dozers (cycle = load + haul + dump + return + manoeuvre) and to concrete: batching plant output against transit-mixer cycle and pump rate.
- Bank (in place)
- Loose (excavated)Loose = bank × (1 + swell)
- Compacted (placed)Compacted = bank × (1 − shrinkage)
Output = capacity per cycle × cycles per hour × efficiency. A 1.2 m³ bucket with a 20 s cycle makes 3600/20 = 180 cycles/h; with a fill factor of 0.9 and a working efficiency of 50 min/h…
Key takeaways
- AOA draws activities as arrows and needs dummies for dependencies; AON draws them as nodes, needs none and allows SS, FF and FS relations with lags; both give the same critical path.
- Forward pass ES = max predecessor constraint, EF = ES + D; backward pass LF = min successor constraint; total float = LS − ES; the critical path has zero float; floats on a chain are shared.
- Earned value: CV = EV − AC, SV = EV − PV, CPI = EV/AC, SPI = EV/PV (below 1 is bad); EAC = BAC/CPI. Crash the cheapest critical activity first, by cost slope = ΔCost/ΔTime.
- Match machine to geometry: backhoe below grade, shovel above, dragline far reach, clamshell deep shaft, scraper medium haul, dozer short push (up to about 100 m); sheepsfoot for clay, vibratory for sand.
- Output = capacity × cycles/h × efficiency; loose = bank × (1 + swell), compacted = bank × (1 − shrinkage); trucks needed = truck cycle ÷ loading time, rounded up.
Practice questions (24)
Attempt each one before opening the answer. Every explanation names the tempting wrong option as well as the right one, because that is where marks are lost.
Which of the following is true of an activity-on-node (precedence) network?
Show answer
Answer: D — It needs no dummy activities and can express SS and FF relationships with lags
In AON the activities are nodes and arrows are pure precedence, so no dummies arise, and relations other than FS (with lags) are a built-in feature. The critical path is the same as in an equivalent AOA diagram.In the example network (A 3, B 4 after A, C 2 after A, D 5 after B, E 3 after C, F 4 after D and E, G 2 after F), find the project duration in days.
Numerical answer — type the value.
Show answer
Answer: 18
The longest path is A–B–D–F–G = 3 + 4 + 5 + 4 + 2 = 18 days; the other path A–C–E–F–G is 14, so C and E each have 4 days of float.In the same network, the total float of activity C is:
Show answer
Answer: D — 4 days
ES = 3; F cannot start later than day 12, so E must finish by day 12 and start by 9, and C must start by 7; float = LS − ES = 4. E shares the same float: using it up in C leaves E none.
Show the other 21 questions
A project has BAC = 1000, PV = 400, EV = 350 and AC = 450. The project is:
Show answer
Answer: C — over budget and behind schedule
CPI = EV/AC = 0.778 < 1 (over budget) and SPI = EV/PV = 0.875 < 1 (behind schedule). EAC = BAC/CPI = 1286.An activity normally takes 9 days at 1500 and can be crashed to 6 days at 2400. Its cost slope is:
Show answer
Answer: B — 300 per day
Slope = (2400 − 1500)/(9 − 6) = 900/3 = 300 per day. Crash the critical activity with the lowest slope first.Which equipment is best suited to digging a trench below its own ground level?
Show answer
Answer: C — backhoe (hoe)
A backhoe digs by drawing the bucket towards itself below its tracks, which suits trenches and foundations. A power shovel digs above its tracks; a bulldozer pushes soil; a scraper loads, hauls and spreads.Which roller is generally preferred for compacting cohesive (clayey) soils?
Show answer
Answer: C — sheepsfoot roller
The projecting feet of a sheepsfoot roller knead and concentrate pressure in cohesive soil. Vibratory rollers suit granular soils, whose particles rearrange under vibration.An excavator has a 1.2 m³ bucket, a 20 s cycle, a fill factor of 0.9 and works 50 minutes in every hour. Its output of loose soil is nearest to:
Show answer
Answer: D — 162 m³/h
180 cycles/h × 1.2 m³ × 0.9 × (50/60) = 162.0 m³/h. The 216 m³/h option leaves out the fill factor and efficiency, and 180 counts only cycles.Soil swells by 25% on excavation. A loose output of 150 m³/h corresponds to a bank volume of:
Show answer
Answer: D — 120 m³/h
Loose = bank × (1 + swell), so bank = 150/1.25 = 120 m³/h. Multiplying by 1.25 instead gives 187.5, the common reversal.In a network, activity A (3 days) precedes B (4 days) and C (6 days); D (2 days) follows both B and C. The total float of activity B is:
Show answer
Answer: C — 2 days
The longest path A–C–D takes 3 + 6 + 2 = 11 days, whereas A–B–D takes 9 days. B can therefore slip by 11 − 9 = 2 days without delaying the project, which is its total float. Zero would be true only on the critical path, and 4 confuses the duration of B with its float.In an activity-on-arrow (AOA) network, a dummy activity:
Show answer
Answer: B — Takes zero time and uses no resources, and only shows a dependency
Dummies enforce logic or keep two activities from sharing both end events. AON networks need no dummies at all, which rules out the last option; dummies are rarely critical.In earned value management, the cost performance index (CPI) is:
Show answer
Answer: A — EV / AC
CPI compares the value of work done with what it actually cost. EV / PV is the schedule performance index, the usual swap.A bulldozer is best suited to:
Show answer
Answer: C — Pushing earth over short distances, up to about 100 m
A dozer moves soil with its blade economically only over short pushes. Long hauls call for dump trucks, the tempting but uneconomic choice for a dozer.Which machine can excavate, load, haul and spread earth by itself over medium distances?
