Plant Design and Economics at Working Depth: Cost Indices and Scaling, Depreciation Methods, Discounted Cash Flow, Annualised Cost, Optimum Sizing and Batch Scheduling

Section 9 of the CH paper lists process economics and cost estimation (depreciation, total annualised cost, cost indices, rate of return, payback period, discounted cash flow), optimisation of equipment sizing (heat exchangers, multistage contactors) and batch plant scheduling — and the existing chapter gives the definitions without a single worked cash flow. A 100 m² exchanger at 50 k$ costs 114.9 k$ at 400 m² by the six-tenths rule; a 1 M$ asset with 0.1 M$ salvage depreciates by 90 k$/yr straight-line and 200 k$ in year 1 double-declining; 1000 invested for 300 a year over 5 years has NPV 137.2 at 10% and IRR 15.24%; a cost of aA + b/A is least at 63.2 m²; and a 3-stage batch line with a 6 h bottleneck turns out 5 batches in 37 h.
Overview

Cost Estimation, Cost Indices, Capacity Scaling and Depreciation

2 min read · 3 parts

Updating a cost from year 1 to year 2 uses a cost index: C₂ = C₁(I₂/I₁). A 250 k$ vessel quoted when the index was 500 costs 250 × 650/500 = 325000 $ at an index of 650. Capacity scaling uses the six-tenths rule C₂ = C₁(Q₂/Q₁)ⁿ with n ≈ 0.6: a 100 m² exchanger costing 50 k$ costs 50 × 4^0.6 = 114.9 k$ at 400 m² — a fourfold size at 2.3 times the cost. The two corrections are combined: scale for size, then index for time. Estimate classes run from an order-of-magnitude (ratio) estimate (±30–50%), through a study estimate with factors (Lang factor method, ±25–30%) to a preliminary, a definitive (±10%) and a detailed estimate. In the factored method the fixed capital is the delivered equipment cost times a Lang factor (about 3–5 depending on the plant); total capital adds working capital, commonly 10–20% of the total. Operating cost has direct (raw material, utilities, labour), fixed (depreciation, tax, insurance) and general (administration, R&D) parts.

Depreciation spreads the cost P less salvage S over a life n. Straight line: d = (P − S)/n = (1,000,000 − 100,000)/10 = 90,000 $/yr; the book value after 3 years is 730,000. Declining balance (double): rate 2/n = 0.2 on the opening book value: year 1 = 200,000, year 2 = 160,000. Sum-of-years-digits: factor (n − k + 1)/[n(n + 1)/2] on (P − S): year 1 = 900 000 × 10/55 = 163,636, year 2 = 147,273. The accelerated methods give larger early charges, thus lower early taxable income and a tax deferral. Depreciation is an accounting charge, not a cash outflow: after-tax cash flow = net profit + depreciation. Land and working capital are not depreciated; the tax shield of depreciation is d × tax rate.

MethodYear 1Year 2
Straight line90,00090,000
Double-declining balance200,000160,000
Sum-of-years-digits163,636147,273
Six-tenths scaling, 100 → 400 m²114.9 k$—
Estimate classes, rough to detailed
  1. Order-of-magnitude (ratio)±30–50%
  2. Study estimateLang factor method, ±25–30%
  3. Preliminary
  4. Definitive±10%
  5. Detailed

Updating a cost from year 1 to year 2 uses a cost index: C₂ = C₁(I₂/I₁). A 250 k$ vessel quoted when the index was 500 costs 250 × 650/500 = 325000 $ at an index of 650. Capacity scaling…

Rate of Return, Payback, Discounted Cash Flow and Total Annualised Cost

2 min read · 2 parts

Take an investment of 1000 (any money unit) at t = 0 returning a net cash flow of 300 a year for 5 years, discounted at i = 10%. Payback period = 1000/300 = 3.33 years, which ignores time value and later cash. Discounted payback (cumulative PV reaching 1000) is 4.26 years. The present value of the annuity is 300 × [1 − (1 + i)^(−n)]/i = 300 × 3.7908 = 1137.2, so NPV = 137.2 > 0 and the project is acceptable at 10%. The IRR is the rate that makes NPV zero: [1 − (1 + r)^(−5)]/r = 1000/300 = 3.333 gives r = 15.24%. A simple rate of return divides average annual profit by investment (here an annual profit after depreciation of 200 on 1000 gives ROI = 20%). Ranking mutually exclusive projects by IRR can mislead; NPV at the cost of capital is the sound criterion.

