Irrigation, Pumps and Farm Machinery in Numbers: Pump Power and NPSH, Drip Layout and Scheduling, Salinity Leaching, Groundwater Recharge, Tillage Draft, Field Capacity and Sprayer Calibration

Section 5 of the Agricultural Engineering paper names the classification of pumps, planning and layout of surface and micro-irrigation, groundwater recharge estimation and salinity control, and Section 2 names the forces acting on a tillage tool, overload safety devices and spraying; the earlier chapters of both describe them in words. Lifting 50 L/s through 30 m at 65% efficiency needs 22.6 kW at the pump shaft; 4 L/h drippers on 0.5 × 1.0 m spacing apply 8 mm/h; a crop with 0.16 m³/m³ available water, a 0.6 m root zone and 50% allowable depletion needs 48 mm every 8.7 days at 5.5 mm/day; a water table rise of 1.5 m in an aquifer of specific yield 0.08 is 120 mm of recharge; a plough of 0.9 m × 0.2 m at 55 kN/m² draws 9.9 kN; and a boom with 0.8 L/min nozzles every 0.5 m at 4 km/h applies 240 L/ha.
Overview

Pumps: Power, NPSH and Well Yield

1 min read

A pump adds head H to a flow Q: the hydraulic power is ρgQH = 1000 × 9.81 × 0.05 × 30 = 14.71 kW, and the shaft power is that divided by the pump efficiency: 14.71/0.65 = 22.6 kW (the motor needs a further 10–15% margin and its own efficiency). Classification: centrifugal (radial, mixed and axial-flow, by specific speed; for high flow and moderate head), positive-displacement (reciprocating, rotary; for viscous or high-head duty), submersible and vertical turbine (for deep wells) and jet pumps; propeller and mixed-flow pumps serve large flows at low head. Centrifugal pumps follow the affinity laws: Q ∝ N, H ∝ N², P ∝ N³. A pump cannot lift by suction beyond atmospheric pressure, and cavitates if the net positive suction head available falls below the required: NPSHa = (P_atm − P_v)/ρg − h_s − h_f = (101.3 − 3.17) kPa/(9.81 kPa/m) − 3.0 − 0.8 = 6.2 m at 25 °C, to be above NPSHr by a margin of about 0.5–1 m. Well yield (Thiem, confined aquifer): Q = 2πT s/ln(R/r) for transmissivity T = 1.2 × 10⁻³ m²/s, drawdown s = 5 m, radius of influence 300 m, well radius 0.1 m: Q = 4.71 L/s.

QuantityFormulaValue here
Hydraulic powerρgQH14.71 kW
Shaft power at 65%ρgQH/η22.6 kW
NPSH available(P_atm − P_v)/ρg − h_s − h_f6.2 m
Well yield (Thiem)2πTs/ln(R/r)4.71 L/s

A pump adds head H to a flow Q: the hydraulic power is ρgQH = 1000 × 9.81 × 0.05 × 30 = 14.71 kW, and the shaft power is that divided by the pump efficiency: 14.71/0.65 = 22.6 kW (the motor…

Micro-Irrigation Layout, Scheduling and Salinity Control

1 min read

A drip system's application rate is the emitter discharge over the area it serves: 4 L/h from an emitter serving 0.5 m × 1.0 m = 0.5 m² gives 4/0.5 = 8 mm/h. The net irrigation depth is the allowable depletion of the root zone: d_n = (FC − PWP) × D_r × MAD = (0.30 − 0.14) × 600 mm × 0.5 = 48 mm, with FC and PWP as volumetric fractions, root depth D_r and the management allowed depletion MAD. With crop evapotranspiration ET_c = K_c × ET_o = 1.1 × 5 = 5.5 mm/day the irrigation interval is 48/5.5 = 8.7 days; the gross depth at an application efficiency of 70% is 48/0.70 = 68.6 mm, which drips for 68.6/8 = 8.6 h per irrigation. Typical efficiencies: surface 50–60%, sprinkler 70–75%, drip 85–90%. Salinity control: salts left in the root zone by the water must be flushed by a leaching requirement LR = EC_w/(5EC_e − EC_w), where EC_w is the irrigation-water salinity and EC_e the tolerable saturation-extract salinity of the crop: for EC_w = 1.5 and EC_e = 4.0 dS/m, LR = 1.5/(20 − 1.5) = 0.081, so the gross requirement rises to ET_c/(1 − LR) = 5.99 mm/day. Drainage must exist to remove the leachate or the water table rises and salinises the root zone.