Show answer
Answer: D — Scraper
The scraper’s bowl cuts, carries and spreads in one cycle. A backhoe digs and loads but does not haul, which makes it the tempting partial answer.Which equipment is primarily used for hoisting materials on a building site?
Show answer
Answer: D — Crane
Cranes lift and place loads vertically and horizontally. A dragline also has a boom and tempts for that reason, but it is an excavator for soft ground below its level.A project has earned value EV = 300 and planned value PV = 400. The schedule performance index is ____.
Numerical answer — type the value.
Show answer
Answer: 0.75
SPI = EV/PV = 0.75, so the work is behind schedule. Inverting the ratio (1.33) would wrongly suggest it is ahead.A project has EV = 300 and AC = 360. Its cost variance (EV − AC) is ____.
Numerical answer — type the value.
Show answer
Answer: -60
CV = 300 − 360 = −60: over budget. Reporting +60 reverses the sign convention, which would read as under budget.A dozer pushes 3 m³ (loose) per cycle with a 1.5-minute cycle and works 50 minutes per hour. Its output, in loose m³ per hour, is ____.
Numerical answer — type the value.
Show answer
Answer: 100
60/1.5 = 40 cycles in a full hour, × 50/60 = 33.3 effective cycles, × 3 m³ = 100 m³/h. Ignoring the 50-minute hour gives 120.1000 m³ of soil measured in the bank is excavated; it swells by 25%. Trucks carry 10 m³ (loose) per trip. The number of truck trips needed is ____.
Numerical answer — type the value.
Show answer
Answer: 125
Loose volume = 1000 × 1.25 = 1250 m³, so 125 trips. Using the bank volume gives 100 trips, the tempting under-count.A project has BAC = 2000, EV = 800 and AC = 1000. Assuming the current cost performance continues, the estimate at completion EAC = BAC/CPI is ____.
Numerical answer — type the value.
Show answer
Answer: 2500
CPI = 800/1000 = 0.8, so EAC = 2000/0.8 = 2500. Adding the overrun so far to BAC (2000 + 200 = 2200) assumes the remaining work will go to plan, which this question does not.A project has BAC = 1000, EV = 400 and AC = 500. The to-complete performance index needed to finish within BAC, (BAC − EV)/(BAC − AC), is ____.
Numerical answer — type the value.
Show answer
Answer: 1.2
600 of work remain with 500 of budget left: TCPI = 1.2, i.e. every rupee must now earn 1.2 rupees of work. The current CPI of 0.8 is the tempting but different figure.An AON network has A (4 days), B (3), C (5, after A), D (2, after A and B), E (6, after C) and F (3, after D); E and F end the project. The total float of activity F, in days, is ____.
Numerical answer — type the value.
Show answer
Answer: 6
The critical path A–C–E takes 15 days. D starts at 4 (after A), so F runs 6–9 and may finish as late as 15: TF = 6. Taking D’s start from B (3) instead of the later of A and B gives 7.An excavator produces 120 m³ of loose soil per hour. Trucks carry 8 m³ each and take 20 minutes for a full cycle (load, haul, dump, return). The minimum number of trucks needed to keep the excavator fully busy is ____.
Numerical answer — type the value.
Show answer
Answer: 5
Each truck moves 8 × 3 = 24 m³ per hour, so 120/24 = 5 trucks. Answering 15 divides 120 by 8, which assumes each truck returns instantly.Which of the following statements about earned value analysis are correct? (More than one may be correct.)
Show answer
Answer: A — Schedule variance is EV − PV; B — SPI > 1 means the project is ahead of schedule; C — CPI < 1 means the work done has cost more than budgeted
The first three are correct. The last is the trap: the budgeted cost of work scheduled is PV; AC is the actual cost of the work performed.