Total annualised cost (TAC) puts capital and operating cost on one yearly basis with the capital recovery factor CRF = i(1 + i)ⁿ/[(1 + i)ⁿ − 1]: for i = 10% and n = 10, CRF = 0.16275, so a capital of 1000 costs 162.75 a year, and TAC = CRF × capital + annual operating cost. Two alternatives with different capital and operating costs are compared on TAC (or on equivalent annual cost when their lives differ). Cost indices (CEPCI, Marshall & Swift) are used for time; inflation raises the nominal rate. Break-even occurs where revenue equals fixed plus variable costs. Cash flows are best tabulated year by year: revenue − operating cost − depreciation = taxable income; tax; net profit; plus depreciation = cash flow.

MeasureValue (1000 invested, 300/yr × 5, i = 10%)
Payback3.33 yr
Discounted payback4.26 yr
NPV137.2
IRR15.24%
Capital recovery factor, 10%, 10 yr0.16275
Building a year's cash flow
  1. Revenue − operating cost − depreciation
  2. Taxable income
  3. Less tax: net profit
  4. Plus depreciation: cash flow

Take an investment of 1000 (any money unit) at t = 0 returning a net cash flow of 300 a year for 5 years, discounted at i = 10%. Payback period = 1000/300 = 3.33 years, which ignores time…

Optimum Sizing: Heat Exchangers, Contactors and Pipes

2 min read · 1 part

Most sizing problems have one cost that rises with size (capital) and one that falls (energy, solvent, utility): the total TAC = aS + b/S has a minimum where the slopes cancel, S* = √(b/a) with TAC_min = 2√(ab) — at the optimum the two costs are equal. Heat exchanger: if annualised capital is a = 50 $/m²·yr and the utility cost, which falls as 1/A for a given duty and approach, is b/A with b = 2.0×10⁵ $·m²/yr: A* = 63.2 m² and TAC_min = 6,325 $/yr, split equally between capital and utility. Multistage contactor (distillation trays, extraction stages, a counter-current absorber): the number of stages N costs aN while the solvent or reflux cost falls like b/N; with a = 50 and b = 8000, N* = 12.6 stages. In practice the minimum is shallow, so designers choose R = 1.2–1.5R_min, an absorber L/G of 1.2–2 times the minimum, and ΔT_min of 10–20 K for exchangers.

Optimum pipe diameter. Capital rises roughly as D^1 to D^1.5 while pumping cost falls steeply (turbulent friction head varies as D^(−4.8)), so there is a minimum-cost diameter; economic velocities of about 1–3 m/s for liquids and 15–30 m/s for gases are the result. Optimum insulation thickness balances insulation cost against heat-loss cost. Reflux ratio trades column cost (stages) against reboiler and condenser duty. Heat-integration uses a minimum approach temperature to trade exchanger area against utility. The calculus is the same each time: write the annualised cost as a function of one variable, differentiate, set dTAC/dS = 0, check it is a minimum.

ProblemOptimum
TAC = aS + b/SS* = √(b/a); TAC_min = 2√(ab)
Exchanger, a = 50, b = 2×10⁵A* = 63.2 m²; 6,325 $/yr
Contactor stages, a = 50, b = 8000N* = 12.6
Reflux ratio1.2 to 1.5 R_min

Most sizing problems have one cost that rises with size (capital) and one that falls (energy, solvent, utility): the total TAC = aS + b/S has a minimum where the slopes cancel, S* = √(b/a)…

Batch Plant Scheduling

2 min read · 1 part

A batch plant makes products in discrete batches through units that are occupied for a processing time. For a single product through three units with times 4, 6 and 3 h, the cycle time (time between batches) is set by the bottleneck unit, 6 h; the first batch needs 4 + 6 + 3 = 13 h, and N batches finish at the makespan 13 + (N − 1) × 6: for N = 5 it is 37 h. Unit utilisations are 4/6 = 0.67, 1.00 and 3/6 = 0.50; the bottleneck unit is the only one fully used, and adding a parallel unit to it (an out-of-phase duplicate) halves its effective time and lowers the cycle time to the next-slowest unit. A Gantt chart shows each unit's occupancy against time; the batch size is limited by the smallest unit capacity, and the production rate is batch size divided by cycle time.