QuantityFormulaValue here
Drip application rateq/(S_e S_r)8 mm/h
Net depth(FC − PWP)·D_r·MAD48 mm
Intervald_n/ET_c8.7 d
Leaching requirementEC_w/(5EC_e − EC_w)0.081

A drip system's application rate is the emitter discharge over the area it serves: 4 L/h from an emitter serving 0.5 m × 1.0 m = 0.5 m² gives 4/0.5 = 8 mm/h. The net irrigation depth is the…

Groundwater Recharge Estimation

1 min read

The water-table fluctuation (WTF) method estimates recharge as the specific yield times the rise in water table over the recharge season: R = S_y Δh = 0.08 × 1.5 m = 120 mm, valid when the rise is caused only by recharge and S_y (the volume of water released per unit volume of aquifer drained, about 0.01–0.30 and 0.08 for silty sand) is known. A water balance at the basin scale gives R = P − ET − Q_surface − ΔS_soil; the rainfall-infiltration factor method takes R = f × P (f ≈ 0.10–0.25 for alluvial and hard-rock areas); and artificial recharge (percolation tanks, check dams, recharge wells, spreading basins) augments it. Net draft is the sum of the abstractions, and a block is classified by its stage of development = annual draft/net annual recharge × 100: below 70% safe, 70–90% semi-critical, 90–100% critical, above 100% over-exploited. For a block with a recharge of 120 mm over 1000 ha (1.2 × 10⁷ m³) and a draft of 1.0 × 10⁷ m³, the stage is 83% (semi-critical). Overview: saline intrusion and falling water tables follow persistent over-draft, and recharge estimation by tracers (tritium, chloride) complements the WTF method.

MethodFormulaValue
Water-table fluctuationS_y Δh120 mm
Stage of developmentdraft/recharge × 10083%
Classification70–90%Semi-critical

The water-table fluctuation (WTF) method estimates recharge as the specific yield times the rise in water table over the recharge season: R = S_y Δh = 0.08 × 1.5 m = 120 mm, valid when the…

Tillage Draft, Field Capacity and Sprayer Calibration

2 min read · 1 part

The draft of a tillage tool is the horizontal force component parallel to travel; it is estimated from the specific resistance of the soil: D = K_s × width × depth. For K_s = 55 kN/m² (a medium soil under a mouldboard plough), 0.9 m wide and 0.2 m deep, D = 55 × 0.9 × 0.2 = 9.9 kN. Draft depends on soil type and moisture, depth, speed (a small rise with speed) and tool shape, and the force on a tool is resolved into draft, vertical and side forces. The drawbar power is draft × speed = 9.9 × 1.4 m/s = 13.9 kW; at 55% overall traction efficiency the engine power is 13.9/0.55 = 25.2 kW. Field capacity: C = W S E/10 ha/h with W the implement width in m, S the speed in km/h and E the field efficiency: 2.4 m × 6 km/h × 0.75/10 = 1.08 ha/h (the theoretical capacity is 1.44 ha/h; turning, filling and adjustment lose the rest). Overload safety devices protect the implement and tractor from stones and stumps: shear bolts (cheap, replaced after a break), spring-trip and hydraulic-release mechanisms (reset automatically), and slip clutches on PTO drives. Spraying must be calibrated: the application rate (L/ha) = Q × 600/(S × W) with nozzle discharge Q in L/min, speed S in km/h and nozzle spacing W in m: 0.8 × 600/(4 × 0.5) = 240 L/ha; to halve it either halve the nozzle flow (reduce pressure by a factor of four, since Q ∝ √p) or double the speed.

QuantityFormulaValue here
Plough draftK_s × width × depth9.9 kN
Drawbar powerD × v13.9 kW
Field capacityW S E/101.08 ha/h
Spray rate600 Q/(S W)240 L/ha
🎯 Pump power from head and flow
The hydraulic power is ρgQH and the shaft power divides by pump efficiency: 20 L/s against 30 m at η = 0.6 needs 1000 × 9.81 × 0.02 × 30 / 0.6 = 9.81 kW at the shaft, more at the motor after its own efficiency. Net positive suction head available must exceed that required by the pump, or cavitation begins. A drip system applying 4 L/h per emitter for 5 hours delivers 20 L, which on a plant spacing of 1 m² is a depth of 20 mm.

The draft of a tillage tool is the horizontal force component parallel to travel; it is estimated from the specific resistance of the soil: D = K_s × width × depth. For K_s = 55 kN/m² (a…

Key takeaways

  • Pump shaft power = ρgQH/η; NPSH available must exceed NPSH required; centrifugal affinity laws are Q ∝ N, H ∝ N², P ∝ N³.
  • Net irrigation depth = (FC − PWP) × root depth × MAD; interval = depth/ET_c; gross depth = net/efficiency.
  • Leaching requirement LR = EC_w/(5EC_e − EC_w); gross water = ET_c/(1 − LR); drainage must remove the leachate.
  • Recharge by water-table fluctuation = S_y Δh; stage of development = draft/recharge × 100, safe below 70%.
  • Draft = specific resistance × area of cut; field capacity = WSE/10 ha/h; spray rate = 600Q/(SW) L/ha; shear bolts and trip mechanisms protect against overload.

Practice questions (24)

Attempt each one before opening the answer. Every explanation names the tempting wrong option as well as the right one, because that is where marks are lost.

  1. A pump lifts 0.05 m³/s through a total head of 30 m with an efficiency of 65%. The shaft power in kW (one decimal) is:

    Numerical answer — type the value.

    Show answer

    Answer: 22.6

    ρgQH = 1000 × 9.81 × 0.05 × 30 = 14.7 kW hydraulic; divided by 0.65 gives 22.6 kW. Forgetting the efficiency would understate the demand.
  2. A centrifugal pump's speed is increased by 20%. By the affinity laws its power demand rises by a factor of about:

    1. 2.0
    2. 1.2
    3. 1.44
    4. 1.73, because P ∝ N³
    Show answer

    Answer: D — 1.73, because P ∝ N³

    Flow rises as N (1.2) and head as N² (1.44), so power, flow times head, rises as N³ = 1.2³ = 1.728. A factor of 1.2 is the flow only.
  3. A soil has FC = 0.30 and PWP = 0.14 (volumetric), a root depth of 600 mm and MAD = 50%. The net irrigation depth in mm (nearest integer) is:

    Numerical answer — type the value.

    Show answer

    Answer: 48

    (0.30 − 0.14) × 600 × 0.5 = 48 mm. Using the whole available water (96 mm) ignores the management allowed depletion.
Show the other 21 questions
  1. With a net depth of 48 mm and crop evapotranspiration of 5.5 mm/day, the irrigation interval in days (one decimal) is:

    Numerical answer — type the value.

    Show answer

    Answer: 8.7

    48/5.5 = 8.7 days, so irrigate about every 8 days (the shorter whole number is the safe choice).
  2. For irrigation water of EC_w = 1.5 dS/m and a crop tolerating EC_e = 4.0 dS/m, the leaching requirement LR = EC_w/(5EC_e − EC_w) (three decimals) is:

    Numerical answer — type the value.