For a multiproduct flow-shop the order matters. Two products through three units with times P1 = (3, 4, 2) h and P2 = (2, 5, 3) h, with unlimited intermediate storage: each unit starts a batch when both it and the batch's previous step are free, so the completion time C(j, s) = max[C(j − 1, s), C(j, s − 1)] + t(j, s). Sequence P1 then P2 has a makespan of 15 h, P2 then P1 of 13 h; the better sequence saves 2 h. With zero-wait or no intermediate storage a batch must pass directly into the next unit, giving longer makespans. Johnson's rule for two stages: schedule first the jobs whose shorter time is on the first machine in ascending order of that time, then the rest in descending order of the second time. Campaign production and shared-unit scheduling are the tools for products of similar recipes.

QuantityValue
Cycle time, units 4, 6, 3 h6 h
Makespan, 5 batches37 h
Utilisation of the three units0.67, 1.00, 0.50
Two-product flow-shop: P1→P2 / P2→P115 h / 13 h
🎯 Two depreciation schedules, side by side
For equipment of ₹100 000 with ₹10 000 salvage and a 5-year life, straight-line depreciation is (100 000 − 10 000)/5 = ₹18 000 every year. Double-declining balance applies twice the straight-line rate, 40%, to the opening book value: ₹40 000 in year 1, then 0.4 × 60 000 = ₹24 000 in year 2, front-loading the deduction and so deferring tax. The book value never falls below the salvage value, and the sum of the depreciation charges over the life equals cost minus salvage.

A batch plant makes products in discrete batches through units that are occupied for a processing time. For a single product through three units with times 4, 6 and 3 h, the cycle time…

Key takeaways

  • Cost index C₂ = C₁(I₂/I₁); six-tenths C₂ = C₁(Q₂/Q₁)^0.6; factored estimate = Lang factor × equipment cost; working capital 10–20%.
  • Straight line (P − S)/n; double declining 2/n of book value; SYD (n − k + 1)/[n(n + 1)/2]; depreciation is not a cash cost and gives a tax shield.
  • Payback = I/CF ignores time value; NPV = ΣCF/(1 + i)^t − I; IRR sets NPV to zero; CRF = i(1 + i)ⁿ/[(1 + i)ⁿ − 1] for TAC.
  • For TAC = aS + b/S the optimum is S* = √(b/a) with equal capital and operating parts; reflux ratio 1.2–1.5R_min, absorber L/G 1.2–2 times minimum.
  • Single-product batch cycle time is the bottleneck time and makespan = Σt + (N − 1) × cycle time; for multiproduct plants the sequence changes the makespan.

Practice questions (24)

Attempt each one before opening the answer. Every explanation names the tempting wrong option as well as the right one, because that is where marks are lost.

  1. A heat exchanger of 100 m² costs 50 k$. By the six-tenths rule the cost of a 400 m² unit in k$ (one decimal) is:

    Numerical answer — type the value.

    Show answer

    Answer: 114.9

    C₂ = 50 × (400/100)^0.6 = 50 × 4^0.6 = 114.9 k$.
  2. An asset costing 1 000 000 $ with a salvage value of 100 000 $ is depreciated over 10 years. The year-1 charge by the sum-of-years-digits method in $ (nearest integer) is:

    Numerical answer — type the value.