    Show answer

    Answer: 0.081

    LR = 1.5/(5 × 4.0 − 1.5) = 1.5/18.5 = 0.081, i.e. about 8% extra water over the crop need.
  3. The water table in an aquifer of specific yield 0.08 rises by 1.5 m during the monsoon. By the water-table fluctuation method the recharge in mm is:

    Numerical answer — type the value.

    Show answer

    Answer: 120

    R = S_y × Δh = 0.08 × 1500 mm = 120 mm. The specific yield, not the porosity, is the right storage coefficient for an unconfined aquifer.
  4. A mouldboard plough 0.9 m wide cuts 0.2 m deep with specific resistance 55 kN/m². The draft in kN (one decimal) is:

    Numerical answer — type the value.

    Show answer

    Answer: 9.9

    D = 55 × 0.9 × 0.2 = 9.9 kN. Doubling the depth doubles the draft, but doubling the speed raises it only slightly.
  5. An implement of width 2.4 m travels at 6 km/h with a field efficiency of 75%. The effective field capacity in ha/h (two decimals) is:

    Numerical answer — type the value.

    Show answer

    Answer: 1.08

    C = W S E/10 = 2.4 × 6 × 0.75/10 = 1.08 ha/h; the theoretical capacity is 1.44 ha/h.
  6. A boom has 0.8 L/min nozzles every 0.5 m and travels at 4 km/h. The application rate in L/ha (nearest integer) is:

    Numerical answer — type the value.

    Show answer

    Answer: 240

    Rate = 600 Q/(S W) = 600 × 0.8/(4 × 0.5) = 240 L/ha. Because Q ∝ √pressure, halving the rate by pressure alone needs a four-fold pressure reduction.
  7. Which statements are correct?

    1. Specific yield is always larger than porosity
    2. Drip irrigation typically reaches 85–90% application efficiency, higher than surface methods
    3. Shear bolts protect an implement from overload by breaking at a set load
    4. Stage of development above 100% means the block is over-exploited
    Show answer

    Answer: B — Drip irrigation typically reaches 85–90% application efficiency, higher than surface methods; C — Shear bolts protect an implement from overload by breaking at a set load; D — Stage of development above 100% means the block is over-exploited

    Specific yield is the drainable fraction of the pores, so it is always smaller than porosity. The other three are standard.
  8. In a drip irrigation system, an emitter’s main function is to

    1. dissipate pressure and deliver water at a slow, controlled rate
    2. pump the water
    3. filter the water
    4. measure soil moisture
    Show answer

    Answer: A — dissipate pressure and deliver water at a slow, controlled rate

    An emitter drops the line pressure to deliver a few litres per hour to each plant. Filtering and pumping are done by filters and pumps, the tempting other components.
  9. Primary tillage of a field is done mainly to

    1. cut, loosen and invert the soil to a substantial depth
    2. apply fertiliser
    3. harvest the crop
    4. level the surface for sowing only
    Show answer

    Answer: A — cut, loosen and invert the soil to a substantial depth

    Primary tillage (e.g. mouldboard ploughing) breaks and inverts soil deeply. Fine levelling and seedbed preparation are secondary tillage, the tempting later operation.
  10. Artificial groundwater recharge through a percolation tank works by

    1. evaporating water faster
    2. pumping water out of the aquifer
    3. sealing the soil surface
    4. storing surface runoff so it slowly infiltrates to the aquifer
    Show answer

    Answer: D — storing surface runoff so it slowly infiltrates to the aquifer

    A percolation tank holds runoff so it seeps down and recharges the aquifer. Pumping out or sealing the surface would deplete or prevent recharge, the tempting opposites.
  11. The emission uniformity of a drip system is reduced most by

    1. short laterals
    2. a pressure regulator
    3. using clean water
    4. emitter clogging and pressure variation along the laterals
    Show answer