    Show answer

    Answer: 163636

    SYD year 1 = (P − S) × 10/55 = 900 000 × 10/55 = 163,636 $; straight line would give 90,000.
  3. Depreciation is best described as:

    1. a non-cash accounting charge that lowers taxable income
    2. a cost that applies to land
    3. a cash outflow each year
    4. an item added to working capital
    Show answer

    Answer: A — a non-cash accounting charge that lowers taxable income

    Depreciation is not paid out; it reduces taxable income and so the tax paid (a tax shield). After-tax cash flow = net profit + depreciation. Land is not depreciated.
Show the other 21 questions
  1. An investment of 1000 returns 300 per year for 5 years; the discount rate is 10%. The net present value (one decimal) is:

    Numerical answer — type the value.

    Show answer

    Answer: 137.2

    PV of the annuity = 300 × 3.7908 = 1137.2; NPV = 1137.2 − 1000 = 137.2.
  2. For the same cash flows, the internal rate of return in percent (two decimals) is:

    Numerical answer — type the value.

    Show answer

    Answer: 15.24

    Solve [1 − (1 + r)^(−5)]/r = 3.3333: r = 15.24%, above the 10% hurdle rate, so NPV > 0.
  3. The capital recovery factor for i = 10% and n = 10 years (five decimals) is:

    Numerical answer — type the value.

    Show answer

    Answer: 0.16275

    CRF = i(1 + i)ⁿ/[(1 + i)ⁿ − 1] = 0.1 × 2.5937/1.5937 = 0.16275.
  4. A heat exchanger has annualised capital cost 50 A $/yr and utility cost 2×10⁵/A $/yr (A in m²). The optimum area in m² (one decimal) is:

    Numerical answer — type the value.

    Show answer

    Answer: 63.2

    d/dA(50A + 2×10⁵/A) = 0 → A* = √(2×10⁵/50) = 63.2 m²; each part then costs 3,162 $/yr.
  5. Three units in series process a single product with times 4, 6 and 3 h. The time to produce 5 batches (no storage limits), in h, is:

    Numerical answer — type the value.

    Show answer

    Answer: 37

    The first batch needs 13 h and each later batch adds the bottleneck time 6 h: 13 + 4 × 6 = 37 h.
  6. Two products with unit times P1 = (3, 4, 2) h and P2 = (2, 5, 3) h pass through three units in the order P1, P2 (unlimited intermediate storage). The makespan in h is:

    Numerical answer — type the value.

    Show answer

    Answer: 15

    Unit 1 ends P1 at 3 and P2 at 5; unit 2 ends P1 at 7 and P2 at 12; unit 3 ends P1 at 9 and P2 at 15; makespan 15 h (reverse order gives 13 h).
  7. Which statements about project economics are correct?

    1. A bottleneck unit has the lowest utilisation
    2. NPV above zero at the cost of capital means the project is acceptable
    3. At the optimum of aS + b/S the two cost terms are unequal
    4. Payback period ignores the time value of money
    Show answer

    Answer: B — NPV above zero at the cost of capital means the project is acceptable; D — Payback period ignores the time value of money

    Simple payback is undiscounted and a positive NPV is the acceptance test. At S* = √(b/a), aS* = b/S*, so the two terms are equal, and the bottleneck is the unit with the highest utilisation.
  8. The purchased equipment cost of a fluid-processing plant is 2 M$. Using a Lang factor of 4.74, the estimated fixed capital investment, in M$ (two decimals), is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 9.48

    FCI = Lang factor × purchased equipment cost = 4.74 × 2 = 9.48 M$. Dividing (0.42) inverts the factor; the Lang factor scales equipment up to the whole installed plant.
  9. A pump bought for 200 k$ when the cost index was 400 is re-estimated at an index of 600. The updated cost, in k$, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 300

    C = 200 × 600/400 = 300 k$. Applying the six-tenths exponent to the index ratio (255 k$) mixes capacity scaling with time escalation.
  10. The discount factor for a cash flow two years ahead at 10 % per year, 1/(1.1)², to four decimals, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 0.8264

    1/1.21 = 0.8264. Using 1 − 2 × 0.1 = 0.8 treats discounting as simple interest and understates present value. Substituting the answer back into the relation confirms it.
  11. A project needing 1500 of capital earns a steady 250 per year. Its simple payback period, in years, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 6