    Answer: D — emitter clogging and pressure variation along the laterals

    Clogging and pressure drop along long laterals make emitter flows unequal, lowering uniformity. Clean water, short laterals and regulators all improve uniformity, the tempting reversed options.
  12. A pump delivers 0.02 m³/s to a head of 15 m (ρ = 1000, g = 9.81). The hydraulic power, in kW (two decimals), is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 2.94

    P = ρgQH = 1000 × 9.81 × 0.02 × 15 = 2943 W = 2.94 kW. Omitting g gives 0.3, a dimensionally wrong figure. Substituting the answer back into the relation confirms it.
  13. A drip emitter discharges 4 L/h and serves a plant on a 1.5 m × 1.5 m spacing. The application rate over that area, in mm/h (three decimals), is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 1.778

    Rate = (4 L/h)/(2.25 m²) = 4/2.25 = 1.778 mm/h (1 L/m² = 1 mm). Dividing by the spacing length (1.5) instead of the area understates it.
  14. For a hydraulic power of 2.94 kW and a pump-plus-motor efficiency of 75%, the electrical input power, in kW (two decimals), is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 3.92

    Input = 2.94/0.75 = 3.92 kW. Multiplying by 0.75 (2.21 kW) would give less than the hydraulic power, which is impossible.
  15. A tractor’s theoretical speed is 10 km/h but its actual speed is 8 km/h. The wheel slip, in %, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 20

    Slip = (1 − actual/theoretical) × 100 = (1 − 0.8) × 100 = 20%. Using actual/theoretical = 80% reports traction efficiency, not slip.
  16. A 5-hectare percolation tank infiltrates water at an average rate of 0.1 m/day over its bed. The daily recharge volume, in m³, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 5000

    Volume = area × rate = (5 × 10⁴ m²) × 0.1 m/day = 5000 m³/day. Using 5 (ha) directly without converting to m² understates the volume 10⁴-fold.
  17. A recharge of 5000 m³/day enters an aquifer of specific yield 0.2 under a 1-hectare area. The daily rise in water table, in m (one decimal), is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 2.5

    Rise = recharge/(area × S_y) = 5000/(10⁴ × 0.2) = 2.5 m. Dividing only by area (0.5 m) forgets that only the drainable pore space fills, so the true rise is larger.
  18. A pump runs at 1450 rpm, delivers 0.05 m³/s at a head of 20 m. Its specific speed N_s = N√Q/H^0.75 (SI), to one decimal, is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 34.3

    N_s = 1450 × √0.05/20^0.75 = 1450 × 0.2236/9.457 = 34.3. Using H instead of H^0.75 in the denominator changes the result substantially.
  19. A drip system applies 1.778 mm/h and a crop needs a net depth of 5 mm per irrigation. The operating time per irrigation, in hours (two decimals), is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 2.81

    Time = depth/rate = 5/1.778 = 2.81 h. Multiplying (5 × 1.778 = 8.9) is dimensionally wrong for a time. Substituting the answer back into the relation confirms it.
  20. A tiller of effective width 1.8 m works at 5 km/h with a field efficiency of 80%. Its effective field capacity, in ha/h (two decimals), is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 0.72

    EFC = (W × S/10) × η = (1.8 × 5/10) × 0.8 = 0.9 × 0.8 = 0.72 ha/h (the /10 converts m·km/h to ha/h). Omitting the 80% efficiency gives the theoretical 0.9 ha/h.
  21. A drip system on 10 hectares has one 4 L/h emitter per plant at a 1.5 m × 1.5 m spacing. The total system discharge, in m³/h (one decimal), is ____.

    Numerical answer — type the value.

    Show answer

    Answer: 177.8

    Plants = 10×10⁴/(1.5×1.5) = 44 444; total = 44 444 × 4 L/h = 177 778 L/h = 177.8 m³/h. Dividing the area by the spacing length (not the area) overcounts emitters by 1.5×.