    1500/250 = 6 years. Payback ignores both the time value of money and anything earned after year 6, which is why discounted measures are preferred.
  12. A positive net present value at the company's discount rate means that the project

    1. makes no accounting profit
    2. earns more than the discount rate on the capital tied up
    3. pays back within one year
    4. has an IRR below the discount rate
    Show answer

    Answer: B — earns more than the discount rate on the capital tied up

    NPV > 0 means the discounted inflows exceed the outlay, i.e. the IRR exceeds the discount rate. An IRR below the discount rate would give a negative NPV, the reverse case; NPV says nothing directly about payback time.
  13. One batch passes through three units in series with times 2, 3 and 1 h. The time to complete this single batch, in h, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 6

    A single batch must visit each unit in turn: 2 + 3 + 1 = 6 h. The bottleneck time (3 h) is the cycle time between successive batches, which matters only when batches overlap.
  14. To add a capital investment to annual operating costs in a total annualised cost, the capital is multiplied by

    1. the capital-recovery factor i(1 + i)ⁿ/[(1 + i)ⁿ − 1]
    2. the Lang factor
    3. the compound-amount factor (1 + i)ⁿ
    4. the single-payment present-worth factor 1/(1 + i)ⁿ
    Show answer

    Answer: A — the capital-recovery factor i(1 + i)ⁿ/[(1 + i)ⁿ − 1]

    The CRF converts a present sum into an equal annual series over n years at rate i. The compound-amount factor gives a future value instead, and the Lang factor scales equipment cost to plant cost, not to an annual charge.
  15. An asset of cost 400 with an 8-year life is depreciated by double-declining balance (rate 2/8). The year-1 charge is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 100

    Rate = 2/8 = 25 %, so year 1 = 0.25 × 400 = 100; salvage is not subtracted under declining balance. The straight-line charge, 400/8 = 50, is half of this.
  16. A loan carries 12 % nominal annual interest compounded monthly. The effective annual rate, in per cent (two decimals), is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 12.68

    i_eff = (1 + 0.12/12)¹² − 1 = 1.01¹² − 1 = 12.68 %. Quoting 12.00 % ignores the compounding within the year. Substituting the answer back into the relation confirms it.
  17. A perpetual annual income of 100 is valued at a discount rate of 10 %. Its present value is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 1000

    PV = A/i = 100/0.1 = 1000, the limit of the annuity as n → ∞. Answering infinity treats an endless income as endlessly valuable, ignoring discounting.
  18. The annual cost of a pipeline is C(D) = 1000D + 4000/D³, where the second term is pumping cost. The optimum diameter, in the same units as D (three decimals), is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 1.861

    dC/dD = 1000 − 12 000/D⁴ = 0 gives D = 12^(1/4) = 1.861. Equating the two cost terms (D⁴ = 4, D = 1.414) is a rule of thumb valid only when both terms have the same power of D.
  19. Four identical batches pass through three units in series with times 2, 5 and 3 h (overlapping operation, unlimited storage). The total time to finish all four, in h, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 25

    Makespan = Σt + (N − 1)·t_max = 10 + 3 × 5 = 25 h: after the first batch, one batch emerges per bottleneck cycle. Running batches one after another without overlap would take 4 × 10 = 40 h.
  20. A project costs 1000 and returns 400 at the end of each year. With a 10 % discount rate, the discounted payback period, in years (two decimals, interpolating within the year), is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 3.02

    Discounted inflows: 363.64, 330.58, 300.53 (cumulative 994.74 after 3 years), then 273.21 in year 4, so payback = 3 + 5.26/273.21 = 3.02 years. The simple payback, 2.50 years, ignores discounting.
  21. The total annual cost of a unit is C(x) = 2000x + 50 000/x. The minimum total annual cost is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 20000

    dC/dx = 0 gives x = √(50 000/2000) = 5, so C_min = 10 000 + 10 000 = 20 000 = 2√(ab). Reporting 5 gives the optimum variable, not the minimum cost asked for.